08-16-2016
|
4.00
|
Finished adjusting and installing deice brush bloc
|
|
|
|
08-09-2016
|
8.00
|
Designing abracket to hold the Brush Block
|
|
|
|
08-03-2016
|
10.00
|
Hooked up deice controllers
|
|
|
|
08-02-2016
|
8.00
|
Ran and hooked the deice grounds
|
|
|
|
07-29-2016
|
8.00
|
Install left wing faring and left wing inboard dei
|
|
|
|
07-21-2016
|
2.00
|
Defined heater power locations.
|
|
|
|
07-13-2016
|
4.00
|
Routed and connected the wing power wires
|
|
|
|
07-12-2016
|
2.00
|
Continue connecting deice wires
|
|
|
|
07-11-2016
|
5.00
|
Install deice alternator
|
|
|
|
05-18-2016
|
7.00
|
Installed the deice electronics and hooked up tail
|
|
|
|
05-17-2016
|
8.00
|
Constructed shelf and installed tail deice control
|
|
|
|
05-13-2016
|
8.50
|
Continue pulling wires for Deice system
|
|
|
|
05-12-2016
|
6.50
|
Started wiring up the deice electrics
|
|
|
|
03-14-2016
|
4.00
|
Windshield deice and vor ant
|
Details
|
|
|
03-10-2016
|
6.00
|
Install windshield deice tank
|
|
|
|
02-22-2016
|
2.00
|
Construct a wind deflector for the spray bar
|
|
|
|
04-21-2015
|
2.00
|
Complete installing deice connectors on outboard l
|
|
|
|
04-20-2015
|
7.00
|
Installed two of three deice connectors
|
|
|
|
04-15-2015
|
5.50
|
Made the R wing landing light cover
|
|
|
|
03-09-2015
|
8.50
|
Reposition L outboard deice terminal
|
|
|
|
03-04-2015
|
2.50
|
Installed R outside horz stab deice terminal and e
|
|
|
|
03-02-2015
|
4.00
|
Installed the two inner deice terminals on the Hor
|
|
|
|
02-27-2015
|
2.00
|
Finish installing one Horz deice power terminal
|
|
|
|
02-23-2015
|
2.00
|
Begin install R outboard Horz stab deice terminal
|
|
|
|
02-18-2015
|
4.00
|
Wired up deice terminals in the L wing Outboard
|
|
|
|
02-13-2015
|
4.00
|
Made R wing deice controller inspection port
|
|
|
|
02-06-2015
|
6.00
|
Installed 3 of 4 L wing power connectors
|
|
|
|
02-05-2015
|
2.00
|
Started installing wing connector studs
|
Details
|
|
|
02-03-2015
|
2.00
|
Layout terminal position and shape first termina
|
|
|
|
02-02-2015
|
2.00
|
Started experimenting on scrap with cutting holes
|
|
|
|
01-23-2015
|
8.00
|
Filled hole for left landing light
|
Details
|
|
|
01-09-2015
|
7.00
|
Installrd the Horizontal stab deice controller bra
|
Details
|
|
|
01-05-2015
|
6.00
|
Make Wing controller brackets
|
Details
|
|