Work Logs Found: 31
Category Work Time: 72 Hours
 Date
Hours
Work Log Summary

Details

 09-15-2015
2.50
route brake lines and bleed
Details
       

 09-15-2015
2.00
clean up brake stuff, run RG400 for transponder
Details
       

 09-15-2015
2.00
brake lines at main wheels
Details

 08-11-2015
2.50
modify brake res. for overflow fitting & tube
       

 08-11-2015
0.75
Mark MG fairings for brake line cut-out
       

 08-04-2015
5.00
mount brake res. and run all brakes lines
Details

 05-04-2015
3.00
finish fitting L MG fairing; final trim on all pan
Details
       

 04-14-2015
1.00
fit hinge pin access from inside of fuselage; R si
Details
       

 04-14-2015
1.00
continue fitting R leg fairing
Details
       

 04-14-2015
2.25
begin cutting/fitting L fairing to pant

 04-12-2015
3.25
trim, fit and hinge on
       

 04-12-2015
1.50
fit, cut repair nose fairing
Details
       

 04-12-2015
2.25
fab and install R main fairing
Details
       

 04-12-2015
1.25
add hinge closure to nose fairing
Details
       

 04-06-2015
4.25
work on nose gear
       

 04-06-2015
2.00
nose pant on
Details
       

 04-06-2015
4.00
mount nose wheel on nose gear
       

 04-06-2015
1.50
fit, fab and install nose pant & brackets, etc
       

 04-06-2015
1.50

       

 03-30-2015
2.50
main gear rivnuts
Details
       

 02-15-2015
2.00
install all nutplates on both MG pants
Details

 02-15-2015
3.00
fit, trim and install L MG pant
Details

 02-09-2015
3.00
MG pants; fit & trim halves
       

 02-09-2015
2.00
fit right pant to axle/leg
Details
       

 02-09-2015
1.50
fit pant to R axle; fab brackets TEDIOUS
       

 02-09-2015
1.50
detail of R pant brackets, etc
Details
       

 02-02-2015
2.50
set toe in and drill/bolt gear legs
Details
       

 02-02-2015
0.50
figure out displacemnt for 1 degree toe in
Details
       

 01-26-2015
1.50
mount all 3 tires
Details
       

 01-26-2015
1.50
main gear to fuselage - loose
Details
       

 01-26-2015
7.00
fab gear legs, brakes and axles
Details
       