Michael and Gayle's RV-7A
RV-7A
Fuselage
Work Logs Found:
176
Category Work Time:
766 Hours
Date
Hours
Work Log Summary
Details
05-29-2009
5.00
Fuselage to Yolo County Airport
Details
05-28-2009
5.00
Fuselage loaded on trailer
Details
08-17-2008
5.00
Fresh Air vent brackets and paint touch-up
Details
08-16-2008
3.00
Add parts back under upper fuse
Details
08-10-2008
4.00
Last fuselage skin!
Details
04-27-2008
4.00
Miscellaneous work in fuselage
Details
04-20-2008
7.00
Upper rear fuselage skins riveted
Details
04-19-2008
7.00
Paint Cabin Frame and upper fuse skin
Details
04-05-2008
7.00
ELT wiring and trimtab cable
Details
04-04-2008
3.00
ELT Antenna mount
Details
04-03-2008
5.00
Whelen Strobe power supply mount
Details
04-01-2008
6.00
ELT Mount
Details
03-30-2008
7.00
Digital clock and Pitot Static line
Details
09-07-2007
5.00
Fresh Air Vents
Details
09-06-2007
9.00
Upper Fuse assembly
Details
09-05-2007
4.00
Panel planning
Details
09-04-2007
8.00
Debur and prep upper fuselage parts
Details
09-03-2007
5.00
Debur and prep upper fuselage parts
Details
07-30-2007
2.00
Heater Mount modification
Details
07-29-2007
3.00
Power cable to Starter Contactor
Details
07-27-2007
8.00
Fuel Lines, Starter Contactor, Alt. OV Contactor
Details
07-26-2007
9.00
Fuel Lines
Details
07-25-2007
6.00
Brake Lines and Fuel Switch
Details
07-24-2007
5.00
Firewall center plate
Details
07-23-2007
4.00
Fuel Pumps
Details
07-19-2007
5.00
Cabin Miscellaneous
Details
07-18-2007
9.00
Cabin Miscellaneous
Details
07-17-2007
6.00
Cabin Miscellaneous
Details
07-16-2007
7.00
Cabin miscellaneous
Details
07-15-2007
8.00
Fuel Vent Line and Brakes
Details
07-14-2007
2.00
Fuel Vent Line and Screen
Details
07-08-2007
4.00
Main and Battery busses wired
Details
07-03-2007
0.25
Experimental decal
Details
06-28-2007
2.50
Battery ground cables
Details
06-24-2007
3.00
Rudder Pedals
Details
06-22-2007
4.00
Gear legs mounted
Details
06-20-2007
3.00
Main and Engine busses
Details
06-17-2007
3.00
Pitch servo mount
Details
06-14-2007
5.00
Miscellaneous
Details
06-10-2007
1.50
F-789 Elevator pushrod
Details
06-10-2007
6.00
Battery mounting
Details
06-09-2007
7.00
Battery mounting
Details
06-08-2007
4.00
Pitch Servo mount
Details
06-05-2007
2.50
Battery mounting
Details
06-01-2007
3.00
Battery mounting
Details
05-31-2007
3.00
Battery mounting
Details
05-30-2007
0.25
Batteries arrived
Details
05-28-2007
8.00
Cabin Frame
Details
05-25-2007
2.00
Cabin Frame
Details
05-23-2007
2.50
Cabin Frame
Details
05-22-2007
2.50
Cabin Frame
Details
05-21-2007
2.50
Cabin Frame
Details
05-19-2007
10.00
Cabin Frame
Details
05-18-2007
3.00
Cabin Frame
Details
05-17-2007
2.00
Cabin Frame
Details
05-16-2007
0.25
Cabin Frame
Details
05-13-2007
1.50
Cabin Frame
Details
05-12-2007
1.00
Cabin Frame
Details
05-11-2007
4.00
Cabin - Interior paint
Details
05-08-2007
2.00
Cabin - Interior paint
Details
05-05-2007
7.00
Cabin - prep for paint
Details
05-04-2007
5.00
Cabin - prep for paint
Details
05-03-2007
3.00
Cabin - prep for paint
Details
04-29-2007
5.00
Cabin - prep for paint
Details
01-27-2007
6.50
Landing Gear Mounts
Details
01-27-2007
2.00
Electric flap assembly
Details
01-22-2007
3.00
Electric flap assembly
Details
01-21-2007
5.00
Electric flap assembly
Details
01-20-2007
4.00
Electric flap assembly
Details
01-14-2007
2.00
Forward Covers
Details
01-14-2007
1.25
Electric flap assembly
Details
01-13-2007
6.00
Fabricate seats
Details
01-12-2007
1.50
Fabricate Seats
Details
01-09-2007
0.50
Fabricate seats
Details
01-05-2007
3.00
Fabricate seats
Details
01-01-2007
4.00
Fabricate seats
Details
12-30-2006
8.00
Forward Seat floors and Control Rod Tunnel
Details
12-29-2006
7.00
Aft Seat Floors
Details
12-28-2006
6.00
Baggage Compartment
Details
12-27-2006
6.00
Baggage Compartment
Details
12-26-2006
4.00
Conduit in center fuselage
Details
12-26-2006
4.00
Baggage floors
Details
12-03-2006
6.00
Baggage access panels
Details
12-02-2006
5.00
Right Step kit
Details
12-01-2006
2.50
Baggage floor access panels
Details
11-28-2006
2.50
Step kit, left side
Details
11-27-2006
3.00
Step kit, left side
Details
11-26-2006
2.00
F-750 L&R Aft Baggage Side covers
Details
11-19-2006
9.00
F-656 gussets and F786A J-Stringers
Details
11-18-2006
3.00
F-635 Bell Crank
Details
11-14-2006
3.50
F-695 Forward firewall gussets
Details
11-10-2006
2.00
F-721B right side
Details
11-07-2006
2.00
F-721B left side
Details
11-05-2006
3.00
F-757 L&R
Details
11-04-2006
3.00
F-757 L&R
Details
11-01-2006
3.00
F-714 Aft deck
Details
10-31-2006
4.50
F-714 Aft deck
Details
10-30-2006
2.00
F-714 Aft deck
Details
10-29-2006
6.00
Rolled the Canoe Over
Details
10-28-2006
8.00
F-770 Side skins
Details
10-27-2006
8.50
F-770 Side skins, F-772 bottom skin
Details
10-24-2006
0.50
F-722 horizontal ribs
Details
10-22-2006
2.00
F-684 gussets, F-719 & F-719B
Details
10-20-2006
8.00
Forward fuselage - preparation
Details
10-14-2006
2.00
Forward fuselage - preparation
Details
10-08-2006
7.00
Forward fuselage - preparation
Details
10-07-2006
3.00
Forward fuselage - preparation
Details
10-06-2006
3.00
Forward fuselage - preparation
Details
10-01-2006
8.00
Forward fuselage - preparation
Details
09-30-2006
8.00
Forward fuselage - preparation
Details
09-28-2006
2.50
Forward fuselage - preparation
Details
09-25-2006
3.00
Forware fuselage - preparation
Details
09-24-2006
8.00
Forward fuselage - preparation
Details
09-23-2006
10.00
Forward fuselage - preparation
Details
09-22-2006
8.00
Forward fuselage - preparation
Details
09-12-2006
3.00
Center fuselage - assembly
Details
09-10-2006
3.00
Center fuselage - assembly
Details
09-09-2006
8.00
Center fuselage - assembly
Details
09-08-2006
12.00
Center fuselage - assembly
Details
09-04-2006
8.00
Center fuselage - assembly
Details
09-03-2006
8.00
Center fuselage - preparation
Details
09-02-2006
8.00
Center fuselage - preparation
Details
09-01-2006
8.00
Center fuselage - preparation
Details
08-27-2006
4.00
Center fuselage - preparation
Details
08-26-2006
3.00
Center fuselage - preparation
Details
07-13-2006
4.00
Center fuselage - preparation
Details
07-12-2006
0.50
Center fuselage - preparation
Details
07-11-2006
4.00
Aft fuselage - Assembly
Details
07-10-2006
2.50
Aft fuselage - Assembly
Details
07-09-2006
6.00
Aft fuselage - Assembly
Details
07-08-2006
8.00
Aft fuselage - prep for assembly
Details
07-07-2006
7.00
Aft fuselage - prep for assembly
Details
07-06-2006
3.00
Aft fuselage - prep for assembly
Details
07-05-2006
2.00
Aft fuselage - J-channel stringers
Details
07-04-2006
7.00
Aft fuselage - J-channel stringers
Details
07-03-2006
4.00
Aft fuselage - longerons
Details
06-29-2006
5.00
Aft fuselage - longerons
Details
06-26-2006
4.00
Aft fuselage - longerons
Details
06-15-2006
3.00
Aft fuselage - test fit parts
Details
06-14-2006
2.00
Aft bulkheads - fluting and straightening
Details
06-12-2006
2.50
Aft Bulkheads - F-712
Details
06-11-2006
8.00
Aft Bulkheads - F-708, F-709, F710 and F-711
Details
06-10-2006
7.00
Aft Bulkheads - Finish F-706, start on F-707
Details
06-08-2006
2.50
Aft Bulkheads - fab & assembly for F-706
Details
06-07-2006
2.50
Aft Bulkheads - Prime parts
Details
06-06-2006
3.00
Aft Bulkheads - cleaning parts
Details
06-05-2006
3.00
Aft Bulkheads - deburring
Details
06-02-2006
3.00
F-705 Final assembly
Details
06-01-2006
2.00
F-705 Prime parts prior to assembly
Details
05-31-2006
5.00
F-705 deburring and prep for primer
Details
05-29-2006
7.00
F-705 seat back stop and miscellaneous fabrication
Details
05-28-2006
7.00
F-705 seat-back stop fabrication
Details
05-27-2006
7.00
F-705 bottom spar fabrication
Details
05-26-2006
3.00
F-705 parts prep
Details
05-24-2006
0.50
Center Section - priming side panels
Details
05-23-2006
3.00
Assemble Control linkages
Details
05-22-2006
5.00
Center Section goes together!
Details
05-21-2006
5.00
Center Section - assembly prep
Details
05-20-2006
6.00
Center Section - more fabrication
Details
05-19-2006
2.50
Center section - fabricate Cover Support rib
Details
05-18-2006
2.00
Center Section prep
Details
05-16-2006
1.50
Begin F-704 Center section
Details
05-15-2006
7.50
Prime spars and rivet Firewall
Details
05-14-2006
2.00
Counter-sink spars for Firewall
Details
05-13-2006
2.50
Debur and counter-sync
Details
05-12-2006
2.00
Rivet Firewall recess
Details
05-11-2006
1.50
Various fabrication and dimple the Firewall
Details
05-10-2006
2.00
Match-drill firewall components
Details
05-06-2006
2.00
Begin preparing firewall components for assembly
Details
05-04-2006
2.00
Organized fuselage bulkhead parts
Details
04-26-2006
2.00
Mount storage bins with fuselage fasteners
Details
04-25-2006
3.00
Inventory fuselage fasteners
Details
04-24-2006
2.00
Inventory fuselage fasteners
Details
04-23-2006
6.00
Inventory fuselage
Details
04-22-2006
4.00
Inventory fuselage
Details
04-06-2006
1.00
Fuselage crates arrive
Details
SITE NAVIGATION
RV-7A Home
Category
# Logs
# Hours
All
566
2696
Avionics
13
64
Electrical and Light
32
168
Empennage
85
302
Engine
19
87
Finish
134
768
Fuselage
176
766
Miscellaneous
3
16
Panel
30
150
Propeller
11
75
Service Bulletins
11
54
Shop Supplies
1
Tools
2
Training/Educational
3
8
Wings
46
238
Copyright © 2001-2024 Matronics. All Rights Reserved.