Work Logs Found:
25
Category Work Time:
110 Hours
Date
Hours
Work Log Summary
Details
11-26-2004
3.00
Completed left elevator
Details
10-24-2004
7.00
Elevator and trim tab
Details
10-17-2004
6.00
Elevator Priming and riveting
Details
10-10-2004
4.00
Left and right elevators
Details
09-18-2004
3.00
Rudder completed
Details
09-12-2004
4.00
Riveted rudder skin to skeleton
Details
09-09-2004
3.00
Priming, Skeleton construction
Details
09-06-2004
4.00
Rudder skeleton
Details
08-05-2004
4.00
Rudder
Details
07-31-2004
3.00
Rudder stiffeners
Details
07-29-2004
12.00
VH priming and final construction
Details
07-25-2004
4.00
Spar lightener holes, skin dimpling
Details
07-20-2004
1.00
Rib Straighten & Fluting
Details
07-17-2004
6.00
Finished Horizonal Stabilizer
Details
07-15-2004
3.00
Rear spar
Details
07-13-2004
2.50
Primed Horizonal stabilizer
Details
07-08-2004
4.00
Conversion for Priming
Details
06-24-2004
4.50
Priming prep
Details
06-19-2004
6.00
Preparation for priming
Details
06-17-2004
9.00
Fitting skins
Details
06-12-2004
7.00
Front spar
Details
06-10-2004
1.00
Rear Spar assembly
Details
06-08-2004
3.00
Second box of parts
Details
06-08-2004
5.00
Rear spar construction
Details
06-07-2004
1.50
Box 1 of empenage parts have arrived
Details
SITE NAVIGATION
Contact Builder
RV7A Home
Category
# Logs
# Hours
All
114
728
Autopilot
1
6
Empennage
25
110
Fuselage
26
232
Left Tank
2
6
Right Tank
12
60
Shop Supplies
3
16
Wings
45
298