Tom's Rans S-19 Builders Log
S-19
Engine
Work Logs Found:
19
Category Work Time:
90 Hours
Date
Hours
Work Log Summary
Details
09-01-2011
2.00
Completed cowling installation
Details
08-24-2011
2.00
Installed oil door in top cowling
Details
08-21-2011
8.00
Installed cowling fasteners and assembled spinner
Details
08-20-2011
6.00
Final fitting / trimming of cowling
Details
08-14-2011
6.00
Fitting of top cowl
Details
08-13-2011
6.00
Fitting of bottom cowl
Details
08-05-2011
8.00
Completed engine installation
Details
07-31-2011
2.00
Engine tachometer and alternator connections
Details
07-31-2011
6.00
Engine cooling system plumbing
Details
07-30-2011
5.00
Engine duct work
Details
07-30-2011
3.00
Completed exhaust system installation
Details
07-29-2011
2.00
Rotax ignition wiring
Details
07-25-2011
6.00
Wirrig of battery, starter, fuel pump, engine send
Details
07-24-2011
6.00
Installation of senders, fuel pump, exhaust system
Details
07-23-2011
4.00
Connected throttle and choke cables
Details
07-22-2011
8.00
Engine installation 2
Details
07-15-2011
6.00
Engine installation 1
Details
07-10-2011
3.00
Mounted oil tank, oil vent, and fuel drains
Details
04-11-2011
1.00
Engine Delivery and Visual Inspection
Details
SITE NAVIGATION
Contact Builder
S-19 Home
Category
# Logs
# Hours
All
191
842
Ailerons
6
27
Avionics
3
6
Electrical System
2
26
Empennage
1
3
Engine
19
90
Final Assembly
24
118
Flaps
9
22
Fuel System
2
3
Fuselage
79
368
Interior
2
4
Landing Lights
3
17
Miscellaneous
1
5
Parts
1
2
Project
2
Vertical Stabilizer
3
3
Wings
34
148
Copyright © 2001-2024 Matronics. All Rights Reserved.