Pete's Bearhawk Web Site
Bearhawk
Wing Skinning
Work Logs Found:
173
Category Work Time:
298 Hours
Date
Hours
Work Log Summary
Details
02-06-2012
2.00
Cut out the stiffeners and pocket covers.
Details
01-17-2012
1.00
Finished riveting the right wing skin.
Details
01-14-2012
4.00
More riveting
Details
01-10-2012
3.00
Riveting the right bottom skin.
Details
01-03-2012
2.00
Riveting on the right wing.
Details
01-02-2012
2.50
Riveting left bottom skin.
Details
12-31-2011
2.00
rivet squeezing.
Details
12-07-2011
2.00
Left bottom side main spar rivets.
Details
11-29-2011
8.00
Finished top skins and installed bottom skins
Details
10-25-2011
3.00
More riveting.
Details
10-11-2011
18.00
riveting, lots of riveting
Details
07-19-2011
2.50
Finished riveting the right bottom nose skin.
Details
07-18-2011
1.00
Began riveting the right bottom nose skin.
Details
07-01-2011
3.00
Finished riveting the right top nose skin.
Details
06-22-2011
2.00
Riveting right top nose skin.
Details
06-19-2011
4.00
Riveting bottom skin, D cell.
Details
05-03-2011
4.00
Began riveting skins!
Details
02-28-2011
1.00
installed 3rd and 4th right skins, prepped 5th.
Details
02-26-2011
1.50
Installed first 2 skins and primed two more.
Details
02-19-2011
1.50
dimpling and priming.
Details
02-16-2011
1.00
Dimple and prep...
Details
02-14-2011
1.00
finished prepping 4th right skin.
Details
02-13-2011
2.00
Work on the 3rd and 4th right wing skin.
Details
02-12-2011
2.00
Prepping the 3rd right skin.
Details
02-07-2011
1.00
Finished dimpling the second right skin.
Details
01-29-2011
1.50
dimpling the right skin.
Details
01-22-2011
2.50
Prepping skins.
Details
01-19-2011
1.00
Prepped some skin.
Details
01-15-2011
3.00
Work on the right wing skeleton.
Details
01-05-2011
0.50
More dimpling on the skeleton.
Details
01-03-2011
7.00
More prep on the right wing skeleton.
Details
12-31-2010
3.00
Finished right bottom skin, removed skins and bega
Details
12-30-2010
6.00
Began prepping the right bottom skin.
Details
12-29-2010
3.00
Prepped left bottom skin.
Details
12-28-2010
2.00
Bottom skin prep.
Details
11-10-2010
1.00
Deburred left bottom skin.
Details
10-06-2010
6.00
Lots of work on the left wing skins.
Details
10-04-2010
1.00
Worked on the left wing skin prep.
Details
09-25-2010
2.50
work on the left wing skins.
Details
09-22-2010
1.00
Installed the second left top skin.
Details
09-15-2010
1.50
Began dimpling the 3rd left top skin.
Details
09-14-2010
1.50
deburred the 3rd left top skin.
Details
09-13-2010
1.50
Finished dimpling the 2nd left top wing skin.
Details
09-11-2010
1.50
More skin prepping.
Details
09-09-2010
1.00
More skin prepping...
Details
09-08-2010
1.00
debur, dimple, repeat.
Details
09-07-2010
1.50
Prepped the short bottom skin by the fuel tank.
Details
09-05-2010
1.00
Fit left root skin onto skeleton.
Details
09-01-2010
1.00
Primed skins.
Details
08-31-2010
1.00
Countersunk the left wing skin stiffeners.
Details
08-25-2010
1.00
Began dimpling the left wing skins.
Details
08-24-2010
1.00
More dimpling...
Details
08-20-2010
2.50
Began dimpling the left wing skeleton.
Details
08-17-2010
0.50
some more deburring
Details
08-14-2010
0.50
More deburring....
Details
08-11-2010
4.00
Deburring and more deburring.
Details
08-09-2010
1.00
Removed the left wing skin for debur/dimpling.
Details
07-22-2010
1.00
Installed the right fuel tank.
Details
07-21-2010
2.00
Mounted left tank; worked on the right tank.
Details
07-20-2010
1.50
Made filler hole doublers.
Details
07-19-2010
2.00
Cut hole for fuel filler in left wing.
Details
06-26-2010
1.00
Finished the fuel tank straps.
Details
06-20-2010
5.00
Forming bottom straps for fuel tanks.
Details
06-07-2010
0.50
Fit the anti-chaff rubber to the bottom tank strap
Details
06-06-2010
1.00
primed the right wing tank straps.
Details
06-05-2010
1.50
Worked on the bottom tank straps.
Details
06-02-2010
1.00
Finished the short tensioner straps.
Details
06-01-2010
1.00
More work on the small tensioner straps...
Details
05-26-2010
1.00
Worked on the tensioner straps.
Details
05-24-2010
1.50
More work on the fuel tank strap tensioners.
Details
05-17-2010
1.50
Worked on the bottom fuel tank strap tensioners.
Details
05-12-2010
1.00
Worked on the fuel tank tensioner straps.
Details
05-05-2010
1.00
Worked on the tank strap tensioners
Details
05-04-2010
1.00
Made top tank straps for the right wing.
Details
05-03-2010
1.50
Began to fit the left fuel tank.
Details
04-28-2010
1.00
Finished fuel tank covers.
Details
04-12-2010
1.00
Began riveting the stiffeners to the left fuel tan
Details
04-10-2010
1.50
Primed the fuel tank covers.
Details
04-07-2010
1.50
Dimpled the fuel tank covers.
Details
04-05-2010
1.00
More work on the fuel tank covers.
Details
03-30-2010
1.00
Drilled stiffeners to the left fuel tank cover.
Details
03-29-2010
1.00
Countersunk holes in fuel tank cover supports.
Details
03-09-2010
0.50
Drilled/installed the right fuel tank bay stiffene
Details
03-08-2010
1.00
Installed left bay stiffeners.
Details
03-06-2010
1.00
Joggled the tank bay stiffeners.
Details
03-03-2010
1.00
Finished forming tank bay stiffeners.
Details
03-02-2010
0.50
Fuel Tank Inspection.
Details
03-02-2010
0.50
Formed 2 tank bay stiffeners.
Details
03-01-2010
1.50
formed the wing stiffeners for the fuel tank bays.
Details
02-25-2010
0.50
Cut out tank bay stiffeners.
Details
02-22-2010
1.00
Drilled the right fuel tank nut plates.
Details
02-17-2010
0.50
Drilled the nut plate holes for the left fuel tank
Details
02-16-2010
1.00
Drilling on the fuel tank covers.
Details
02-15-2010
1.50
Drilled the right fuel tank cover.
Details
02-13-2010
3.00
Fuel tank cover.
Details
02-10-2010
1.00
Drilled the right aft root skin.
Details
02-09-2010
2.00
Worked on the left aft root skin.
Details
02-03-2010
1.50
Drilled the left root skin.
Details
02-02-2010
1.00
Finished drilling the left root skin.
Details
02-01-2010
1.00
Started drilling the root skin.
Details
01-24-2010
1.00
Formed root leading edges.
Details
01-20-2010
1.00
Cut out root skins and tank panels.
Details
01-19-2010
1.00
Installed lugs on the large inspection holes.
Details
01-18-2010
1.50
Finished riveting the lugs onto the rings.
Details
01-12-2010
1.50
More work on the rings.
Details
01-11-2010
1.00
Began riveting lug nuts.
Details
01-10-2010
1.00
Applied a light coat of zinc oxide to rings.
Details
01-06-2010
1.00
Finished prepping backing rings.
Details
01-05-2010
1.00
More work on the backing rings.
Details
01-04-2010
1.50
Nut plate work on the backing rings.
Details
01-02-2010
2.00
Prepping the inspection hole covers.
Details
12-31-2009
6.00
More work on the inspection holes and covers.
Details
12-30-2009
5.50
More work on the inspection hole covers.
Details
12-29-2009
3.50
Working on the inspection hole covers.
Details
12-29-2009
3.00
Cut all inspection holes in wings.
Details
12-28-2009
6.00
Inspection hole work.
Details
11-24-2009
2.50
Inspection hole covers...
Details
11-18-2009
1.00
Made templates for inspection holes/covers.
Details
11-16-2009
1.00
Finished drilling the bottom right skin.
Details
11-14-2009
1.00
Drilled the bottom right skin to the skeleton.
Details
11-11-2009
2.00
Work on the right wing's bottom skin.
Details
11-10-2009
1.00
Finished drilling the last top skin.
Details
11-06-2009
1.00
More drilling on the last top right skin.
Details
11-04-2009
1.50
Installed the final top skin on the right wing.
Details
11-03-2009
1.00
Final leading edge formed.
Details
10-28-2009
0.50
Rough cut out most inspection hole covers and ring
Details
10-27-2009
1.50
Worked on the inspection cover jigs.
Details
10-15-2009
0.50
fit and drilled skin to right wing aft the fuel ta
Details
10-12-2009
1.00
Cut and drilled the left skin aft the fuel tank ba
Details
10-02-2009
2.00
Drilled the bottom skin to the spar.
Details
09-30-2009
1.00
Began drilling left bottom skin.
Details
09-29-2009
1.00
Aligned skin onto skeleton.
Details
09-28-2009
1.00
Marked and predrilled the left bottom skin.
Details
09-24-2009
1.00
Started work on the left bottom main skin.
Details
09-23-2009
0.50
oops.
Details
09-22-2009
1.50
Predrilled and began drilling the last right skin.
Details
09-21-2009
1.50
Formed the last right leading edge.
Details
09-14-2009
1.00
Finished drilling the 3rd right skin.
Details
09-09-2009
2.50
Drilled the 3rd right skin.
Details
09-03-2009
1.00
formed the right wing 3rd skin leading edge.
Details
09-02-2009
1.50
Finished drilling the second right wing skin.
Details
08-18-2009
1.50
More work on the second right skin.
Details
08-17-2009
1.00
finished prepping the second right wing skin.
Details
08-05-2009
1.00
Fit and traced the second right wing skin.
Details
08-04-2009
0.50
Formed the second leading edge.
Details
07-23-2009
1.00
Drilled the 1st right skin.
Details
07-22-2009
1.00
More work on the first right skin.
Details
07-21-2009
1.00
Fitted and traced the 1st right wing skin.
Details
07-06-2009
1.00
Formed the first leading edge of the right wing.
Details
06-24-2009
1.00
Finished replacing the third left skin.
Details
06-23-2009
0.50
More work on the "new" 3rd skin.
Details
06-18-2009
1.00
More work on the new 3rd left skin.
Details
06-17-2009
1.00
Began to repair the 3rd left skin.
Details
06-10-2009
0.50
drilled overlap holes to #30.
Details
06-09-2009
1.50
More drilling of the left wing skin.
Details
06-08-2009
1.50
Worked on the 4th left skin.
Details
06-07-2009
1.50
Prepped the 4th left skin.
Details
06-02-2009
2.00
Worked on the third and fourth left skin.
Details
06-01-2009
1.00
Third left skin nose drilled.
Details
05-29-2009
1.00
trimmed and reinstalled 3rd skin.
Details
05-21-2009
1.00
Prepped 3rd skin for drilling.
Details
05-20-2009
1.50
Matched and traced the 3rd left skin.
Details
05-18-2009
1.50
Finished drilling 2nd skin and formed next leading
Details
05-17-2009
2.00
Drilled the second left skin.
Details
05-16-2009
0.50
Marked hole locations for second skin.
Details
05-14-2009
1.50
Another skin fitted.
Details
05-11-2009
2.00
Drilled left tip skin to ribs.
Details
05-07-2009
0.50
Drilled holes in left tip skin.
Details
05-05-2009
1.50
more work on the left tip skin.
Details
05-04-2009
1.50
Traced the left wing tip skin.
Details
04-27-2009
0.50
Marked center line on ribs
Details
04-23-2009
0.50
Made another leading edge.
Details
04-22-2009
1.50
Began wing skinning.
Details
SITE NAVIGATION
Contact Builder
Bearhawk Home
Category
# Logs
# Hours
All
677
1060
Flaps
85
111
Flaps&Ailerons
85
111
Fuselage
12
46
Miscellaneous
1
Painting
1
2
Ribs
117
195
Shop Arranging
3
Spars
133
192
Tools
11
20
Welding
1
Wing Assembly
55
85
Wing Skinning
173
298