KENNETH T.'S WEB SITE
RV-7A
Empennage
Work Logs Found:
68
Category Work Time:
306 Hours
Date
Hours
Work Log Summary
Details
03-07-2013
4.00
Nutplate installed on elevator horn inspection hol
Details
03-05-2013
4.00
Sanded fairing & connected elevator push rod.
Details
03-04-2013
3.50
Trimmed off excess glass on empennage fairing.
Details
03-03-2013
4.50
Brake, airblast tube, and empennage work.
Details
02-26-2013
4.00
Began measuring baffles for trimming.
Details
02-25-2013
4.00
Riveted rudder cable fairings.
Details
02-23-2013
4.00
Continued empennage work.
Details
02-22-2013
4.00
Trimmed empennage fairing.
Details
02-18-2013
3.50
Removed enclosure for more needed work.
Details
02-17-2013
4.00
Crimped pins to wires for circular molex connector
Details
02-15-2013
4.00
Final fitting of the bottom rudder enclosure.
Details
02-14-2013
3.50
More trimming on bottom rudder enclosure.
Details
02-13-2013
4.00
Pulled wires through the aft bulkhead.
Details
02-12-2013
4.00
Started installing rudder bottom enclosure.
Details
02-11-2013
4.00
Fabricated rudder pedal to cable links & installed
Details
02-08-2013
4.00
Pulled rudder cables.
Details
02-07-2013
4.50
Worked on upper & lower horz. fairings.
Details
02-06-2013
4.00
Drilled empennage fairing screw holes.
Details
02-05-2013
4.00
Installed Vert Stab with AntiSplat mod.
Details
02-04-2013
4.00
Drilled nutplate holes on vert & horiz. stabs.
Details
02-02-2013
4.00
Installed Horizontal Stabilizer
Details
03-17-2012
6.00
Installed rudder stops.
Details
03-16-2012
4.00
Installed rudder to vertical stabilzer.
Details
03-12-2012
4.00
Riveted attach plate to VS forward spar.
Details
03-10-2012
4.00
Match drilled VS forward spar to attach plate.
Details
03-09-2012
6.00
Clamped VS to the forward spar attach plate.
Details
03-08-2012
3.00
Clamped VS to the HS for measuring.
Details
03-07-2012
4.00
Started installing vertical stabilizer.
Details
03-02-2012
6.00
Elevator deflection angles continued.
Details
02-28-2012
8.00
Installed elevator pushrods to check deflection an
Details
02-26-2012
5.00
Connected elevator trim wiring in aft tailcone.
Details
02-24-2012
4.00
Installed elevator trim servo.
Details
02-23-2012
5.00
Drilled HS forward and aft spars.
Details
02-22-2012
4.00
Started leveling HS on aft deck.
Details
02-18-2012
2.00
Started installing empennage.
Details
07-10-2009
5.00
Cut the flanges off the canopy bubble.
Details
05-12-2009
4.00
Started riveting the panel framework to firewall.
Details
06-23-2008
2.00
Finished installing VS tip.
Details
06-20-2008
3.00
Fabricated HS tip plexiglass enclosure.
Details
06-18-2008
3.00
Start install of Tip on Vertical Stabilizer.
Details
06-17-2008
3.00
Enclosed HS Tips using Plexiglass & Fiberglass.
Details
06-16-2008
4.00
Started Horizontal Stab Tips Installation.
Details
06-11-2008
4.00
Installed elevators onto horizontal stabilizer.
Details
06-09-2008
5.00
Finish elevator tips installation.
Details
06-07-2008
4.00
Mounted elevators to HS.
Details
06-05-2008
3.00
Start to install elevator fiberglass tips.
Details
06-04-2008
5.00
Installed elevator trim servo.
Details
06-03-2008
4.50
Installed elevator rod end hinges & counter weight
Details
05-25-2007
1.00
Drilled out bad rivets and used new Tungsten bucki
Details
05-22-2007
2.00
Riveted the VS rear spar to the other side of the
Details
05-21-2007
2.00
Inventoried ordered tools then tried riveting the
Details
05-17-2007
3.00
Riveted VS skin to the VS frame (ribs and front sp
Details
05-16-2007
5.00
Riveted VS ribs to the front spar with difficulty.
Details
05-15-2007
4.00
Riveted the rear spar, doubler and hinge brackets.
Details
05-14-2007
3.00
Set up and primed Vertical Stabilizer Components
Details
05-12-2007
4.00
Tried to set up to prime VS components.
Details
05-11-2007
4.50
Dimpled spars and ribs and countersunk holes in do
Details
05-10-2007
2.00
Finished deburring components and dimpled skin.
Details
05-09-2007
4.00
Match drilled VS skin to frame then disassembled a
Details
05-08-2007
3.00
Assembled and drilled frame then clecoed skin on.
Details
03-14-2007
0.00
Home with the goodies.
Details
03-11-2007
4.00
Finished and installed trim tab.
Details
03-10-2007
11.50
Finish riveting HS skins and elevator skins.
Details
03-09-2007
11.00
Rivet rudder and start riveting HS skins.
Details
03-08-2007
11.50
Start Elevator Prep and riveting HS rear spar.
Details
03-07-2007
10.75
Finished HS Prep and start Rudder Prep
Details
03-06-2007
11.50
Continued prepping Horizontal Stabilize.
Details
03-05-2007
10.00
Started on the empennage kit by inventoriing.
Details
SITE NAVIGATION
Contact Builder
RV-7A Home
Category
# Logs
# Hours
All
720
3309
Avionics
40
188
Cowling
11
54
Electrical System
113
524
Empennage
68
306
Engine
50
228
Fuselage
195
867
Instrument Panel
33
164
Miscellaneous
120
581
Wings