Leos Web Site
RV-10
Electrical
Work Logs Found:
57
Category Work Time:
419 Hours
Date
Hours
Work Log Summary
Details
09-03-2019
30.00
Continue configuring the G3X communication channel
Details
08-10-2019
15.00
Debug G3X and correct minor issues
Details
03-12-2019
1.00
Terminate sensor wires at the GEA24
Details
03-11-2019
2.00
Battery Shunt
Details
01-27-2018
3.00
Main electrical leads and ELT test wire
Details
01-26-2018
8.00
Debug and install MP3 Stereo and CO detector
Details
01-15-2018
10.00
Install switch plates
Details
01-05-2018
20.00
Switch plate swap
Details
01-01-2018
4.00
install switch plate backlights
Details
12-31-2017
4.00
Wire the Seat Heater/Door Indicator switchplate
Details
12-17-2017
8.00
Switch plates
Details
11-24-2017
10.00
Install GTN650 tray and connectors
Details
10-07-2017
3.00
add new buss bar in rear
Details
08-25-2017
10.00
working back along the harness with integration
Details
08-12-2017
15.00
install headset jacks and USB outlets to center co
Details
08-11-2017
10.00
wire harness integration into main power distribut
Details
08-09-2017
4.00
PTT integration, Heater tube
Details
08-07-2017
20.00
integrating the harness into the aircraft
Details
08-04-2017
15.00
construct the wire harness
Details
08-02-2017
15.00
wire harness continued
Details
07-31-2017
60.00
develop detailed design for electrical
Details
07-04-2017
15.00
installed Ardunio and servos
Details
11-05-2016
8.00
Overhead switch backlighting
Details
10-30-2016
3.00
Footwell lighting
Details
10-29-2016
6.00
Defrost fans, IP Brow light, Overhead map/reading
Details
10-23-2016
6.00
wiring the overhead
Details
10-16-2016
4.00
Finish kit on the way, Footwell lighting 2 years
Details
09-02-2016
6.00
wire runs and install tunnel fan
Details
08-22-2016
3.00
VPX configuration
Details
08-20-2016
6.00
Master switch group install
Details
07-22-2016
3.00
switch and backlighting
Details
07-20-2016
1.00
switch work and remodeling delays
Details
05-16-2016
4.00
Switch back lighting
Details
04-25-2016
1.00
switch plates
Details
04-24-2016
4.00
Electrical diagrams for switch groups
Details
04-15-2016
4.00
Prewire overhead switch plate
Details
04-12-2016
4.00
Switch plate layut
Details
04-08-2016
1.00
Fuel pump, key switch wiring
Details
04-06-2016
5.00
Fly LED controler mounting and wiring
Details
03-21-2016
2.00
reworked sub buss panel and ran wires
Details
02-25-2016
2.00
mounted tail strobe
Details
02-21-2016
2.00
mounted LED tail strobe
Details
02-19-2016
4.00
LED Readinf ligh holders
Details
02-16-2016
6.00
Working on the VPX configuration
Details
02-14-2016
4.00
rudder trim wiring and set up
Details
02-13-2016
6.00
LED tail strobe
Details
02-09-2016
1.00
ordered parts for electrical etc..
Details
01-30-2016
2.00
checking out the switches
Details
01-19-2016
6.00
prewire switch panels
01-17-2016
4.00
electrical content, layout and switches
Details
01-02-2016
5.00
Fly LED assembly
Details
12-31-2015
5.00
Install grips and wiire trim switches
Details
12-21-2015
6.00
main power leads and VPX ro insallation
Details
12-16-2015
0.00
More electrical archetecture
Details
12-15-2015
6.00
Refine electrical main power distribution design
Details
12-07-2015
2.00
elevator trim wire
Details
12-05-2015
5.00
Electrical Planning
Details
SITE NAVIGATION
Contact Builder
RV-10 Home
Category
# Logs
# Hours
All
465
3762
Avionics
9
55
Avionics
10
48
Canopy
9
55
Commentary
3
20
Controls
14
72
Cowel
4
48
Doors
17
100
Doors
30
263
Electrical
10
82
Electrical
57
419
Empennage
10
98
Engine
24
224
Fuselage
52
355
Horz Stab and Elevat
6
36
Instrument Panel
57
419
Interior
14
72
Interior
30
263
Misc.
6
57
Miscellaneous
6
57
None
2
Overhead
8
49
Painting
9
307
Prop
1
20
Stabilizer/Elevator
10
82
Tailcone
17
100
Things learned
8
49
Vert Stab and Rudder
3
20
Vert Stab/Rudder
6
36
What have I learned
2
2
Wings
31
354