N144GP Lancair Super ES
Lancair Super ES
Move
Work Logs Found:
15
Category Work Time:
21 Hours
Date
Hours
Work Log Summary
Details
08-07-2011
1.00
move cowling and rest of parts to airport
Details
07-18-2011
0.00
only damage from the move; left HS horn
Details
07-18-2011
5.50
move wings to airport; set up shop
07-17-2011
8.25
move fusleage to KCXY
Details
07-17-2011
2.00
load up wings - wrong way
Details
07-16-2011
0.00
ready to go to airport in the morning
07-16-2011
0.00
add'l load up pics
07-16-2011
0.00
07-10-2011
0.00
manuevering tail through door
07-10-2011
0.50
load up some parts to take to KCXY; misc shop
Details
07-10-2011
2.50
build new dolly set-up; test
07-10-2011
0.00
add'l manuevering fuselage pics
07-10-2011
0.00
add'l maneuvering pics
07-10-2011
1.50
10"heels on...attempt moving around garage
Details
07-09-2011
0.00
add'l pics
SITE NAVIGATION
Contact Builder
Lightning (EAB-LSA) Home
Lancair Super ES Home
Category
# Logs
# Hours
All
1827
4433
Avionics
113
163
Bodywork - misc.
10
25
Electrical
23
36
Elevators
15
60
Empennage
27
28
Engine
33
86
Firewall forward
77
163
Flying - test flying
29
94
Fuselage
633
1070
Garmin 3X Touch pane
139
256
Garmin GMC 507 Autop
18
35
Gear and wheels
102
196
Horizontal Stab
75
148
Interior
7
18
Miscellaneous
128
298
Move
15
60
Paint
1
973
Prop
7
13
Research, prep shop,
1
1
Speed Brakes
22
25
Vert Stab - Rudder
136
166
Wings
163
393
Wiring
53
126