Aviation Partners, LLC Project
RV-10
Fuselage
Work Logs Found:
157
Category Work Time:
1972 Hours
Date
Hours
Work Log Summary
Details
08-29-2012
2.00
Installed nose wheel pant
Details
08-28-2012
4.00
Installed the Aerosport Rudder Trim
Details
08-01-2012
12.00
Installed stick grips and adjusted torque tubes
Details
07-06-2012
2.00
Bleed Brakes
Details
04-09-2012
7.00
Installed louvers in cowl
Details
04-08-2012
9.00
Worked on air inlet
Details
04-07-2012
30.00
Completed Filtered Air Box and started cowl air in
Details
04-03-2012
30.00
Continued with the cowling installation
Details
03-30-2012
48.00
Installed attachment hinges on cowl
Details
03-24-2012
26.00
Trimmed Cowling
Details
03-19-2012
5.00
Installed Tail
Details
03-15-2012
38.00
Worked on Cowling
Details
03-09-2012
7.00
Completed Fab of the spinner
Details
03-08-2012
9.00
Began spinner fabrication
Details
03-07-2012
10.00
Installed Upper Click Loc Tabs
Details
03-06-2012
42.00
Completed Farings and Wheel Pants
Details
02-29-2012
9.00
Began install of lower right intersection fairing
Details
02-28-2012
30.00
Began installation of the gear leg fairings
Details
02-18-2012
20.00
Installed Nose Strut Fairing
Details
02-14-2012
55.00
Finished Left and Front Wheel Pants
Details
02-07-2012
25.00
Installed right wheel pant
Details
02-03-2012
4.00
Assembled Right Wheel Pant
Details
02-02-2012
4.00
Reconfigured Fuse Stand
Details
01-15-2012
2.00
Fabricated hinge cover plate
Details
01-13-2012
25.00
Attached Right Door
Details
01-09-2012
30.00
Finished up with the windows and priming
Details
01-04-2012
23.00
First Prime on Doors And fuse
Details
01-02-2012
52.00
Continued with final installation of windows
Details
12-26-2011
34.00
Continued with installation of front and side wind
Details
12-20-2011
6.00
Began installation of wind screen
Details
12-19-2011
9.00
Installed last interior panels
Details
12-16-2011
45.00
Installed right and left window
Details
12-12-2011
45.00
Installed Cabin Cover
Details
12-08-2011
9.00
Finished installing Glareshield
Details
12-07-2011
5.00
Fitted Windshield
Details
12-06-2011
4.00
Epoxied Cabin Cover
Details
12-04-2011
3.00
Cut out interior Kydex
Details
12-03-2011
36.00
Began re-assembly of cabin cover
Details
11-29-2011
20.00
Started assembling panel and interior
Details
11-26-2011
7.00
Fabricated glare shield overlays
Details
11-25-2011
9.00
Finished Priming panel overlay
Details
11-23-2011
6.00
Attached upper fwd fuselage
Details
11-22-2011
6.00
Primed center arm rest and various pieces
Details
11-09-2011
30.00
Continued with firewall
Details
11-01-2011
12.00
Installed Firewall Insulation
Details
10-30-2011
4.00
Installed remaining insulation
09-19-2011
9.00
Painted instrument sub-panel
Details
09-03-2011
10.00
Continued installation of the inst. panel
Details
09-02-2011
9.00
Began installation of Instrument Panel
Details
08-28-2011
4.00
Attached right wing fairings
Details
08-27-2011
3.00
Attached Right Wing
Details
08-26-2011
6.00
Completed disassembly of wing attachment
Details
08-25-2011
10.00
Installed wing root fairings
Details
08-24-2011
24.00
Attached control surfaces and pushrods
Details
08-23-2011
12.00
Attached Left Wing
Details
07-24-2011
6.00
Completed Wing Root Fairings
Details
07-22-2011
9.00
continued with section 44
Details
07-21-2011
5.00
Began Wing attachment tasks
Details
07-20-2011
2.00
Built Flap Pushrod
Details
05-29-2011
4.00
Installed Right Door Window
Details
05-26-2011
8.00
Finished trim on glass in Left Door
Details
05-24-2011
6.00
Fabricated Rudder Pulley Assembly
Details
05-23-2011
12.00
Installed glass in left door
Details
05-18-2011
6.00
Began final fitting and prep of door windows
Details
05-17-2011
2.00
Installed Heat selector boxes
Details
05-12-2011
4.00
Installed Fibrefrax ceramic insulation
Details
05-11-2011
6.00
Installed overhead vents and pnuematic strut brack
Details
05-10-2011
6.00
Re-installed latch system on doors
Details
05-09-2011
10.00
Completed Paint on Overhead
Details
05-05-2011
60.00
Finished Painting the Inside of Doors
Details
05-03-2011
28.00
Finished Primer on outside of doors
Details
05-02-2011
6.00
Skim coated and filled outside left and right door
Details
04-25-2011
60.00
Completed primer of door inside panels
Details
04-23-2011
4.00
Applied primer to inside of Cabin Cover
Details
04-20-2011
32.00
Continued with Overhead Console Paint Prep
Details
04-19-2011
9.00
Began installation of Overhead console
Details
04-15-2011
30.00
Finished fitting the Door Seal
Details
04-08-2011
45.00
Continued finishing the cabin cover
Details
04-03-2011
10.00
Completed left door latch and installed
Details
04-02-2011
2.00
Added locking clip to right door latch
Details
03-28-2011
9.00
Trimmed left and right door windows
Details
03-25-2011
8.00
Fabricated hinge cover for both doors
Details
03-24-2011
7.00
Began Trimming doors
Details
03-22-2011
8.00
Bonded Left Door Skins
Details
03-21-2011
8.00
Prep'd left door for installation of Center Latch
Details
03-18-2011
4.00
Completed Right Door installation of latch
Details
03-17-2011
4.00
Continued installation of center latch
Details
03-16-2011
12.00
Began installation of center latch
Details
03-15-2011
4.00
Installed door latch in right door
Details
03-11-2011
4.00
Installed right door hinge half
Details
03-11-2011
10.00
Finished Right door trimming
Details
03-10-2011
4.00
Assembled Door Latches
Details
03-09-2011
12.00
Trimmed doors and match drilled
Details
03-08-2011
10.00
Installed Cabin top
Details
03-07-2011
10.00
Installed center brace and support bracket
Details
03-05-2011
6.00
Completed final drilling of all attaching holes
Details
03-04-2011
9.00
Installed Cabin Cover and Match Drilled
Details
03-01-2011
6.00
Sanding and Fitting door openings
Details
02-28-2011
12.00
Continued Sanding Cabin Cover
Details
02-25-2011
3.00
Assembled Mid-seat Rail Support
Details
02-17-2011
10.00
Finalized fitting of Cabin cover to Fuselage
Details
02-16-2011
14.00
Continued Trimming Cabin Cover
Details
02-15-2011
10.00
Continued work on Cabin Cover installation
Details
02-14-2011
10.00
Began fitting of Cabin Cover
Details
02-13-2011
4.00
Fuel Line Re-Do
Details
02-09-2011
12.00
Completed Rear Seat Backs
Details
02-08-2011
12.00
Completed Section 40 Flaps Installation
Details
02-08-2011
3.00
Began construction of rear seat backs
Details
02-07-2011
4.00
Partlially completed Flap torque tube installation
Details
02-06-2011
7.00
Began flap system assembly
Details
02-05-2011
6.00
Finished Installation of controls
Details
02-04-2011
4.00
Completed installation of pedals and brake lines
Details
02-04-2011
5.00
Completed Brake Line and Brake Reservoir Installat
Details
02-04-2011
5.00
Assembled and installed control stick base
Details
02-03-2011
14.00
Fabricated remaining pushrods for Aileron
Details
02-02-2011
6.00
Installed Rudder Cable Fairings
Details
02-02-2011
2.00
Fabricated Elevator Pushrod
Details
02-01-2011
7.00
Routed left and right rudder cables through fuse
Details
01-31-2011
7.00
Installed Matco Parking Brake
Details
01-30-2011
2.00
Installed Safair1 Static Ports
Details
01-29-2011
6.00
Attached Brake Assemblies to WD1006
Details
01-28-2011
14.00
Primed remaining panels and covers, painted rudder
Details
01-28-2011
4.00
Assembled Brake Pedals
Details
01-27-2011
18.00
Fabricated inspection panel
Details
01-26-2011
1.00
My old flight instructors visit
Details
01-24-2011
18.00
Fabricated Lines and Installed Fuel System
Details
01-23-2011
10.00
Fabricated and installed brake lines
Details
01-12-2011
3.00
Cut out Rear NACA vent slots
01-11-2011
7.00
Completed Tunnel Covers
Details
01-10-2011
6.00
Installed Px seat floors
Details
01-10-2011
4.00
Final Riveted the PAX seat bottom
Details
01-08-2011
2.00
Installed Left Baggage cover to Fuse
Details
01-07-2011
7.00
Installed completed baggage door to fuselage
Details
01-07-2011
5.00
Completed baggage door
Details
01-06-2011
6.00
Ran additional conduit through baggage floor
Details
01-05-2011
6.00
Painted baggage door hardware
01-04-2011
6.00
Completed initial assy of baggage door
Details
01-04-2011
1.00
Completed Baggage Bulkead Assy
01-03-2011
12.00
Completed Baggage Close-Out
Details
01-02-2011
6.00
Installed right baggage cover to fuse
Details
12-31-2010
17.00
Riveted Baggage floor to fuse
Details
12-30-2010
8.00
Modified right baggage floor for inspection cover
Details
12-29-2010
10.00
Fabricated comm antenna doubler and installed
Details
12-28-2010
16.00
Assembled Baggage Door Frame
Details
12-27-2010
8.00
Installed Insulation and ran conduit
Details
12-27-2010
4.00
Assembled Baggage Door
Details
12-23-2010
14.00
Prepared Baggage Floor Panels for Installation
Details
12-21-2010
15.00
Continued riveting the fuse to the tailcone
12-20-2010
12.00
Began Riveting of Fuse to Tailcone
Details
12-19-2010
17.00
Re-Attached Fuse
Details
12-18-2010
14.00
Finished Prime of Fuse and Floor Panels
Details
12-17-2010
19.00
Built Paint Booth and Primed Fuse
Details
12-16-2010
15.00
Removed Tailcone and prepared for re-attachment
Details
12-14-2010
12.00
Continued with Tailcon and Fuse Attachment
Details
12-13-2010
10.00
Began attachment of Tailcone to fuse
Details
12-10-2010
18.00
Dis-asembled Fuse QB
Details
12-08-2010
18.00
QB Fuse and Wing Kit Arrived
Details
SITE NAVIGATION
Contact Builder
RV-10 Home
Category
# Logs
# Hours
All
303
4002
Avionics
32
566
Empennage
24
254
Engine
7
79
Final Assembly
10
69
Firewall Forward
7
159
Flight Testing
2
67
Fuselage
157
1972
Interior
3
41
Miscellaneous
3
22
Paint
17
398
Prop
1
140
Wings
40
235