LARRY'S WEB SITE
Sopwith Baby
Empennage
Work Logs Found:
14
Category Work Time:
59 Hours
Date
Hours
Work Log Summary
Details
06-26-2019
3.20
Installed Lower Braces on Horizontal Stabilizer
Details
06-24-2019
4.10
Final Installation of The Elevator
Details
06-23-2019
2.70
Final Assembly of Horizontal and Vertical Stabiliz
Details
06-20-2019
1.20
Started Mounting the Horzintial Stabilizer
Details
08-23-2016
4.00
Tail Light Bracket and Rudder Extension
Details
07-09-2016
6.00
Correct Horizonatal Stabilizer Supports
Details
07-02-2016
4.50
Trial Fitting of the Horizonal Stablizer and Rudde
Details
07-02-2016
2.50
Construction of the Cable Bracing on the Tail
Details
03-02-2016
3.50
Vertical Stabilizer
Details
02-27-2016
7.00
Horizontal Stabilizer
Details
02-22-2016
6.50
Elevator Completion
Details
02-20-2016
5.00
Construction of the Elevator
Details
02-12-2016
4.00
Finish the Rudder Frame
Details
02-08-2016
5.00
Construction of the Rudder
Details
SITE NAVIGATION
Contact Builder
Sopwith Baby Home
Category
# Logs
# Hours
All
890
2613
Avionics
61
155
Brake System
21
56
Component
122
253
Configuration
5
15
Controls
6
13
Design
7
12
Documentation
61
275
Electrical
57
125
Empennage
14
59
Engine
64
150
Fabric Covering
94
310
Fuselage
97
376
Inspections
5
17
Miscellaneous
13
33
Painting
92
272
Prop
3
3
Shop Supplies
3
6
Testing
7
13
Wheels
22
60
Wings
136
410