Powered By Kitlog Pro v2.0
John (Jack) Clark's Web Site
RV-A8
Engine
Work Logs Found:
88
Category Work Time:
158 Hours
Date
Hours
Work Log Summary
Details
12-22-2014
10.00
Engine Skipping
Details
07-26-2014
2.00
Mapped the ECU AFRs According to Instructions
Details
07-24-2014
2.00
Calibrated the SDS ECU to the Magnet Position
Details
07-19-2014
3.00
PSRU Spline and PSRU Re-installed
Details
07-16-2014
3.00
Re-Built Engine Back on the Aircraft
Details
07-14-2014
4.00
Replacement Valve Spacers Received
Details
07-04-2014
2.00
Engine Re-assembly Continues
Details
07-03-2014
1.00
Installed New Valve Spacers and Measured Gaps
Details
06-27-2014
3.00
Gears and Timing Chains Installed
Details
06-27-2014
0.25
Converted Surface Corrosion on the Flywheel
Details
06-27-2014
3.00
Aft Cover in Place
Details
06-25-2014
2.00
Heads on Short Block
Details
06-25-2014
0.00
Got the Heads Back From the Machine Shop
Details
06-23-2014
0.00
Received the Replacement Short Block
Details
06-23-2014
2.00
Brought the Heads In to be Machined
Details
06-22-2014
6.00
Removed the Heads
Details
06-21-2014
6.00
Disassembled the Engine
Details
06-20-2014
5.00
Removed the Engine From the Aircraft
Details
06-19-2014
2.00
Removed the PSRU
Details
06-18-2014
3.00
Drained the Coolant and Oil
Details
06-13-2014
1.00
Compression Testing of Engine
Details
04-11-2014
0.00
Engine Serial Number
Details
03-17-2014
2.00
Performed Compression and Leak Down Tests
Details
01-07-2014
1.50
Installed Tailpipe Hangers
Details
12-17-2013
1.00
Installed T-Bolt Clamps to the Tailpipe Hangers
Details
11-27-2013
0.25
Found Out the Airbox Sensor Nut Size
Details
11-25-2013
2.00
Installed the Airbox
Details
11-24-2013
3.00
Cut and Fit Airbox on the Left Side of Engine
Details
11-23-2013
0.00
Installed Tailpipes and Fabricated Muffler Brace 2
Details
11-23-2013
2.50
Installed Tailpipes and Fabricated Muffler Brace
Details
09-30-2013
0.50
Re-installed the Altenator
Details
09-30-2013
0.25
Re-attached Throttle Cable Support to Throttle Bod
Details
09-30-2013
0.50
Filled the Engine Oil and Coolant Reservoir
Details
09-29-2013
0.50
Re-attached the Coolant Hoses on the Engine Top
Details
09-28-2013
3.00
Re-installed the Timing Chain and the Cover
Details
09-25-2013
1.00
Installed Left AVCS Modification on Engine
Details
09-24-2013
1.00
Removed Old Sealant From Timing Chain Cover
Details
09-24-2013
1.50
Installed the Right Re-worked AVCS Modification
Details
09-19-2013
3.00
Removed the Timing Chain Cover
Details
09-19-2013
0.00
Removed AVCS from Both Sides of Engine
Details
09-18-2013
2.50
Started Process to Change the AVCS System Parts
Details
07-26-2013
1.00
Pulled the Injectors and Sent for Cleaning
Details
06-15-2012
0.00
Finished the Throttle Cable Installation 3
Details
06-15-2012
0.00
Finished the Throttle Cable Installation 2
Details
06-15-2012
3.00
Finished the Throttle Cable Installation 1
Details
06-14-2012
1.50
Cut a Hole in the Firewall for the Throttle Cable
Details
06-12-2012
1.50
Attached Throttle Cable to the Throttle Lever
Details
06-11-2012
1.00
Started Throttle Cable Installation
Details
03-06-2012
1.00
Troubleshoot Alternator Field Fault
Details
03-04-2012
0.50
Starter and Fuel Pumps Working
Details
03-02-2012
1.00
Changed the PSRU Oil and Installed Magnetic Plug
Details
03-01-2012
1.50
Changed the Engine Oil and Filter
Details
02-27-2012
3.00
Connected Engine Wires to Terminal and Connector
Details
02-26-2012
2.00
Fabricated and Mounted Engine Electrial Terminal
Details
02-21-2012
2.50
Mounted ECU in the Fwd. Electrical Compartment
Details
02-12-2012
4.00
Wired EIS to Eggenfellner Subaru 9 pin Connector
Details
02-12-2012
0.00
Wired EIS to Eggenfellner Subaru 9 pin Connector
Details
01-22-2012
4.50
Secured the Fuel Pressure Regulator to Firewall
Details
01-22-2012
1.50
Installed Firesleeve on the Firewall Penetration
Details
01-15-2012
3.50
Ran Fat Wire to Starter Contactor and Starter
Details
01-13-2012
0.50
Test Fit Airbox and Filter to Engine Mount
Details
01-13-2012
1.00
Attached ANL Fuse Holder and Starter Contactor
Details
01-13-2012
1.50
Attached Airbox Flange to Airbox
Details
01-12-2012
0.00
Fabricated Airbox
Details
01-12-2012
2.50
Assembled, Modified and Fit the Airbox
Details
01-11-2012
0.50
Mounted the Coolant Reservoir to the Firewall
Details
01-10-2012
1.00
Ran Engine Cables Through the Firewall
Details
01-03-2012
0.50
Patched Extra Firewall Penetrations
Details
01-03-2012
2.00
Made Several Firewall Penetrations
Details
01-03-2012
0.00
Made Several Firewall Penetrations
Details
12-31-2011
0.25
Cut Firewall Pass Through From SS Hand Rail
Details
12-22-2011
4.00
Attached the Engine to the Fuselage
Details
12-20-2011
0.75
Flipped the Engine Vertical
Details
09-06-2011
0.25
Added a Red Switch Guard to the Engine Kill Switch
Details
03-21-2011
0.50
Changed the Engine Oil and Ran the Engine
Details
06-28-2009
2.50
Installed heater in forward right corner
Details
06-26-2009
2.50
Began heater installation
Details
06-07-2009
4.00
New ECU/First Engine Start
Details
06-03-2009
0.00
Delivered the ECU to Jan Eggenfellner
Details
06-01-2009
3.00
Continued coil combinations
Details
05-31-2009
3.00
Can't stop blowing fuses
Details
05-30-2009
2.00
Blowing 20A inline fuse when engine terminal on
Details
05-29-2009
3.00
Daisy chain wired the terminal for engine start
Details
03-27-2009
0.50
Added Gear oil to the PSRU
Details
03-23-2009
0.25
Added 4 quarts of 5W-30 Oil to the engine
Details
10-27-2008
1.00
Drilled 1/4" engine mount holes in the firewall
Details
10-26-2008
2.00
Fit Engine mount to firewall
Details
08-17-2008
0.00
Picked up my Eggenfellner H-6 Engine
Details
SITE NAVIGATION
Contact Builder
RV-14A Home
RV-A8 Home
Category
# Logs
# Hours
All
2277
6152
Aircraft Related
314
1432
Avionics
206
404
Brakes
11
18
Canopy
41
63
Cooling System
7
9
Cowl Flap
13
20
Cowling
146
354
Electrical System
157
311
Empennage
29
48
Engine
88
158
Fiberglass
148
316
Finishing Kit
27
76
First Flight Prep
4
1
Flight Control Syste
75
118
Flight Testing
18
20
Flights
6
7
Forward Baggage Comp
6
9
Forward Top Skin
24
36
Fuel System
84
155
Fuselage
344
812
Heating System
1
0
Inspection
5
5
Interior
24
20
Landing Gear
53
100
Lighting
17
27
Miscellaneous
8
5
None
14
6
Oxygen System
5
6
Painiting
11
28
Painting
11
28
Prop
22
27
Sensors
5
7
Testing
1
1
Ventilation
3
4
Windscreen
8
13
Wing Construction
27
76
Wings
314
1432
Copyright © 2001-2024 Matronics. All Rights Reserved.