Colin Cameron - Skybolt build
Skybolt Delta
Fuselage
Work Logs Found:
72
Category Work Time:
168 Hours
Date
Hours
Work Log Summary
Details
09-19-2009
3.00
Cut and fit front left gear leg
Details
09-07-2009
3.00
Finish weld battery tray and supports
Details
09-06-2009
4.00
Tack weld battery tray in place
Details
09-05-2009
1.00
Plot battery tray position using Deltacad
Details
09-04-2009
3.00
Fabricate battery tray
Details
09-03-2009
2.00
Finish weld seat frames
Details
09-02-2009
3.00
Align seat frames and tack weld in final position
Details
09-01-2009
2.00
Cut and fit front seat supports
Details
08-31-2009
4.00
Cut and fit rear seat supports
Details
08-30-2009
2.00
Fabricate two seat pan frames
Details
08-29-2009
1.00
Draw seats in CAD and make jig
Details
08-16-2009
1.00
Remove finished basic fuselage from jig
Details
08-15-2009
2.00
Finish weld 0 lower
Details
08-14-2009
2.00
Finish weld 0 upper
Details
08-13-2009
2.00
Finish weld 13
Details
08-11-2009
3.00
Finish weld 34 to 24
Details
08-10-2009
3.00
Finish weld 57 1/8 to 51
Details
08-09-2009
2.00
Finish weld 79
Details
08-08-2009
3.00
Finish weld 99 to 85
Details
08-07-2009
4.00
Finish weld 137 to 111
Details
08-06-2009
2.00
Finish weld 162 to 142
Details
08-05-2009
1.00
Finish weld Tailpost
Details
08-04-2009
1.00
Trim top longeron at 0
Details
08-04-2009
2.00
cap longerons at tailpost
Details
08-03-2009
2.00
Fit fuselage to jig
Details
08-02-2009
2.00
Construct finish welding jig
Details
08-01-2009
2.00
internal diagonal 0 to 24 (2 of 2)
Details
07-31-2009
3.00
internal diagonal 0 to 24 (1 of 2)
Details
07-30-2009
1.00
Ready for longeron to fuel tank clearance check
Details
07-29-2009
2.00
Internal diagonal 120 to 137
Details
07-28-2009
3.00
Internal diagonal 85 to 120
Details
07-27-2009
2.00
Dummy fuel tank for diagonal clearance check
Details
07-25-2009
2.00
Internall diagonals 79 to 85
Details
07-24-2009
2.00
Internal diagonals 0
Details
07-23-2009
2.00
Trim bottom longeron at station 0
Details
07-22-2009
2.00
Bottom diagonals 79 to 142
Details
07-21-2009
2.00
Bottom diagonals 57 1/8 to 79
Details
07-19-2009
2.00
Bottom diagonals 34 to 57 1/8
Details
07-16-2009
2.00
Bottom diagonals13 to 34
Details
07-14-2009
2.00
Bottom diagonals 0 to 13
Details
07-12-2009
2.00
top rear diagonals
Details
07-10-2009
2.00
bottom rear crossmembers
Details
07-08-2009
2.00
Top rear cross members
Details
07-05-2009
5.00
Main gear truss
Details
07-01-2009
2.00
square tailpost and tack weld in position
Details
06-30-2009
2.00
Form Longerons to tailpost
Details
06-29-2009
1.00
drill table for tailpost
Details
06-28-2009
2.00
Bend longerons
Details
06-27-2009
4.00
square fuselage sides in jig
Details
06-26-2009
2.00
layout assembly table for fuselage top
Details
06-25-2009
2.00
tack weld second fuselage side
Details
06-23-2009
1.00
17th upright
Details
06-22-2009
1.00
16th upright
Details
06-20-2009
1.00
15th upright
Details
06-17-2009
1.00
14th upright
Details
06-14-2009
1.00
12th & 13th upright
Details
06-08-2009
1.00
10th & 11th
Details
06-04-2009
1.00
8th & 9th uprights
Details
06-02-2009
5.00
Start second fuselage side
Details
04-26-2003
3.00
Tack weld all joints
Details
04-25-2003
3.00
16th & 17th upright
Details
04-24-2003
4.00
13th, 14th & 15th upright
Details
04-23-2003
1.00
12th upright
Details
04-22-2003
4.00
8th - 11th uprights
Details
04-21-2003
2.00
6th & 7th upright
Details
04-20-2003
3.00
4th & 5th upright
Details
04-15-2003
3.00
1st, 2nd & 3rd upright
Details
04-14-2003
3.00
Weld longeron splice and bend lower
Details
04-11-2003
2.00
Longeron Splice
Details
04-08-2003
4.00
Mark fuselage sides on assembly table
Details
04-07-2003
3.00
Steel and Centerline aids
Details
03-03-2003
6.00
Assembly table
Details
SITE NAVIGATION
Contact Builder
Skybolt Delta Home
Category
# Logs
# Hours
All
190
535
Cabane
6
21
Control Systems
31
103
Empennage
31
100
Fittings
9
20
Fuselage
72
168
Landing Gear
26
85
Rudder Pedals
10
31
Tools
5
7