KitLog pro

Powered By Kitlog Pro v2.0

PAUL'S WEB SITE
Work Logs Found: 50
Category Work Time: 132 Hours
 Date
Hours
Work Log Summary

Details

 05-13-2020
1.50
Rebuild throttle linkage - again

 05-12-2020
2.00
Adjest wing washout. Correct tailwheel chain.

 05-10-2020
2.50
Adjust right wing dihedral

 05-05-2020
2.50
Test fit throttle.Still needs adjustment. Adjust l

 05-03-2020
0.75
Test fit Throttle. Need spacers. Make spacers

 04-29-2020
1.50
Modift Throttle linkage - again

 04-28-2020
0.25
Test fit Throttle. No good :(

 04-27-2020
1.00
Modify Throttle linkage

 04-21-2020
0.50
Trial fit modified pedals. Interferrence with thro

 04-14-2020
2.00
Extend pedals 2". Make angle bracket for throttle

 04-08-2020
2.00
Remove pedals and throttle. Torque and safety all

 03-16-2020
3.00
Reassemble elevator and rudder. Adjust rudder peda

 03-13-2020
2.50
Reinstall pedals. Shorten Rudder cables. Remove el

 03-11-2020
2.50
Work on pedals and misc.

 03-09-2020
1.50
Misc

 12-22-2019
3.50
Complete left door. Fit Tiny Tach. Fit new fuel pu

 11-24-2019
4.50
Hanger - install kick panels. Install windscreen
       

 11-17-2019
5.00
Hanger - Fix fuel drain. Attch kick panels

 11-11-2019
4.50
Hanger - complete electrical. Zip tie, Installcomp
     

 11-08-2019
1.50
Hanger - general assembly

 11-06-2019
1.00
Hanger - General assembly

 11-03-2019
3.50
Hanger - general assembly

 10-29-2019
2.50
Hanger - Install seat adjusters
     

 10-17-2019
2.50
Hanger - Wire fuel pump. Mount pilot seat. Misc
     

 10-16-2019
3.00
Hanger - Complete bleeding brakes, Install electri
       

 10-10-2019
3.00
Hanger - general assembly

 10-08-2019
2.50
Hanger - general assembly

 10-06-2019
4.00
Hanger - General assembly

 10-03-2019
2.50
Hanger - General assembly

 10-01-2019
2.50
Hanger - Connect and adjust aileron push rods. Mou
       

 09-29-2019
3.50
Hanger - general assembly

 09-26-2019
2.00
Hanger - General assembly

 09-13-2019
3.50
Hanger - general assembly

 09-11-2019
2.50
Hanger - Attach and adjust propeller
       

 09-09-2019
3.00
Hanger - Install oiling system, add fuel, general
     

 09-08-2019
4.00
Hanger - Prep engine for starup. General assembly
       

 09-03-2019
2.50
Hanger - general assembly

 08-29-2019
2.00
Hanger - general assembly

 08-27-2019
3.50
Hanger - general assembly

 08-25-2019
3.50
Hanger - general assembly

 08-24-2019
4.00
Hanger - General Assembly

 08-15-2019
2.50
Hanger - Install Rudder and elevator stops. Fit ai

 08-12-2019
1.50
Hanger - Continue assembly

 08-10-2019
2.50
Hanger - Continue assembly

 08-08-2019
2.50
Hanger - Continue assembly

 08-06-2019
3.00
Hanger - Continue assembly

 08-02-2019
3.00
Hanger - Continue assembly

 08-01-2019
3.00
Hanger - Continue assebmly of tail feathers

 07-30-2019
3.00
Hanger - Assemble Tail feathers

 07-28-2019
5.00
Hanger - General assembly










Copyright © 2001-2024 Matronics. All Rights Reserved.