KitLog pro

Powered By Kitlog Pro v2.0

My Airplane Projects
Work Logs Found: 83
Category Work Time: 311 Hours
 Date
Hours
Work Log Summary

Details

 12-21-2010
6.00
More final assembly work.
Details
       

 10-14-2010
4.00
Hooked up tail control surfaces, then disassembled
Details
       

 04-02-2010
5.00
Finished the tail cone.
Details
       

 01-08-2010
2.00
Drilled forward bow, fabbed the latch handles.
Details
       

 01-05-2010
6.00
Temporarily installed aft window.
Details
       

 12-22-2009
7.00
Riveted fuselage/empennage.
Details
     

 12-21-2009
4.00
Mated fuselage & empennage.
Details
       

 12-17-2009
2.00
Installed servo doubler.
Details
     

 12-09-2009
5.00
Finished wiring, started flight controls.
Details
       

 12-03-2009
3.00
More wiring.
Details
       

 11-13-2009
2.00
Finished instrument panels.
Details
     

 11-09-2009
5.50
Worked on instrument panels and map box.
Details
     

 11-08-2009
3.00
Continued prepping panel and map box parts.
Details

 11-07-2009
3.00
Finished upper forward skin.
Details
       

 11-06-2009
5.00
Installed forward fuselage skin.
Details
       

 11-05-2009
4.50
Completed the panel base assembly.
Details
       

 11-04-2009
1.50
Corrected longeron misalignment problem.
Details
       

 11-03-2009
2.00
Discovered longeron misalignment problems.
Details
       

 11-02-2009
4.00
Worked on canopy ribs.
Details
       

 10-30-2009
5.00
Installed upper firewall.
Details
       

 10-29-2009
7.00
Built the upper firewall.
Details
       

 10-28-2009
7.50
Finished roll bar and aft bulkhead structure.
Details
       

 10-27-2009
4.00
Drilled and painted roll bar.
Details

 10-26-2009
6.00
Mounted side skins and roll bar.
Details
       

 10-25-2009
2.50
Finished side skin prepping and painting.
Details
     

 10-24-2009
4.00
Drilled longerons.
Details
       

 10-23-2009
6.00
Worked on frames and side skins.
Details
       

 10-22-2009
3.00
Painted interior.
Details
       

 10-20-2009
6.00
Trial fit rudder and masked interior.
Details
       

 10-17-2009
4.50
Completed rudder/brake pedal assembly.
Details
       

 10-16-2009
2.00
Began work on rudder/brake pedals.
Details
       

 10-15-2009
3.00
Finished roll bar.
Details

 10-14-2009
1.00
Primed roll bar parts.
Details

 10-13-2009
4.00
Assembled and drilled roll bar.
Details
       

 10-12-2009
6.00
Finished seat backs, started roll bar.
Details
       

 10-11-2009
4.00
Finished prepping seat back parts.
Details
     

 10-08-2009
4.00
Tested interior paint, began seat backs.
Details
       

 10-04-2009
1.00
Rudder pedal powder coat problems.
Details
       

 10-03-2009
5.00
Finished fuel system.
Details
       

 10-02-2009
7.00
Continued work on fuel system - some problems.
Details
       

 09-30-2009
3.00
Began work on the fuel system.
Details
       

 09-29-2009
3.00
Finished prepping all Section 23 parts and stored.
Details
     

 09-28-2009
6.50
Temporarily installed side skins to fit longerons.
Details
       

 09-27-2009
5.00
Dry fit fuselage members including longerons.
Details
       

 09-26-2009
3.00
Reorganized workbench.
Details
     

 09-25-2009
5.00
Fabricated longerons.
Details
       

 09-24-2009
2.00
Started longerons.
Details

 09-08-2009
2.00
Finished Section 22.- Forward Lower Fuselage.
Details
       

 09-06-2009
1.00
Mated two fuselage sections.
Details
       

 09-03-2009
3.00
Continued on Forward Lower Fuselage.
Details

 09-02-2009
3.00
Finished Page 22-02.
Details

 08-31-2009
0.50
EAA 602 Meeting
Details
       

 08-29-2009
1.00
Broke in two "Rosies", worked on Section 22.
Details
       

 08-24-2009
1.00
Installed cooler stiffener.
Details
       

 08-23-2009
6.00
Summer update & some progress!
Details
       

 07-24-2009
6.00
Completed Section 21, center fuselage.
Details
     

 07-23-2009
4.00
Installed bulkhead and steps.
Details
     

 07-12-2009
1.00
Finished riveting bottom skin.
Details

 07-07-2009
1.00
Riveting bottom skin.
Details

 07-06-2009
2.00
Clecoed bottom skin.
Details
       

 07-05-2009
3.00
Worked on bottom skin.
Details
       

 07-04-2009
1.00
Installed corner skins with Nick & Lauren.
Details
       

 07-03-2009
3.00
Installed fuselage corner skins.
Details
       

 07-02-2009
5.00
Continued with assembly, flipped over.
Details
       

 07-01-2009
4.00
Finished bulkhead, installed control column.
Details
       

 06-30-2009
3.50
Continued assembling bulkhead.
Details
       

 06-29-2009
1.00
Fabricated control column mounts.
     

 06-25-2009
1.00
Prepped bulkhead doublers.
Details

 06-24-2009
5.00
Prepped bulkhead and parts.
Details
     

 06-22-2009
5.00
Finished seat area and joined to center section.
Details
       

 06-20-2009
7.00
Worked on seat frames.
Details
     

 06-18-2009
6.50
Finished baggage area, began seat area.
Details
       

 06-15-2009
4.00
Continued work on baggage floor assembly.
Details
     

 06-13-2009
2.00
Riveted baggage floor, installed nutplates.
Details

 06-09-2009
3.50
Squeezed rivets, began baggage floor assembly.
Details
     

 06-08-2009
6.00
Prepped parts.
Details
     

 06-07-2009
3.50
Completed Section 20 except for final riveting.
Details
     

 06-06-2009
4.00
Building up Center Section Assembly.
Details
       

 06-03-2009
2.00
Hung up on center assembly leaning.
Details
       

 05-27-2009
1.00
Continued prepping parts.
Details
     

 05-26-2009
4.50
Prepped parts for Section 20.
Details

 05-15-2009
1.50
Fuselage kit inventory 100% comlete!
Details
     

 05-14-2009
8.00
Worked on fuselage kit inventory.
Details
       










Copyright © 2001-2024 Matronics. All Rights Reserved.