The RV-10 Dream
RV-10
s02 Workshop Fitout
Work Logs Found:
5
Category Work Time:
34 Hours
Date
Hours
Work Log Summary
Details
04-13-2014
8.00
Get Hanger set up and ready for final assembly
Details
09-23-2012
3.00
Pull down spray booth
Details
03-20-2011
8.00
Spray Booth Setup
Details
07-26-2010
5.00
Collecting tools required for build
Details
02-27-2010
10.00
Build Work Benches
Details
SITE NAVIGATION
Contact Builder
RV-10 Home
Category
# Logs
# Hours
All
302
2194
AA Tips/Technique
2
s01 Garden/Garage
8
57
s02 Workshop Fitout
5
34
s03 QB Kit
2
12
s06 Empennage
2
14
s06 Vert Stabiliser
6
45
s07 Rudder
3
30
s08 Horizontal Stab
5
63
s09 Elevators
4
54
s10 Tail Cone
10
113
s18 Fuel Tank
1
2
s19 Stall Warning
1
8
s20 Wings
16
98
s23 Aileron Actuator
3
18
s24 Wing Tip
3
16
s29 Fuse Side Skins
1
8
s32 Tailcone Attach
2
10
s33 Baggage Area
2
14
s34 Baggage Door
2
11
s35 Floor panels
4
28
s36 Brake lines
1
3
s37 Fuel System
7
32
s38 Pedals and Brake
1
10
s39 Control System
6
26
s40 Flap System
1
4
s41 Up Fwd Fuse Inst
3
18
s43 Cabin Cover
14
77
s44 Wing Attachment
1
40
s45 Cabin Doors
17
111
s46 Eng Mnt and Lndg
5
24
s47 Spinner & Cowl
7
48
s48 Gear Legs
4
52
s49 Seats and Belts
4
20
s50 Cabin Heat
1
3
s80 Engine
25
158
s85 Prop
3
15
s90 Avionics
45
229
s99 Miscellaneous
32
151
sFF1 Engine Install
3
13
sFF2 Cowl Baffle
8
48
sFF3 Control Cables
1
8
sFF4 Fuel System
2
6
sFF6 Exhaust System
3
13
sPNT Painting
12
350
sUP Upholstery
4
28
Test Flights
5
6
z0 Maintenance
5
66
Copyright © 2001-2024 Matronics. All Rights Reserved.