TODD'S WEB SITE
Work Logs Found: 484
Category Work Time: 734 Hours
 Date
Hours
Work Log Summary

Details

 05-03-2015
1.00
First flight!
Details
       

 04-30-2015
1.00
Airworthiness Certificate!
Details
       

 03-15-2015
1.00
First Engine Start!
Details

 03-07-2015
1.00
Pre-Certification Condition Inspection
Details

 12-09-2014
1.00
N-numbers and data plate
Details
       

 12-08-2014
1.00
Pitot-static and transponder inspections
Details

 12-06-2014
1.00
Panel Fired up
Details
       

 12-03-2014
1.00
Finishing panel wiring
Details
       

 12-02-2014
1.00
Exhaust
Details
       

 12-01-2014
1.00
FWF wrap-up
Details
       

 11-29-2014
1.00
Brake bleeding
Details
       

 10-04-2014
1.00
Door install
Details
       

 09-02-2013
1.00
Exhaust headers
Details
       

 09-02-2013
1.00
Completed oil acess door
Details
       

 08-02-2013
1.00
Completing the air scoop
Details
       

 07-29-2013
1.00
Baffe seal templates and install
Details
       

 07-14-2013
1.00
Baffles, cont.
Details
       

 07-10-2013
1.00
Air Scoop extension
Details
       

 07-08-2013
1.00
Red Cube fuel flow transducer
Details
       

 07-07-2013
1.00
Match drilled the emp fairing
Details
       

 07-03-2013
1.00
Mounting filter tabs to FAB top
Details
       

 07-01-2013
1.00
Initial oil access door fitting
Details
       

 06-30-2013
1.00
Establishing FAB alignment
Details
       

 06-27-2013
1.00
Fitting the baffles
Details
       

 06-26-2013
1.00
Cutting out the hole for the oil filler door
Details
       

 06-15-2013
1.00
Connecting throttle & mixture cables
Details
       

 06-07-2013
1.00
Fabricating a new baffle bracket
Details
       

 06-04-2013
1.00
Installing the camloc support strips
Details
       

 06-03-2013
1.00
Matching camloc support strips
Details
     

 06-03-2013
1.00
Baffle assembly
Details
       

 06-02-2013
1.00
Lower Cowl Vent Slots
Details
     

 05-25-2013
1.00
Drilling/riveting the horizontal support strips
Details
       

 05-18-2013
1.00
Trimming inlets
Details
       

 05-18-2013
1.00
Lower Cowl
Details
       

 05-11-2013
1.00
Top cowl inlet ramps
Details
       

 05-10-2013
1.00
Cutting the slot in the lower cowl
Details
       

 05-06-2013
1.00
Fitting the top cowl, continued
Details
       

 05-05-2013
1.00
Fitting the top cowl
Details
       

 05-04-2013
1.00
Cowl inlet trimming
Details
     

 04-27-2013
1.00
Prop hanging, continued
Details
       

 04-26-2013
1.00
Prop hanging
Details
       

 04-16-2013
1.00
Spinner cutouts
Details
     

 04-15-2013
1.00
Spinner backplate
Details
       

 03-16-2013
1.00
Pitch trim servo
Details
       

 03-10-2013
1.00
Starter install
Details
     

 02-13-2013
1.00
Final wing install
Details
       

 02-12-2013
1.00
Initial wing install
Details
       

 02-11-2013
1.00
Prop governor
Details
       

 02-09-2013
1.00
Primary Alternator install
Details
       

 01-25-2013
1.00
VOR/LOC Antenna
Details
       

 12-15-2012
1.00
Standby alternator install
Details
       

 11-17-2012
1.00
Moving to the Airport, cont.
Details
       

 11-17-2012
1.00
Moving to the airport
Details
       

 11-13-2012
1.00
Windscreen install
Details
       

 11-12-2012
1.00
Rear window install
Details
       

 11-11-2012
1.00
Door window install
Details
       

 10-21-2012
1.00
Hanging the engine, cont.
Details
       

 10-21-2012
1.00
Hanging the engine
Details
       

 10-17-2012
1.00
Finishing the latch mechanism
Details
       

 10-16-2012
1.00
Installing center latch
Details
       

 10-15-2012
1.00
Center latch, cont.
Details
       

 10-14-2012
1.00
Center latch
Details
       

 10-13-2012
1.00
Door pin guides. cont.
Details
       

 10-12-2012
1.00
Door pin guides
Details
       

 10-11-2012
1.00
Latch pocket and pointers
Details
       

 10-10-2012
1.00
Door racks and rods
Details
       

 10-09-2012
1.00
Fitting the doors, cont.
Details
       

 10-08-2012
1.00
Fitting the doors to the fuse
Details
       

 10-01-2012
1.00
My prop arrives
Details
       

 09-22-2012
1.00
Door trimming
Details
       

 09-21-2012
1.00
Glueing the doors together
Details
       

 09-20-2012
1.00
Drilling door halves to each other
Details
       

 09-19-2012
1.00
Rough trimming door & window cutouts
Details
       

 09-08-2012
1.00
Nosegear install
Details
       

 09-04-2012
1.00
Canopy install
Details
       

 09-02-2012
1.00
ELT and aft fuse block
Details
       

 08-29-2012
1.00
Battery, GPP, and contactor install
Details
       

 08-28-2012
1.00
Installing copper tape groundplane
Details
       

 08-25-2012
1.00
Installing the canopy headliner
Details
       

 08-22-2012
1.00
Painting the OHC
Details
       

 08-14-2012
1.00
Fitting the windscreen
Details
       

 08-13-2012
1.00
Creating eyeball vent mount brackets
Details
       

 08-12-2012
1.00
Drilling the canopy brace
Details
       

 08-11-2012
1.00
Drilling the canopy to the fuse
Details
       

 08-05-2012
1.00
GPS antenna mounts
Details
       

 07-08-2012
1.00
More OHC fairing, filling, & sanding
Details
       

 07-03-2012
1.00
Avionics test fit
Details
       

 07-02-2012
1.00
Riveting radio stack supports
Details
       

 07-01-2012
1.00
Drilling panel radio stack supports
Details
       

 06-30-2012
1.00
Fairing in the OHC to the canopy
Details
       

 06-09-2012
1.00
OHC Install
Details
       

 06-08-2012
1.00
OHC wiring
Details
       

 06-06-2012
1.00
Brake caliper install
Details
     

 05-23-2012
1.00
Making the air manifold
Details
       

 05-21-2012
1.00
Air manifold, cont.
Details
       

 05-20-2012
1.00
OHC coat hanger rod install
Details
       

 05-20-2012
1.00
OHC Air duct manifold
Details
       

 05-20-2012
1.00
More work on the OHC
Details
       

 05-19-2012
1.00
OHC Eyeball vent, reading light & switch holes
Details
       

 05-16-2012
1.00
OHC air ducting
Details
       

 05-12-2012
1.00
Transponder antenna
Details
       

 05-11-2012
1.00
More tailcone items
Details
       

 05-06-2012
1.00
Ground Power Point
Details
       

 05-05-2012
1.00
Cabin Top
Details
       

 04-26-2012
1.00
Cabin Doors
Details
       

 04-24-2012
1.00
Instrument Panel #2
Details

 04-21-2012
1.00
NACA vents
Details
       

 04-14-2012
1.00
Instrument Panel #1
Details

 03-24-2012
1.00
Floors and cover panels
Details

 03-23-2012
1.00
Engine mount and landing gear
Details
       

 01-22-2012
1.00
Rear Seat backs
Details

 01-19-2012
1.00
Upper Forward fuse install
Details

 01-09-2012
1.00
Flap system
Details
       

 01-07-2012
1.00
Control System
Details

 01-02-2012
1.00
Brake lines
Details

 12-31-2011
1.00
Brakes
Details
     

 11-19-2011
1.00
Fuel Lines
Details
       

 10-30-2011
1.00
Baggage door
Details

 10-23-2011
1.00
Baggage Area
Details

 10-02-2011
1.00
Upper Forward Fuse
Details

 09-25-2011
1.00
Mating the tailcone to the fuse
Details

 09-10-2011
1.00
Step Install
Details
       

 08-04-2011
1.00
Began riveting the right side mid skin
       

 08-03-2011
1.00
Riveting baggage floor support angles
       

 08-03-2011
1.00
Clecoed fuse side skins in-place
       

 08-01-2011
1.00
Riveting upper and lower fuse channels
Details
       

 07-23-2011
1.00
Primed side skins, longerons, and channels
Details

 07-21-2011
1.00
Cutting out the baqgage door
Details
       

 06-30-2011
1.00
Fwd side skins removed
Details
       

 06-29-2011
1.00
Drilling the fuse forward side skins
Details
       

 06-28-2011
1.00
Drilling fuse mid side skins, cont.
Details
       

 06-27-2011
1.00
Drilling fuse mid side skins
Details
       

 06-24-2011
1.00
Install of comm antenna doublers
Details
       

 06-23-2011
1.00
Fab comm antenna doublers
Details
       

 06-22-2011
1.00
Drilling the mid-cabin decks
Details
       

 06-20-2011
1.00
Baggage door seal angles
Details
       

 06-19-2011
1.00
Checking the side skin bends
Details
       

 06-19-2011
1.00
Bending the mid fuse side skins
Details
       

 06-18-2011
1.00
Cutting and bending the longerons
Details

 06-17-2011
1.00
Drilling landing gear weldment braces
Details
       

 06-16-2011
1.00
Mid seat rail supports
Details
     

 06-12-2011
1.00
Side channels, seat supports, cntrl col
Details
       

 06-11-2011
1.00
Permanently mating fuse assemblies
Details
       

 06-09-2011
1.00
Seat floor covers and heater boxes
Details
       

 06-05-2011
1.00
Completed forward fuse subassembly
Details
       

 06-04-2011
1.00
Riveting the firewall assembly
Details
       

 06-03-2011
1.00
Riveting forward floor ribs, cont.
Details
       

 05-30-2011
1.00
Riveting forward floor ribs
Details
       

 05-29-2011
1.00
Fab'd boost pump & filter mounts, cont.
Details
       

 05-29-2011
1.00
Fab'd boost pump & filter mounts
Details
       

 05-23-2011
1.00
Priming forward fuse parts
Details
     

 05-12-2011
1.00
Match drilling, cont.
Details
       

 05-05-2011
1.00
Mating mid and forward fuse assemblies
Details
       

 05-01-2011
1.00
Drilling forward fuse components
Details
       

 04-26-2011
1.00
Completed riveting the firewall
Details
       

 04-25-2011
1.00
Riveting the Firewall
Details
       

 04-24-2011
1.00
Forward fuse floor ribs
Details
       

 04-23-2011
1.00
Match drilling the seat supports/contrl mnts
Details
       

 04-22-2011
1.00
Fab'ing the control column mounts
Details
       

 04-21-2011
1.00
Attach angles and forward seat rail support
Details
       

 04-17-2011
1.00
Finishing the pass-throughs, firewall dimpling
Details
       

 04-17-2011
1.00
Control Cable pass-throughs
Details
       

 04-16-2011
1.00
Supplemental tunnel access panel
Details
       

 04-07-2011
1.00
SCAT tube support and parking brake
Details
       

 04-06-2011
1.00
Match drilling the firewwall
Details
       

 03-06-2011
1.00
Riveting bottom skins on
Details
       

 02-27-2011
1.00
Floor stiffeners and dimpling skins
Details
       

 02-23-2011
1.00
Riveting the step brackets
Details
       

 02-23-2011
1.00
Mid-fuse bottom skins
Details
       

 02-21-2011
1.00
Riveting rear seat ribs in-place
Details
       

 02-21-2011
1.00
Baggage ribs and step brackets
Details
       

 02-20-2011
1.00
Match drilling outboard seat ribs
Details
       

 02-20-2011
1.00
Drilling rear seat ribs
Details
       

 02-17-2011
1.00
Riveting flap actuator bracket
Details
       

 02-16-2011
1.00
Rear seat rib intercostals and seat ribs
Details
       

 02-16-2011
1.00
Outboard/inboard seat assemblies
Details
       

 02-15-2011
1.00
Rear seat ribs, cont.
Details
       

 02-13-2011
1.00
Rear seat rib assemblies
Details
       

 02-11-2011
1.00
Riveting fuselage bulkhead components
Details
       

 02-10-2011
1.00
Drilling rear spar attach bar
Details
       

 02-09-2011
1.00
Drilling the fuse bulkhead assembly
Details
       

 02-07-2011
1.00
Drilling, priming, & riveting of upright bars
Details
       

 02-06-2011
1.00
Riveting aft seat rail supports
Details
       

 02-01-2011
1.00
Modifing the Hat stiffeners
Details
       

 01-31-2011
1.00
Riveting fwd center section blkhd parts
Details
       

 01-31-2011
1.00
Drilling lng gear & riveting seat rail supports
Details
       

 01-30-2011
1.00
Drilling the landing gear weldments
Details
       

 01-29-2011
1.00
Match drilling seat rail supports/bulkheads
Details
       

 01-28-2011
1.00
Locating mid-fuse bulkhead parts
Details
     

 01-28-2011
1.00
Fab'd stiffener angles
Details
       

 01-27-2011
1.00
Riveting ail trim attach brackets
Details
       

 01-26-2011
1.00
Aileron trim to push rod attch brackets
Details
       

 01-25-2011
1.00
Riveting the aileron trim assembly
Details
       

 01-25-2011
1.00
Aileron trim servo install
Details
       

 01-24-2011
1.00
Priming aileron trim links
Details
       

 01-22-2011
1.00
Gretz Pitot attach
Details
       

 01-21-2011
1.00
Aileron torque tube assembly
Details
       

 01-20-2011
1.00
Drilling the aileron torque tubes
Details
       

 01-19-2011
1.00
Cutting the torque tubes
Details
       

 01-17-2011
1.00
Finished riveting wing bottom skins
Details
       

 01-15-2011
1.00
Priming aileron push rod exteriors
Details
       

 01-14-2011
1.00
Riveting rod ends on aileron push rods
Details
       

 01-13-2011
1.00
Priming the inside of the push rods
Details
       

 01-12-2011
1.00
Dilling the rod ends, cont.
Details
       

 01-11-2011
1.00
Drilling the rod ends
Details
       

 01-08-2011
1.00
Double flush riveting the flap trailing edges
Details
       

 01-04-2011
1.00
Riveting flap leading edges, bottom skins
Details
       

 01-02-2011
1.00
Wing and flap close-out inspections
Details

 01-01-2011
1.00
Riveting flap top skins
       

 12-31-2010
1.00
Riveting flap top skins, cont.
       

 12-31-2010
1.00
Riveting flap skins
       

 12-31-2010
1.00
Flap riveting, cont.
       

 12-27-2010
1.00
Riveting flap nose ribs/hinge brackets, cont.
       

 12-27-2010
1.00
Riveting flap nose ribs
       

 12-24-2010
1.00
Dimpling, cont., riveting nose ribs/hinge brackets
       

 12-21-2010
1.00
Dimpling flap skins
Details
       

 12-18-2010
1.00
Prepping flaps for riveting
Details
       

 12-18-2010
1.00
Flap lightening holes and dimpling
Details
       

 12-16-2010
1.00
Drilling the flap components, cont.
Details
       

 12-15-2010
1.00
Drilling the flap components, cont.
Details
       

 12-14-2010
1.00
Drilling the flap components
Details
       

 11-02-2010
1.00
Ailerons

 11-01-2010
1.00
Fuel tanks
Details

 10-31-2010
1.00
Fuel tank close-out inspection
Details

 06-01-2010
1.00
Wing leading edge close-out inspections
Details

 05-30-2010
1.00
Match drilling the leading edge ribs
Details
       

 05-28-2010
1.00
Riveting the ailreon brackets
Details
 

 05-23-2010
1.00
Drilling the leading edges
Details
       

 05-14-2010
1.00
Riveting left top skins
Details
       

 05-13-2010
1.00
Deburring attach Zee's
Details
       

 05-08-2010
1.00
Riveting top skins, cont.
Details
       

 05-06-2010
1.00
Dimpling leading edge splice strips
Details
       

 04-26-2010
1.00
Installed wiring conduit in right wing
Details
       

 04-25-2010
1.00
Finished drilling left ribs, stiffener & skin
Details
       

 04-25-2010
1.00
Clecoed left wing top skins on
Details
       

 04-24-2010
1.00
Drilling left leading edge assembly, cont.
Details
       

 04-23-2010
1.00
Drilling left leading edge assembly
Details
       

 04-19-2010
1.00
Completed riveting right top skins
Details
       

 04-18-2010
1.00
Riveting top right wing skins
Details
       

 04-17-2010
1.00
Cut attch zee's and tank stiffeners
Details
       

 04-07-2010
1.00
Riveting in-board top skin
Details
       

 03-31-2010
1.00
Assembled LE cradle
Details
       

 03-28-2010
1.00
Cut out parts for LE cradle
Details
       

 03-27-2010
1.00
Primed faying surfaces, LE Ribs
Details
       

 03-27-2010
1.00
Completed scarf joints and dimpling
Details
       

 03-24-2010
1.00
Left wing skin dimpling
Details
       

 03-18-2010
1.00
Dimpling the outboard skin
Details
     

 03-11-2010
1.00
Dimpling in-board skin and stiffeners
Details
       

 03-08-2010
1.00
Creating scarf joint and dimpling
Details
       

 03-07-2010
1.00
Countersinking screw s& rivet hole
Details
       

 03-06-2010
1.00
Top skin drilling complete
Details
       

 03-05-2010
1.00
Match drilling right top skins, cont.
Details
       

 03-04-2010
1.00
Match drilling right top skins
Details
       

 03-02-2010
1.00
Removed plastic from rivet lines
Details
       

 02-28-2010
1.00
Riveting the rear spar, cont.
Details
       

 02-27-2010
1.00
Finshed riveting doublers
Details
       

 02-26-2010
1.00
Riveting on right rear spar
Details
       

 02-15-2010
1.00
Finishing up some replacement parts
Details
       

 02-13-2010
1.00
Deburring rear spar doublers
Details
       

 02-12-2010
1.00
Clecoed rear spar to ribs
Details
     

 02-11-2010
1.00
Completing aileron brackets
Details
       

 02-10-2010
1.00
Aileron hinge brackets & doublers
Details
       

 02-09-2010
1.00
Riveted & bolted ribs to right spar
Details
       

 02-07-2010
2.00
Primed ribs and torque tube parts
Details
       

 02-06-2010
2.00
Deburred ribs & torque tube components
Details

 02-05-2010
3.00
Matched drilled right ribs to right spar
Details
     

 02-04-2010
1.00
Match drilled flap hinge brackets
Details

 02-03-2010
2.00
Finshed bolting on left ribs
Details
       

 02-02-2010
1.00
Re-riveted the inboard rib
Details

 02-01-2010
1.00
Started completion of attaching ribs
Details
       

 01-31-2010
6.00
Riveted left wing ribs to spar
Details
       

 01-30-2010
6.00
Prepped and primed left ribs
Details
       

 01-29-2010
2.00
More rib deburring
Details

 01-28-2010
1.00
Rib deburring
Details
       

 01-27-2010
1.50
Enlarged tooling holes for pitot & conduit
Details
       

 01-26-2010
2.00
Matched drilled left wing ribs and spar
Details
       

 01-25-2010
1.50
Drilled flap hinge brackets
Details
       

 01-24-2010
6.00
Finished fluting ribs, assembled torque tube brack
Details
       

 01-23-2010
4.00
Primed screw holes
Details
       

 01-23-2010
2.00
Fluted/straightened all the ribs
Details

 01-21-2010
2.00
Attached tiedowns and misc nutplates
Details
       

 01-20-2010
2.00
CSK'd screw holes
Details
     

 01-19-2010
6.00
Riveted on nutplates
Details
     

 01-17-2010
6.00
Countersinking rivet holes
Details
       

 01-14-2010
2.00
Match drilled j-stiffeners
Details
       

 01-12-2010
2.00
Cut j-stiffeners to length
Details
     

 01-11-2010
2.00
Fab'd tiedown brackets
Details
       

 01-10-2010
2.00
Riveted on wing spar extensions
Details
       

 01-09-2010
3.00
Prepped/primed splice plates & spar extensions
Details
     

 01-08-2010
1.00
Match drilling spar extensions
Details
       

 01-06-2010
4.00
Inventory
Details
       

 01-04-2010
1.00
Wing Kit arrives
Details
       

 01-04-2010
2.00
Bottom rudder fairing
Details
       

 10-09-2009
1.50
Added interior layups to the HS fairings
Details

 10-06-2009
2.00
Added micro fillets
Details
       

 10-05-2009
2.00
Fitting and glassing in the foam ribs
Details
     

 10-04-2009
2.00
Initial fitting of HS/Elevator fairings
Details
       

 10-03-2009
2.00
Final sanding of VS and rudder fairings
Details
       

 09-07-2009
3.00
Sanding the VS fairing to shape
Details
       

 08-30-2009
2.00
Adding micro to the VS fairing
Details
       

 08-23-2009
6.00
Fitting VS fairing
Details
       

 02-12-2009
3.00
Added micro fillets, finshed closing off aft side
Details

 02-09-2009
2.00
Glassed in the temp rib
Details

 02-08-2009
6.00
Temp foam rib for the VS fairing
Details
       

 10-22-2008
3.00
Sanding the top rudder fairing
Details
       

 10-17-2008
4.00
Match drilled top rudder fairing
Details
       

 10-10-2008
2.00
Fitting rudder top fairing
Details
       

 09-15-2008
1.00
Rudder adjust & elevator pushrod install
Details
       

 09-14-2008
4.00
Attached HS, Elevators, VS, and rudder
Details
       

 09-12-2008
2.00
Match drilling the elevator horns
Details
       

 09-11-2008
2.00
HS mounted to work table
Details
       

 09-10-2008
1.00
Elevator push rod assembly
Details
       

 09-09-2008
2.00
Primed the elevator push rod and rod ends
Details
       

 09-07-2008
1.00
Push rod priming prep
Details

 09-06-2008
2.00
Drilling the elevator push rods
Details
       

 09-05-2008
2.00
Elevator push rod fabrication
Details

 09-03-2008
2.00
Assembled trim tab servo components
Details
       

 09-02-2008
1.50
Drilled and CSK'd servo spacer
Details
     

 08-30-2008
0.50
Drilled servo link and bell brank
Details
     

 08-29-2008
3.00
Fabricated trim cable and bellcrank brackets
Details
       

 08-24-2008
3.00
Riveted on aft top skin
Details
       

 08-23-2008
2.00
Rear deck finished
Details
       

 08-22-2008
2.00
Riveting the rear deck, continued
Details
       

 08-20-2008
2.00
Riveting the rear deck and associated parts
Details
       

 08-19-2008
3.00
Tailcone riveting, continued
Details
       

 08-16-2008
1.50
Installed bell crank, more tailcone riveting
Details
       

 08-15-2008
4.00
Began partner riveting
Details
       

 08-13-2008
2.50
Riveted bellcrank ribs together
Details
       

 08-12-2008
3.00
Begain riveting the tailcone
Details
       

 08-11-2008
3.50
Began tailcone assembly
Details
       

 08-10-2008
4.00
Primed the stiffeners, longerons, and skins
Details

 08-09-2008
4.00
More priming prep
Details

 07-13-2008
3.00
Riveted frames together
Details
       

 07-10-2008
0.75
Riveted elevator bellcrank
Details
       

 07-08-2008
8.00
Pirmed interior parts
Details
     

 06-29-2008
0.50
Initial work on SB 06-08
Details
       

 05-18-2008
1.00
Finished the VOR antenna doubler
Details
       

 05-17-2008
1.00
Began building a doubler for the VOR antenna
Details
       

 05-13-2008
1.00
All skins deburred and dimpled
Details

 05-10-2008
0.75
And the deburring and dimpling continues
Details

 05-08-2008
2.00
Finished the right skin, deburred/dimpled the left
Details
       

 05-04-2008
3.50
Finished edge deburring skins, on to holes
Details
       

 05-03-2008
2.50
Deburring complete except skins, dimpling
Details
       

 04-27-2008
4.00
Deburring, continued
Details

 04-19-2008
2.00
Disassembled the tailcone, began deburring
Details
       

 04-18-2008
0.50
Final drilled seat belt anchors, cover plates
Details
       

 04-15-2008
2.00
Misc drilling and fabrication while awaiting drill
Details
       

 04-14-2008
1.00
Drilled aft deck to longerons
Details
       

 04-13-2008
3.00
Attached and drilled top skins
Details
       

 04-09-2008
1.00
Fabricated HS attachment bar support angle
Details
       

 04-07-2008
0.50
Drilled static ports, fab'd up elevator stop
Details
       

 04-06-2008
1.00
Attached F-1075 top skin to frame
Details
       

 04-05-2008
4.50
Drilled the longerons and skins to frames
Details
       

 04-04-2008
0.50
Rebent the left longeron
Details

 04-03-2008
1.00
Attached longerons, spacer, and aft deck
Details
       

 04-02-2008
0.30
Fabricated F-1010B spacer
Details
       

 04-01-2008
2.00
Final drilled & CSK'd bell crank angle
Details
       

 03-31-2008
2.00
Leveled tailcone and drilled rudder stop brace
Details
       

 03-30-2008
0.00
Initial Tech counselor visit
Details

 02-23-2008
3.00
Finished match drilling right-side stiffeners
Details
       

 02-22-2008
2.00
Set bottom skin on sawhorses
Details
       

 02-16-2008
0.50
Started on longerons
Details
     

 02-15-2008
3.00
Fabricated stiffeners
Details
       

 02-09-2008
3.00
Rolled elevator leading edges, more deburring
Details
       

 02-08-2008
1.00
Corrosion clean-up
Details
       

 02-02-2008
1.00
Installed trim tabs, bent hinge pins
Details
       

 01-31-2008
0.50
Continued to deburr bulkheads
Details
       

 01-29-2008
0.45
Finished riveting hinges, drilled safety wire hole
Details

 01-28-2008
3.00
Cut hinges, drilled, deburred, and began riveting
Details
       

 01-27-2008
2.00
Finished skin to tip rib rivets, more deburring
Details

 01-26-2008
2.00
Riveted trailing edges
Details
       

 01-20-2008
1.50
Trimmed elevator counter-weights, deburred blkhd
Details
       

 01-19-2008
0.75
Riveted trim cable attch brackets and fab'd HS att
Details
       

 01-18-2008
2.00
Pro-sealed the foam ribs and AEX wedge
Details
       

 01-17-2008
1.00
Riveted trim tab horns and spar to bottom skin
Details
       

 01-13-2008
3.00
Prepped and primed trim tab parts
Details
     

 01-12-2008
1.50
Bulkhead stiffener and VS attachment bars
Details
       

 01-11-2008
1.00
Finshed deburring and final drilled tie down bar
Details
       

 01-10-2008
0.50
Started tailcone construction
Details
       

 01-05-2008
1.00
Deburring trim tabs
Details

 01-01-2008
3.00
Trim tabs continued
Details
       

 12-31-2007
1.50
Began working on the trim tabs
Details
       

 12-30-2007
2.50
Continued riveting tip rib assembly to elevators
Details
       

 12-29-2007
2.00
Riveted root and tip ribs in-place
Details
       

 12-29-2007
2.00
Riveted root and tip ribs in-place
Details
       

 12-29-2007
2.00
Continued riveting tip rib assembly to elevators
Details
       

 12-28-2007
1.50
Riveted skins to front spar
Details
       

 12-28-2007
2.00
Began riveting front spar to elevator assembly
Details
       

 12-27-2007
1.00
Continued riveting skins to rear spar
Details
       

 12-27-2007
2.00
Continued riveting skins to rear spar
Details
       

 12-24-2007
1.50
Began riveting skins to rear spar
Details
       

 12-23-2007
2.50
Riveted ribs to skins
Details
       

 12-22-2007
1.00
Riveted nutplates to reinforcement plates
Details
       

 12-16-2007
0.50
Riveted doublers, root ribs, & elev horns to front
Details
       

 12-16-2007
0.50
Continued riveting front spar components
Details
       

 12-13-2007
1.00
Finished tip ribs and added counterbalance skin
Details
       

 12-12-2007
0.50
Riveted tip ribs together
Details
       

 01-21-2007
3.00
Primed all parts
Details

 01-20-2007
3.00
Dimpled all parts
Details
       

 01-19-2007
1.50
Deburring complete! Finally
Details

 01-18-2007
1.50
Deburring is now my life
Details

 01-15-2007
1.50
Even more deburring (make it stop), CSK'd AEX
Details
       

 01-11-2007
1.00
More beburring
Details

 01-10-2007
1.00
Began hole deburring with rear spars
Details

 01-09-2007
1.00
Disassembly complete
Details
       

 01-08-2007
1.00
Finished final drilling, started disassembly
Details
     

 01-07-2007
3.50
Drilled trim cable brackets, moved clecos to right
Details
       

 01-06-2007
2.50
Began final drilling with left side
Details
       

 01-05-2007
1.00
Cut trailing edge AEX to size, attached horns
Details
       

 01-04-2007
1.00
Attached left top skin to skeleton
Details
       

 01-03-2007
1.00
Attached tip rib assemblies
Details
     

 01-02-2007
2.50
Deburring complete, bent close-out tabs
Details
       

 01-01-2007
3.50
More deburring, celcoed/drilled internal and t-rib
Details
       

 12-31-2006
2.00
More deburring
Details

 12-30-2006
4.50
Edge deburring cont.
Details
     

 12-29-2006
3.00
Began work on elevators
Details
       

 12-28-2006
2.00
Riveting the HS
Details
       

 12-27-2006
2.00
HS clecoed for riveting
Details
       

 12-26-2006
1.00
Finished the riveting the skin to the ribs
Details
       

 12-25-2006
3.00
More skin riveting
Details
       

 12-24-2006
4.00
Started riveting HS skin to the spar flange
Details
       

 12-23-2006
3.50
Riveted front spar to nose ribs
Details
       

 12-21-2006
0.70
Riveted the nose ribs to the HS skins
Details

 12-21-2006
1.00
Close-out Inspection
Details

 12-20-2006
1.10
Riveted stringer assembly/1004 ribs to the front s
Details
       

 12-19-2006
1.50
Riveted stringer assembly together
Details
       

 12-17-2006
6.00
Primed HS parts
Details

 12-15-2006
2.00
Dimpling and CSK complete
Details
       

 12-14-2006
0.50
Dimpling cont.
Details

 12-13-2006
1.00
Dimpled ribs and scuffed parts
Details

 12-12-2006
1.00
Finished dimpling the skins
Details
       

 12-11-2006
1.00
Finished deburring ribs
Details

 12-09-2006
0.50
More dimpling
Details

 12-06-2006
1.00
Skins deburred! On to dimpling
Details

 12-05-2006
1.00
Even more deburring
Details
     

 12-04-2006
1.00
Deburring holes
Details

 12-03-2006
3.70
Disassembled the HS, began deburring
Details
     

 12-02-2006
3.70
Moved clecos from right to left, final drilled lef
Details
       

 12-01-2006
1.70
Final drilled right skin
Details

 11-29-2006
1.50
Installed stringer web, finshed right skin attach
Details
       

 11-28-2006
1.50
Clecoing initial HS assembly
Details
       

 11-26-2006
3.00
Initial HS skin-rib-spar assembly
Details
       

 11-25-2006
4.00
Cradel construction and more rib prep
Details
     

 11-24-2006
4.00
HS inspar and nose rib fitting and prep
Details
       

 11-22-2006
2.00
Riveted douber, spar caps, and brackets
Details

 11-19-2006
4.00
Diassembled, prepped, and primed parts
Details
     

 11-18-2006
3.00
Fab'd attach brackets and match driled to spar
Details
       

 11-16-2006
1.00
Marked layout lines for attach brackets
Details
     

 11-12-2006
3.00
Began building up the front spar
Details
       

 11-09-2006
2.00
Cut stringers to size
Details
       

 11-07-2006
4.00
Riveted hinges and doubler to spar.
Details
       

 11-05-2006
3.00
Installed Cnter-bal rib, rolling leading edge
Details
       

 11-02-2006
2.00
Double-flush riveted trailing edge
Details
       

 11-01-2006
1.00
Rudder Close-out inspection
Details

 11-01-2006
2.00
Riveted left stiffeners, tp & btm ribs, joined ski
Details
       

 10-29-2006
0.80
Positioned stiffeners on left skin
Details

 10-28-2006
6.50
Finished riveting VS
Details
       

 10-28-2006
1.00
Began riveting rudder
Details
       

 10-27-2006
2.00
Riveted rear spar components
Details
       

 10-27-2006
1.00
Close-out Inspection
Details

 10-23-2006
1.00
Riveted rudder stops
Details

 10-22-2006
6.50
Primed VS, Rudder, and part of HS
Details
       

 10-21-2006
2.00
Spar assembly and final drilling- ready to prime
Details
       

 10-20-2006
1.30
Continued to edge deburr the rear spar
Details

 10-19-2006
1.90
Started on HS.
Details
       

 10-18-2006
0.70
VS ready for priming
Details
       

 10-17-2006
2.10
Completed deburiing and dimpling all VS parts
Details
       

 10-16-2006
2.00
Deburring and dimpling the VS
Details
       

 10-15-2006
6.10
Assembled frame, attached and drilled skin
Details
       

 10-14-2006
2.10
Restarted the VS after getting new parts
Details
       

 10-13-2006
2.00
Trailing edge wedge CSK - rudder ready for primer
Details
       

 10-12-2006
1.00
Rudder dimpling continued
Details
     

 10-11-2006
2.00
Rudder teardown, deburr, and dimple
Details
       

 10-10-2006
2.00
Final drilled rudder trailing egde
Details
       

 10-09-2006
1.00
Match drilling rudder skin to skeleton
Details
       

 10-08-2006
2.00
Rudder skeleton match drilling
Details
       

 10-07-2006
2.00
Rudder match drilling and deburring
Details
     

 10-06-2006
2.00
Rudder start -- ribs, stiffeners, and shear clips
Details
       

 10-05-2006
2.50
Rib and spar doubler deburring
Details
       

 10-02-2006
0.00
Ordered replacement parts
Details

 09-29-2006
0.50
Match drill spar caps to spar
Details

 09-28-2006
0.00
Ordered missing parts
Details

 09-27-2006
2.00
VS Start
Details
       

 09-26-2006
3.50
Kit delvery and inventory
Details
       