Jims RV-8
Work Logs Found: 252
Category Work Time: 533 Hours
 Date
Hours
Work Log Summary

Details

 06-03-2024
2.00
LED wiring and Canopy fit to sides
Details
       

 06-02-2024
2.30
LED lights and wiring under glare shield
Details
     

 05-26-2024
0.30
Checked the GI-260 stubs and defrost fan
Details
     

 05-22-2024
2.00
AOA display wires and edge grommets
Details
       

 05-20-2024
2.50
Electrical/Avionics Ops check #2
Details
     

 05-15-2024
1.30
Fuel Vent and Flap Sensor - continued
Details
       

 02-17-2024
0.90
Antenna spacers
Details
       

 02-11-2024
3.20
Right-angle TNC fittings assembly
Details
       

 02-10-2024
5.00
GTN-650Xi antenna securing and general work
Details
       

 02-06-2024
0.80
GTN-650Xi antenna cable routing
Details
       

 02-04-2024
2.50
CPC PIC stick attach work
Details
       

 02-01-2024
0.50
PIC stick troubleshooting with Ralph
Details
     

 01-31-2024
1.30
PIC stick CPC wired
Details
     

 01-30-2024
1.00
PIC stick wires pinned
Details
     

 01-28-2024
1.80
More PIC stick wire work
Details
     

 01-27-2024
3.50
PIC stick wires gathered and labeled
Details
     

 01-22-2024
0.50
Pilot stick CPC location
Details
       

 01-21-2024
4.10
Trim motor relay wiring
Details
       

 01-20-2024
0.90
Relay socket wiring
Details
       

 01-15-2024
1.80
Relay attachment work
Details
       

 01-14-2024
1.00
Relay socket disassembly
Details
       

 01-07-2024
1.80
Trim motor relay wiring
Details
       

 01-06-2024
2.30
Trim motor power wire
Details
       

 01-06-2024
2.00
Flap Relay troubleshooting #2
Details
     

 01-05-2024
2.30
Flap Relay troubleshooting
Details

 12-29-2023
2.10
Flap Relay wiring #3
Details
     

 12-28-2023
2.50
Flap Relay wiring (except power)
Details
     

 12-27-2023
1.80
Flap Relay wiring
Details
       

 12-18-2023
0.90
Flap Relay install
Details
       

 12-05-2023
3.80
Trim relay nutplate installs
Details
       

 11-29-2023
0.80
Pitch/Roll trim relay location
Details
       

 11-05-2023
4.10
PIC stick wiring #3
Details
       

 11-04-2023
1.60
PIC AMP Connector
Details
     

 10-29-2023
1.20
Glare shield planning #2
Details
       

 10-15-2023
1.70
AoA indicator location
Details
       

 08-16-2023
1.20
Pilot - Music Input
Details
     

 04-27-2023
0.90
Remove the electrical boxes
Details
     

 04-01-2023
2.30
The Bird is Alive!
Details
       

 04-01-2023
0.30
Switch wiring - TCW Backup Battery
Details
     

 04-01-2023
2.00
Smoke pump diagnosis
Details
       

 03-31-2023
0.50
Pilot stick install
Details
       

 03-28-2023
1.20
Turning stuff on
Details
       

 03-28-2023
1.10
G-Meter change out
Details
       

 03-28-2023
0.90
Connector - Indicator lights : Done
Details
       

 03-26-2023
1.70
Connector - Indicator lights
Details
       

 03-18-2023
0.00
Smoke oil relay wiring
Details
       

 03-18-2023
6.10
Misc stuff + more electrical
Details
       

 03-12-2023
1.60
Smoke Oil Relay wiring
Details
       

 03-11-2023
1.60
Desiccant + Smoke oil relay cogitation
Details
       

 03-07-2023
2.80
Alternator wires + tidying firewall wires
Details
       

 03-04-2023
4.80
ANL/Shunt standoff
Details
       

 02-28-2023
0.00
ANL, shunt standoff model in 3D
Details
     

 02-28-2023
3.00
ANL + shunt wiring
Details
       

 02-19-2023
1.90
ANL, Shunt layout
Details
       

 01-07-2023
4.80
Roll trim servo wiring
Details
       

 01-06-2023
1.60
Smoke Pump/Defrost Fan wiring
Details
       

 12-31-2022
0.90
Smoke Pump Wiring #1
Details
       

 12-27-2022
0.90
Elevator Trim wire continuity
Details

 12-26-2022
0.00
Pitch trim indicator wiring
Details
       

 12-26-2022
4.30
Music Input 2 installed
Details
       

 11-20-2022
1.50
Routing the GEA 24 P244 harness wires
Details
       

 11-15-2022
0.70
GEA 24, harness P244 route planning
Details
     

 11-09-2022
1.70
GMA 24 harness #3
Details
       

 10-28-2022
1.50
GI 260 : AoA wiring
Details
       

 10-15-2022
2.00
GTP-59 : OAT sensor wire connections
Details
       

 10-12-2022
0.70
GTP-59 : OAT sensor wires
Details
       

 09-17-2022
1.50
Finished the Battery wire
Details
       

 09-05-2022
2.00
Route CHT/EGT harness wires to firewall
Details
       

 09-04-2022
3.50
New battery hold down
Details
       

 09-03-2022
2.10
Lateral battery security
Details
       

 08-31-2022
1.90
Battery Cables
Details
       

 08-30-2022
0.00
Pilot LEMO installed
Details
     

 08-30-2022
2.30
Co-pilot LEMO plug finished
Details
       

 08-29-2022
1.00
Co-Pilot LEMO headset wiring work
Details
       

 08-28-2022
2.50
Nav/Strobes finished
Details
       

 08-27-2022
0.60
Transponder cable installed
Details
     

 08-27-2022
1.20
Nav/Strobe ground
Details
       

 08-26-2022
0.70
Pitch servo ground wire
Details
     

 08-25-2022
1.70
ELT Wiring to remote switch
Details
     

 08-24-2022
2.90
ELT shielded ground
Details
       

 08-21-2022
3.50
Bob visit - Day 3
Details
       

 08-20-2022
0.00
Bob visit - Day 2A
Details
     

 08-20-2022
11.60
Bob visit - Day 2
Details
       

 08-19-2022
0.00
Bob visit - Day 1A
Details
       

 08-19-2022
10.10
Bob visit - Day 1
Details
       

 08-16-2022
2.30
Nav/Strobe power wires to switch
Details
       

 08-14-2022
2.10
Nav/Strobe wiring work
Details
       

 08-13-2022
4.20
Nav/Strobe wire routing
Details
       

 08-11-2022
0.70
Bulkhead hole drilled for Nav/Strobe wiring
Details

 08-07-2022
3.00
Landing/Taxi wiring at terminal block
Details
       

 08-06-2022
2.00
Landing/Taxi and Nav/Strobe wiring routing
Details
       

 07-30-2022
7.00
Aerosun VX light wiring
Details
     

 07-16-2022
0.70
Planning next steps, Relay location options
Details
       

 07-16-2022
2.00
Electron separators
Details
       

 07-16-2022
1.50
Boost Pump, Pitot Heat and Pitot Ground wired
Details
       

 07-13-2022
0.30
Installed the fire sleeve on the pass-thru
Details
       

 07-08-2022
1.00
C/B power supply
Details
     

 07-04-2022
3.00
Panel wiring - cleanup + Fire sleeves
Details
       

 07-02-2022
1.50
C/B Bank Wiring - Finish
Details
     

 06-27-2022
1.90
C/B bank wiring - AeroLED lights
Details
       

 06-26-2022
5.50
C/B bank wiring - pitot heat wires
Details
       

 06-25-2022
5.00
C/B bank wiring
Details
       

 06-24-2022
2.90
Alternator and Starter power wire
Details
       

 06-16-2022
1.00
New Label and Re-Do
Details
       

 06-12-2022
2.00
Wire pulls
Details
       

 06-05-2022
1.40
Add Alternate Static Air switch
Details
       

 06-04-2022
4.00
Right-Side Panel Wiring #7 - Finished
Details
       

 05-31-2022
2.30
Right-Side Panel Wiring #6
Details
       

 05-30-2022
3.10
Boost pump wiring
Details
       

 05-14-2022
5.00
P-Mag switch wiring
Details
       

 05-12-2022
1.90
Wired the Bus Sense/Low volt lamp
Details
       

 05-10-2022
1.50
New Battery Bus label and install
Details
     

 05-07-2022
2.40
More Power wiring - Fuses
Details
     

 05-06-2022
1.20
CB Power wires - Labeling and organizing
Details
     

 05-01-2022
2.00
CB Power wires and stuff
Details
       

 04-26-2022
0.70
P-Mag grounds + some tidying
Details
       

 04-23-2022
4.00
CB bank - extension and organization
Details
     

 04-22-2022
1.40
Electrical - Computer work
Details
     

 04-20-2022
1.40
Right-Side Panel Wiring #5
Details
       

 04-19-2022
2.20
Right-Side Panel Wiring #4
Details

 04-16-2022
4.80
Right-Side Panel Wiring #3
Details
       

 04-12-2022
1.20
Right-Side Panel Wiring #2
Details
       

 04-10-2022
3.10
Right-Side Panel Wiring
Details
       

 04-09-2022
1.50
Electrical consult + dessicant change
Details
       

 03-27-2022
3.20
Harness power wires
Details
       

 03-19-2022
0.00
Main wiring trunk work #2, Grounds
Details
       

 03-19-2022
5.90
Main wiring trunk work #1,Rear/GIB/wing wires
Details
       

 03-19-2022
1.10
Additional reliefs
Details
       

 03-10-2022
0.70
More Fiddling with the Batt Bus
Details
       

 03-06-2022
0.00
Main Avionics Wiring Harness #2
Details
       

 03-06-2022
4.60
Main Avionics Wiring Harness #1
Details
       

 03-06-2022
2.00
Clean up shop - fiddle with batt bus
Details
       

 03-04-2022
2.10
Plastic panel washers
Details
       

 11-11-2021
2.00
Clean up, organization of wires
Details
       

 11-07-2021
3.20
Measuring Wire Lengths #2
Details
     

 10-26-2021
1.30
Finished wiring the Ebus / Relay
Details
       

 10-24-2021
1.20
Remaining Bus wiring
Details
     

 10-24-2021
2.00
Measuring wire lengths
Details
       

 10-23-2021
1.00
Relay Wiring & Flight with Greg
Details
       

 10-19-2021
2.30
Bus Wiring #4 - Bus connections
Details
       

 10-12-2021
1.20
Bus Wiring #3 - Wire keepers
Details
       

 10-10-2021
0.00
Bus Wiring #2
Details
       

 10-10-2021
6.00
Bus Wiring #1
Details
       

 10-08-2021
0.50
Remote box support riveting
Details
     

 10-07-2021
1.50
Cradle angle and aluminum sheet work
Details
     

 10-05-2021
1.50
More #2 wire securing – under console
Details
       

 10-03-2021
1.00
Gear tower conduit Adel clamps
Details
       

 10-02-2021
2.00
More #2 wire securing - forward of spar
Details
       

 09-29-2021
0.80
More #2 cable securing with additional adels
Details
       

 09-28-2021
1.50
Secure the #2 wire
Details
       

 09-09-2021
2.00
Bus Bar replacement
Details
     

 09-02-2021
1.40
Additional gear tower conduit installed
Details
       

 09-01-2021
0.90
More Labels, wire run placement
Details
       

 09-01-2021
1.00
Fun with Relays
Details
     

 08-31-2021
2.50
Electrical Pass-Thru in Firewall
Details
       

 08-29-2021
2.90
Battery Tray beef up
Details
       

 08-28-2021
2.00
CB Bus bar
Details
       

 08-27-2021
0.00
Electrical Wiring Decisions - Failure Modes
Details

 08-27-2021
10.00
Electrical Wiring Decisions - A
Details

 08-21-2021
1.00
Switched CBs for Load Leveling
Details
       

 08-21-2021
2.50
Battery Contactor wire
Details
       

 08-20-2021
0.50
Starter Contactor connector test
Details
     

 08-19-2021
1.30
Load leveling and wire distances
Details

 08-19-2021
1.00
Angle Riveted to Battery tray
Details
       

 08-18-2021
1.40
Battery Tray support angle
Details
     

 08-17-2021
1.50
2AWG battery contactor wire crimped
Details
       

 08-15-2021
3.50
Fuse panel consolidation & Electrical review
Details
       

 08-15-2021
2.40
Bundling and tidying the wires
Details
       

 08-11-2021
1.80
LED cockpit lighting removal + Bob stuff
Details
       

 07-28-2021
1.10
Panel Circuit Breakers
Details
       

 07-26-2021
1.40
Panel Switches and Lights back in
Details
     

 07-25-2021
2.20
Battery Ground
Details
       

 07-24-2021
2.00
Right side Switch install and lacing initiation
Details
       

 07-24-2021
1.70
Right side console labels
Details
     

 07-24-2021
1.30
Pilot LEMO plug drilled and labels
Details
       

 07-22-2021
0.60
Pilot LEMO hole
Details
       

 07-21-2021
2.00
LEMO drilling for Rear Seater
Details
       

 07-20-2021
1.10
Prep for LEMO plug drilling - Part 1
Details
       

 07-17-2021
1.00
Rear seat headset location of wire run
Details
     

 07-17-2021
1.50
More panel labels
Details
       

 07-15-2021
2.20
Panel Labels
Details
       

 07-05-2021
2.30
Panel label final test fit
Details
       

 07-04-2021
8.50
Labels in PowerPoint
Details
       

 06-30-2021
2.70
Panel lettering re-design
Details
     

 06-17-2021
1.70
Dimple the Doubler, panel light test
Details
     

 06-06-2021
2.50
ILS Antenna Doubler
Details
       

 05-23-2021
3.90
Side & Other Panel Labels
Details
       

 05-21-2021
1.80
Applying Panel Labels
Details
       

 05-20-2021
3.00
Panel labels - Final draft
Details
       

 05-18-2021
1.10
Finish Battery Tray + Battery Contactor
Details
       

 05-14-2021
1.00
Test run of the 2 AWG wire
Details
       

 05-08-2021
5.00
Panel labels - more testing
Details
       

 05-06-2021
1.30
Panel Labels - Testing
Details
     

 03-09-2021
0.50
Re-install the Regulators
Details
       

 02-22-2021
1.00
Remove the LR3C Voltage Regulators
Details
       

 12-14-2020
1.50
Nav / Strobe wingtip wiring
Details
       

 12-13-2020
2.30
Wingtip lighting terminals
Details
       

 11-15-2020
1.50
Pitot Temps
Details
       

 11-14-2020
2.00
Gap 26 heated pitot test
Details
       

 09-24-2020
1.00
Ran fishing line for future wires
Details
       

 09-15-2020
1.50
Electrical discussion + two holes drilled
Details
       

 06-28-2020
2.00
Labels for electrics
Details
       

 04-12-2020
0.70
Misc items and flip the fuse back over
Details
       

 04-11-2020
2.00
Wired up the extra rear cockpit lights
Details
       

 04-04-2020
4.00
Additional Lights in front Cockpit
Details
     

 03-10-2020
1.90
more adhering and drilled hole
Details
       

 03-05-2020
0.60
Adhering the LED light ends/wires
Details
       

 03-04-2020
1.00
Move up the two LR3C-14's
Details
       

 03-03-2020
0.90
Longer buss screws (20)
Details
       

 02-29-2020
2.50
Defrost fan – initial wiring
Details
     

 02-19-2020
1.00
Clean up the shop
Details
       

 02-18-2020
1.00
Attaching hard points for wire wraps
Details
     

 02-17-2020
2.00
LED experimenting (messing around)
Details

 02-16-2020
3.00
Finish rear cockpit lights
Details
       

 02-15-2020
3.50
Rear cockpit lighting
Details
     

 02-15-2020
3.50
Rear baggage lighting
Details
       

 02-15-2020
3.00
Electrical – Rheostat and controller “design”
Details
     

 01-24-2020
0.50
Baggage compartment lighting
Details

 01-23-2020
1.50
Installing the Rear cockpit light rheostat
Details
       

 01-20-2020
1.50
Finished wiring the front cockpit lights
Details
       

 01-18-2020
3.00
Gluing the front cockpit lights
Details
       

 01-16-2020
1.70
Last two fuse busses installed
Details
       

 01-14-2020
3.00
Wiring the front cockpit lights
Details
       

 01-12-2020
1.70
Solder and install the dimmers
Details
       

 01-11-2020
4.50
Front cockpit lighting
Details
       

 01-11-2020
1.50
Dimmer work on the 10-2 switch
Details

 01-06-2020
1.20
Wiring the 700-10-2 DPDT switch
Details
       

 01-04-2020
2.00
Routing path of aft strobe wires
Details

 01-03-2020
2.00
Right console panel hole drilling and installing
Details
     

 01-02-2020
2.40
Finished front seat heat wiring
Details
       

 01-01-2020
0.50
Smoke system pump and front seat heat
Details
       

 12-31-2019
2.00
Wiring the Rheostat + solder
Details
       

 12-27-2019
2.00
“Final” cockpit lighting decisions
Details

 12-23-2019
2.50
Making Garmin boxes and mounting to panel
Details
       

 12-21-2019
1.50
switch layout decisions
Details
     

 12-19-2019
2.00
More cockpit lighting work
Details
       

 12-16-2019
1.50
Interior cockpit lighting
Details
       

 12-04-2019
1.60
Front seat heat
Details
       

 11-19-2019
1.00
Molex on the rear seat heat connections
Details
       

 11-16-2019
3.50
B. Aft Seat heat & USB installation
Details
       

 11-16-2019
5.00
A. Molex connections - AeroLED's
Details
       

 11-13-2019
3.00
Rear seat hinge and GIB ergonomics
Details
       

 11-09-2019
1.00
molex work - need better crimper
Details
       

 11-07-2019
1.70
Wired up the first appliance - Pilot USB
Details
       

 11-03-2019
1.00
Installed the first electrical device – pilot USB
Details
       

 10-22-2019
1.00
Wire label and storage
Details
       

 10-14-2019
2.00
Switches and switch locations
Details
       

 10-10-2019
2.00
Aux power supply install
Details
       

 09-29-2019
1.50
Beginning the Electrical install
Details
       

 09-25-2019
0.50
B and C Electrical order inventory
Details
       

 09-24-2019
17.00
Final electrical decision making and order prep
Details
       

 08-03-2019
1.00
Talked avionics & electrical with Walt
Details
     