LEE'S WEB SITE
CH750 Cruzer
Landing Gear
Work Logs Found:
3
Category Work Time:
21 Hours
Date
Hours
Work Log Summary
Details
03-12-2021
5.00
Brake Lines Route
03-11-2021
8.00
Brake Line Guides Install
03-10-2021
8.00
Wheels and Landing Gear Installed