08-29-2015
|
3.50
|
Applied firewall sealant to firewall penetrations
|
Details
|
|
|
08-23-2015
|
2.00
|
Firewall forward work
|
Details
|
|
|
08-22-2015
|
5.00
|
Connected Throttle and Choke cable to Carbs
|
Details
|
|
|
08-21-2015
|
2.00
|
Replaced carburetor floats
|
Details
|
|
|
06-13-2015
|
4.00
|
Work on cooling system, empennage & glare shield
|
Details
|
|
|
06-11-2015
|
1.50
|
Installed shroud hose, repositioned oil cooler
|
Details
|
|
|
05-31-2015
|
1.50
|
Fitting the Bottom Cowl and Oil Cooler
|
Details
|
|
|
05-30-2015
|
5.00
|
Placed heat shield on cow, installed oil hoses
|
Details
|
|
|
05-23-2015
|
7.00
|
Installed heat shield and Trim Tab. AP knob work
|
Details
|
|
|
05-21-2015
|
1.00
|
Made templates for Cowl Bottom heat shields
|
Details
|
|
|
05-19-2015
|
1.50
|
Attached Cowl Duct Seal
|
Details
|
|
|
05-17-2015
|
3.50
|
Work on Cooling Duct and Throttle & Choke cables
|
Details
|
|
|
05-16-2015
|
4.00
|
Work on cooling system, throttle and choke cables
|
Details
|
|
|
05-10-2015
|
4.00
|
Epoxied the Cooling Duct and Interface to the Cowl
|
Details
|
|
|
04-26-2015
|
1.50
|
More work on the cooling duct and interface
|
Details
|
|
|
04-19-2015
|
4.00
|
Work on the Cooling Duct and Cowl Interface
|
Details
|
|
|
04-12-2015
|
5.00
|
Work on cooling system
|
Details
|
|
|
01-11-2015
|
2.00
|
Trimmed Drain Hose and Vent Tube, checked SV
|
Details
|
|
|
01-10-2015
|
4.00
|
Pitot Interconnect, Cooler Cable & Prop Spacer wor
|
Details
|
|
|
01-04-2015
|
4.00
|
Relocated Regulator, Redo of Cable to Cooler Door
|
Details
|
|
|
01-03-2015
|
6.50
|
Cooling system work, rectifier reposition
|
Details
|
|
|
12-23-2014
|
3.00
|
Work on Cooler Box cable & Secured brake lines
|
Details
|
|
|
12-22-2014
|
3.00
|
Installed Radiator and Seal Face
|
Details
|
|
|
12-21-2014
|
5.00
|
Installed Oil Tank Assembly and Overflow Bottle
|
Details
|
|
|
12-20-2014
|
3.50
|
Installed Cowl Oil Door and new throttle springs
|
Details
|
|
|
12-14-2014
|
3.00
|
Work on the Cowl Cooling Duct & Oil Cooler
|
Details
|
|
|
12-13-2014
|
1.00
|
Trimmed Cowl Cooling Duct
|
Details
|
|
|
11-30-2014
|
1.50
|
Work on Radiator positioning
|
Details
|
|
|
11-29-2014
|
8.00
|
Work on Cooling System
|
Details
|
|
|
11-23-2014
|
1.50
|
Painted Cooling System parts
|
Details
|
|
|
11-22-2014
|
6.00
|
Work on Cooling System
|
Details
|
|
|
11-21-2014
|
1.50
|
Work on Cooler Box Assembly
|
Details
|
|
|
11-16-2014
|
3.00
|
Work on Bottom Cowl Close-Out
|
Details
|
|
|
11-15-2014
|
6.00
|
Cowling and Cooling System work
|
Details
|
|
|
11-09-2014
|
1.50
|
Riveted the Upper Cowl Hinges
|
Details
|
|
|
11-08-2014
|
5.50
|
Work on Cowling
|
Details
|
|
|
11-02-2014
|
3.00
|
Cowling work
|
Details
|
|
|
11-01-2014
|
8.00
|
Work on Spinner and Cowling
|
Details
|
|
|
10-31-2014
|
0.50
|
Primed spinner plates
|
Details
|
|
|
10-14-2014
|
5.50
|
Work on Exhaust System
|
Details
|
|
|
10-13-2014
|
6.50
|
Riveted nutplates to spinner parts
|
Details
|
|
|
10-11-2014
|
5.00
|
Positioned spinner and drilled holes into plates
|
Details
|
|
|
09-28-2014
|
2.50
|
Installed Exhaust System, trimmed gap fillers
|
Details
|
|
|
08-16-2014
|
4.00
|
Torqued engine mt. bolts, FWF wiring & plumbing
|
Details
|
|
|
07-27-2014
|
4.00
|
FWF wiring and plumbing
|
Details
|
|
|
07-26-2014
|
5.50
|
Hung Rotax 912 ULS
|
Details
|
|
|
07-04-2014
|
5.50
|
Installed ADAHRS stiffener, drilled holes for engi
|
Details
|
|
|
06-22-2014
|
3.00
|
Wiring for canopy latch. Drilled hole for engine m
|
Details
|
|
|
04-05-2014
|
2.00
|
FWF wiring, EAA Tech Counselor visit
|
Details
|
|
|
04-03-2014
|
4.00
|
Firewall forward wiring
|
Details
|
|
|
04-02-2014
|
1.00
|
Work on EGT, FWF and Power wiring
|
Details
|
|
|
03-16-2014
|
1.50
|
Installed battery and other electrical parts
|
Details
|
|
|
05-10-2009
|
2.00
|
Parts inventory.
|
Details
|
|
|
05-07-2009
|
0.00
|
Empennage/Tail cone kit arrives.
|