Matt's Hangar
A-23 PROMETHEUS
Landing Gear
Work Logs Found:
31
Category Work Time:
100 Hours
Date
Hours
Work Log Summary
Details
10-21-2017
2.00
Reassembled nose gear
Details
09-10-2017
3.50
More NG rebuild
Details
09-04-2017
1.80
Mounted bow and wheels
Details
08-22-2017
0.60
Finished installing the NG-1
Details
08-21-2017
1.00
Finish assembly of the NG-1
Details
02-01-2016
2.50
Wheels and brakes
Details
01-20-2016
3.00
NG-1 Modification
Details
01-16-2016
8.00
Completed D-41, Installed nose gear
Details
01-12-2016
2.00
Finishing up NG-1
Details
01-09-2016
8.00
Finishing up NG-1 and 2
Details
01-08-2016
2.00
Nose gear truss temp installation
Details
01-08-2016
3.50
NG-2
Details
01-02-2016
5.00
NG-1 work
Details
12-26-2015
3.00
Axle work
Details
12-23-2015
4.00
General work day
Details
12-22-2015
4.00
CON parts and Axle Mounts
Details
12-20-2015
5.00
Bow is mounted...
Details
12-20-2015
1.00
Bow is mounted 2...
Details
12-18-2015
3.00
More work on the gear bow
Details
12-15-2015
5.00
More gear bow work
Details
12-13-2015
2.50
LG Mounting Layups
Details
12-11-2015
7.00
Landing gear parts - band saw
Details
12-04-2015
3.00
Layup 1, 2 and 3 on gear bow
Details
12-01-2015
4.50
Bow ear jig
Details
11-29-2015
3.00
Landing gear parts
Details
11-29-2015
3.00
Gear Bow Installation
Details
11-05-2015
0.10
Nose gear bushing research
Details
11-04-2015
0.50
Testing nose gear
Details
10-21-2015
3.00
Nose Gear - and box
Details
10-09-2015
4.50
Final cross plies on gear bow
Details
10-04-2015
0.70
Gear cleanup
Details
SITE NAVIGATION
Contact Builder
A-23 PROMETHEUS Home
Category
# Logs
# Hours
All
282
1377
Control
24
117
Design and Research
1
3
Firewall Forward
1
78
Fuel System
1
37
Fuselage
88
555
Interior
1
4
Jigs and Templates
14
44
Landing Gear
31
138
Misc Aircraft
1
0
Miscellaneous
5
109
Shop
6
10
Tools
4
13
Vertical Stabilizer
22
77
Wings
83
192