 08-17-2020
2.00
Canopy Trimming
     

 08-13-2020
2.00
Canopy Slider Jig
       

 08-13-2020
5.00
Canopy Big Cut
       

 08-09-2020
3.00
Canopy trimming
       

 08-06-2020
3.00
Canopy Slid Block
       

 08-05-2020
2.00
Canopy Frame Rear Bow
       

 08-04-2020
8.00
Canopy rails, slide block & anchor block
       

 08-01-2020
1.00
Tank attach bracket 1/4" slot and nut plate
       

 08-01-2020
2.00
Installed Aft Flooring with LP4-3 pop rivets
       

 07-19-2020
8.00
Installing canopy slide cap and fabricating side r
       

 07-07-2020
2.00
Installed Flap Fairings
       

 07-06-2020
1.00
Completed aileron trim control installation
       

 07-06-2020
1.00
Aft Throttle Quandrant
       

 07-05-2020
0.50
Fuel Tank Line Fittings
       

 07-03-2020
3.00
Installed fuel tank brackets and working on wing r
       

 06-23-2020
16.00
Rear Seat Throttle Installation
       

 06-17-2020
2.00
Tank attach bracket fabrication
       

 06-17-2020
5.00
Heater knob and bowden cable installation
       

 06-15-2020
2.00
Install Dynon Temperature Probe
       

 06-11-2020
5.00
Cut out instrument sub-panel. Anodized sub-panel.
Details
       

 06-10-2020
4.00
Baggage Door Lock
       

 06-09-2020
10.00
OP-6 Manual Aileron Trim System
       

 06-08-2020
5.00
Tie-down holders
       

 06-07-2020
8.00
Fabricating baggage door
       

 06-06-2020
3.00
Installed 2 AWG Starting Wire & 8 AWG Master Switc
       

 05-30-2020
3.00
Throttle Quantrant Installation
       

 05-30-2020
2.00
Heater Box installed on Firewall
       

 05-26-2020
2.00
Installed wiring from elevator autopilot servo to
       

 05-22-2020
3.00
Elevator Pitch Trim Servo Wiring
Details
       

 05-22-2020
3.00
ADHRS Mount
       

 05-21-2020
4.00
Dynon Static Ports Installation
Details
       

 05-20-2020
4.00
Fueslage NACA Vent Installation
       

 05-19-2020
3.00
Roll bar installed
       

 05-19-2020
6.00
Forward upper skin match-drilled
       

 05-08-2020
6.00
Installed fuel pump and plumbing to righ and left
       

 05-07-2020
2.00
Forming edge of top aft skin & debur/dimpling
       

 05-07-2020
4.00
Dimple and rivet top aft bulkheads
       

 05-06-2020
1.00
Fuselage Conduit
Details
       

 05-06-2020
2.00
Fuel valve fittings installed. Aft battery tray.
       

 05-05-2020
2.00
Debur and paint bulkhead assemblies
     

 05-03-2020
4.00
Final-drill Aft fuselage bulkheads and Aft top ski
       

 05-02-2020
4.00
Installed fuel vent lines
       

 05-01-2020
2.00
Install fuel pump
       

 04-30-2020
4.00
Dynon Pitch Installation Guide RV8 Pitch
       

 04-25-2020
4.00
Recieved new elevator F-840 Pushrod
       

 04-24-2020
7.00
Installed rudder cables. Begin assembling rudder p
       

 04-19-2020
8.00
Elevator Control System
       

 04-18-2020
4.00
Painted interior of fuselage & interior panels
       

 04-17-2020
4.00
Painted interior of fuselage & interior panels
       

 04-14-2020
2.00
Interior panels prepping for painting
       

 04-11-2020
6.00
Foot well recess and throttle quandrant cable anch
       

 04-09-2020
3.00
Alodine stiffeners and rivet to seat floors
       

 04-08-2020
6.00
Seat Floors & Flap Bearing Blocks
       

 04-05-2020
4.00
Pilots seat back
       

 04-04-2020
5.00
Fitting landing gear
       

 04-03-2020
3.00
Fitting landing gear
       

 04-02-2020
3.00
Drilling Gear Leg Brackets
       