The Joyce Family RV-7A
Work Logs Found: 23
Category Work Time: 152 Hours
 Date
Hours
Work Log Summary

Details

 10-25-2010
75.00
Finished the elevators and wrapped up the empennag
Details
       

 07-18-2008
25.00
Finished Rudder
Details
     

 07-03-2008
4.00
Continued work on the Rudder
Details

 06-25-2007
4.50
More Rudder work
Details
     

 06-20-2007
1.00
Back Riveting Rudder Stiffners
Details
       

 06-19-2007
2.00
Debur, Dimple rudder skins and stiffners
Details
       

 06-18-2007
1.50
Match Drilled the Rudder Stiffners
Details
       

 04-29-2007
3.00
Finished the Horizontal Stab!
Details
       

 03-08-2007
1.00
Rivet the front spar components
Details

 03-07-2007
2.00
Dimple, prime
Details

 03-04-2007
1.50
Dimpled the ribs& spars. Deburred the skins.
Details

 03-03-2007
2.00
Deburred the HS ribs & spars
Details

 02-15-2007
2.00
Corrected the HS-710 drilling mistake
Details

 02-14-2007
3.50
Finished the Vertical Stab
Details
       

 02-03-2007
8.00
Work on the Vertical Stab
Details
       

 02-02-2007
3.00
Worked on the Horizontal Stab
Details
     

 01-31-2007
1.50
More work on the HS
Details
     

 01-30-2007
2.50
Drilling the Left Horizontal stab
Details
       

 01-29-2007
1.50
Forward HS Spar Assembly Fabrication
Details
       

 01-28-2007
1.50
HS Front Spar Assembly
Details

 01-27-2007
2.50
Inventoried the Tail Kit
Details
     

 01-27-2007
2.50
Horizontal Stab. Rear Spar Assembly
Details
       

 12-29-2006
0.50
Ordered the Tail Kit
Details
     