06-22-2019
|
2.00
|
Drilled Right Fuel Tank
|
Details
|
|
|
06-20-2019
|
1.00
|
Installing Replacement Tank Right Wing
|
Details
|
|
|
05-28-2019
|
2.00
|
Aileron Plugs
|
Details
|
|
|
05-26-2019
|
2.00
|
Balancing Ailerons
|
Details
|
|
|
05-24-2019
|
2.00
|
Riveted Handholes Right Wing
|
Details
|
|
|
05-19-2019
|
2.50
|
Riveting Bottom Skin Right Wing
|
Details
|
|
|
05-01-2019
|
3.00
|
Drilled Aft Spar to Bottom Skin
|
Details
|
|
|
04-18-2019
|
3.00
|
Riveting Bottom Skin Right Wing
|
Details
|
|
|
04-03-2019
|
1.00
|
Riveting Bottom Skin on the Right Wing
|
Details
|
|
|
03-17-2019
|
4.00
|
Dimpled Leading Edge of bottom Right Wing Skin
|
Details
|
|
|
03-16-2019
|
4.00
|
Clecoed and Drilled Bottom Right Skin
|
Details
|
|
|
03-13-2019
|
2.00
|
Installed Hand Hole Doublers, Right Wing
|
Details
|
|
|
03-11-2019
|
2.00
|
Installed Bottom Skin, Right wing
|
Details
|
|
|
03-10-2019
|
3.00
|
Gap Seal Adjustment to Wing Contour
|
Details
|
|
|
02-20-2019
|
1.00
|
Riveted Gap Seal to Right Wing
|
Details
|
|
|
02-19-2019
|
2.00
|
Finished Riveting Top Skin Right Wing
|
Details
|
|
|
02-18-2019
|
2.50
|
Rivets plus Gap Seal, Right Wing
|
Details
|
|
|
02-17-2019
|
4.50
|
Drilled Rear Right Spar
|
Details
|
|
|
02-11-2019
|
2.00
|
Riveting Top Skin, Right Wing
|
Details
|
|
|
02-06-2019
|
2.00
|
Riveting Top Skin on Right Wing
|
Details
|
|
|
01-28-2019
|
2.00
|
Began Riveting Top Skin ,R. Wing
|
Details
|
|
|
01-22-2019
|
4.00
|
Dimpled wing skin and countersank D -Spar
|
Details
|
|
|
01-21-2019
|
4.50
|
Drilled Top Skin to D Spar Right Wing
|
Details
|
|
|
01-18-2019
|
1.50
|
Installing Top Skin to Right Wing
|
Details
|
|
|
01-06-2019
|
3.00
|
Ran Wiring for Right Wing Lights
|
Details
|
|
|
01-05-2019
|
3.00
|
Aileron Cable, Teleflex & Wire Grommets R. Wing
|
Details
|
|
|
01-03-2019
|
3.00
|
Installed Bell Cranks in Right Wing
|
Details
|
|
|
12-14-2018
|
3.00
|
Riveted Ribs &Spars on Right Wing
|
Details
|
|
|
12-13-2018
|
3.00
|
Relief Drilled in R. Root Ribs, Bolted Truss to Re
|
Details
|
|
|
12-03-2018
|
4.00
|
Assembled & Clecoed Right Wing Frame
|
Details
|
|
|
11-29-2018
|
4.00
|
Laid out ribs and prepped flap and aileron hinges.
|
Details
|
|
|
11-28-2018
|
3.00
|
Connecting Right Forward Spar to Wing Truss
|
Details
|
|
|
11-27-2018
|
1.00
|
Deburring Wing Ribs
|
Details
|
|
|
11-26-2018
|
3.00
|
Started Right Wing Construction
|
Details
|
|
|
10-15-2018
|
2.00
|
Began plumbing Fuel tank in Left Wing
|
Details
|
|
|
07-29-2018
|
1.50
|
Riveted all Hand Holes--Bottom Left Wing
|
Details
|
|
|
07-28-2018
|
5.50
|
Drilled and Riveted Bottom Skin--Left Wing
|
Details
|
|
|
07-25-2018
|
3.50
|
Continued Riveting Bottom Skin on Left Wing
|
Details
|
|
|
07-24-2018
|
3.00
|
Rivet Bottom Skin on left wing
|
Details
|
|
|
07-23-2018
|
2.00
|
Clecoed Bottom Skin Back in Place
|
Details
|
|
|
07-22-2018
|
5.00
|
AA 185--Aileron Bell Cranks
|
Details
|
|
|
07-09-2018
|
5.50
|
Drilled and Riveted Bottom Skin-Left Wing
|
Details
|
|
|
05-15-2018
|
4.00
|
Deburring & Countersinking D-Spar & Bottom Skin
|
Details
|
|
|
05-14-2018
|
2.00
|
Drilled Leading Edge Bottom Skin to D-Spar
|
Details
|
|
|
05-06-2018
|
4.00
|
Fitting Bottom Skin for riveting
|
Details
|
|
|
05-05-2018
|
4.00
|
Cinco de Mayo!!!
|
Details
|
|
|
05-03-2018
|
3.50
|
Flipped Wing and Set Bottom Skin in Place
|
Details
|
|
|
04-30-2018
|
3.00
|
Riveted Gap Seal, Finished Top Skin
|
Details
|
|
|
04-28-2018
|
4.00
|
Riveted Top Skin and fit up Gap Seal
|
Details
|
|
|
04-27-2018
|
3.00
|
Drilled aft Spar for Top Skin & Gap Seal
|
Details
|
|
|
04-25-2018
|
2.00
|
Pulled Three more rows of Rivets in Left Wing
|
Details
|
|
|
04-24-2018
|
4.00
|
Pulled Six more Rows of Wing Rivets, Left Wing
|
Details
|
|
|
04-22-2018
|
2.00
|
Pulled 4 Rows of Rivets in Top Skin, Left Wing
|
Details
|
|
|
04-18-2018
|
3.50
|
Began Riveting Top Skin Left Wing
|
Details
|
|
|
04-17-2018
|
3.50
|
Dimpled top Wing Skin & Countersinked D-Spar
|
Details
|
|
|
03-30-2018
|
4.00
|
Drilled top Skin to D-Spar leading edge
|
Details
|
|
|
03-20-2018
|
4.00
|
Drilled Relief in Root Ribs & Installed Top Left S
|
Details
|
|
|
03-19-2018
|
2.50
|
Installed Left Wing Stringers
|
Details
|
|
|
03-18-2018
|
1.50
|
Checked Left Wing for Twist
|
Details
|
|
|
03-17-2018
|
3.50
|
Wired Left Wing & Ran Pitot Tubing
|
Details
|
|
|
03-04-2018
|
1.50
|
Drilled Ribs and installed Grommets
|
Details
|
|
|
02-28-2018
|
3.00
|
Safety Wired Bell Cranks & Installed Cables
|
Details
|
|
|
02-27-2018
|
4.00
|
Riveted Ribs to Spars and Bolted in Bell Cranks
|
Details
|
|
|
02-26-2018
|
4.00
|
Straightened Ribs and Adjusted Fit to D-Spar
|
Details
|
|
|
02-23-2018
|
4.50
|
Riveted Hinges and Clecoed Ribs to Spars
|
Details
|
|
|
02-22-2018
|
4.00
|
Preparing Ribs To Accept Flap & Aileron Hinges
|
Details
|
|
|
02-19-2018
|
5.00
|
Fluted Ribs, Deburred aileron & flap hinges
|
Details
|
|
|
02-13-2018
|
4.00
|
Laid out Left Wing Spar and Ribs. Began Fluting R
|
Details
|
|
|
02-11-2018
|
3.00
|
Preping Wing Trusses
|
Details
|
|
|
02-03-2018
|
3.00
|
Assembled Bell Cranks
|
Details
|
|
|
01-28-2018
|
3.00
|
Riveted Doublers on all four Spars
|
Details
|
|
|
01-26-2018
|
4.00
|
Installing Doublers on Wing Spars
|
Details
|
|
|
01-23-2018
|
4.00
|
De-burring Wing Spars
|
Details
|
|
|
01-21-2018
|
4.00
|
Right Flap Finished
|
Details
|
|
|
01-17-2018
|
1.50
|
Left Flap Finished
|
Details
|
|
|
01-12-2018
|
4.00
|
Riveted Left Flap
|
Details
|
|
|
01-09-2018
|
2.00
|
Assembled Left Flap and preped parts for right fla
|
Details
|
|
|
01-08-2018
|
3.00
|
Right Flap Assembly
|
Details
|
|
|
01-07-2018
|
1.00
|
Began work on flaps.
|
Details
|
|
|
12-27-2017
|
2.00
|
Completed Left Aileron
|
Details
|
|
|
12-07-2017
|
2.00
|
Riveting left aileron skin.
|
Details
|
|
|
11-27-2017
|
3.00
|
Drilling Right Aileron Skin and Spar then Completi
|
Details
|
|
|
11-18-2017
|
4.50
|
Deburring and installing aileron spars.
|
Details
|
|
|
11-12-2017
|
1.50
|
Clecoing left aileron together
|
Details
|
|
|
11-09-2017
|
2.00
|
Aileron-deburing, drilling hinges,hand holes.
|
Details
|
|
|
11-06-2017
|
3.00
|
Worked left Aleron. Bob Schoen dropped in today.
|
Details
|
|
|
11-05-2017
|
1.00
|
Laid out ribs for left aleron.
|
Details
|
|
|
11-04-2017
|
3.00
|
Installed inspection ports on left aleron.
|
Details
|
|
|
11-03-2017
|
2.00
|
Finished parts inventory and demolished shipping c
|
Details
|
|
|
11-02-2017
|
2.00
|
Inventoried parts, many parts!
|
Details
|
|
|
10-17-2017
|
2.00
|
Unpacking wing kit crate.
|