KitLog pro

Powered By Kitlog Pro v2.0

Darrel's Kitfox - SS7
Work Logs Found: 40
Category Work Time: 121 Hours
 Date
Hours
Work Log Summary

Details

 07-01-2024
2.90
Fabricated and rough install elevator fences
Details
       

 07-11-2023
5.10
Finished HT and started the end of the canopy
Details
       

 07-09-2023
1.30
Primed and de-burred HT
Details
 

 07-06-2023
3.10
Final size rivet holes drilled
Details
     

 06-30-2023
2.00
SED issues
Details
     

 06-25-2023
3.00
Set up HS for final riveting
Details
     

 06-24-2023
3.50
Fitted the skins to the HS and fuselage
Details
       

 06-23-2023
1.10
Verified and rough installed HS forward spars
Details
 

 06-22-2023
2.20
Installed HS spar
Details
       

 06-21-2023
2.10
HS spar rough mounted
Details
 

 06-20-2023
4.00
Do over on HT inside ribes
Details
 

 01-22-2023
4.00
More work on the canopy frame
Details
 

 01-15-2023
2.10
Installed the hinge and restraing cable
Details
     

 12-26-2022
1.00
HT Twist issue
Details
 

 12-24-2022
3.20
Finished the Horizontal Stabilizer
Details

 12-22-2022
3.70
Rough install the elevator drive weldment assembly
Details
       

 12-20-2022
2.90
Rough install elevators
Details
 

 12-19-2022
1.50
Begin fitting the elevator
Details

 12-14-2022
4.10
Intitial assembly right elevator
Details
     

 12-13-2022
4.20
HT riveting completed
Details
 

 12-12-2022
4.70
Primer, fitting and aligning
Details

 12-11-2022
4.60
Deburring and more fitting
Details
 

 12-09-2022
3.00
Bracket fabrication
Details
     

 12-06-2022
5.50
Finished rough install of HT skins
Details
     

 12-04-2022
5.30
Began rough fitting the full HT
Details
       

 12-03-2022
4.10
Completed HT spar and rough installed
Details
 

 12-02-2022
2.10
Began fitting HT spar components
Details

 12-01-2022
2.00
HT Progress
Details
       

 11-30-2022
3.00
Began work on the horizontal stabilizer
Details

 10-02-2022
5.80
Completed rudder plus more
Details
       

 09-28-2022
2.30
Began assembly of the rudder
Details

 08-12-2022
1.30
Installed bottom rudder rib
Details

 08-11-2022
3.10
Began assembling the rudder
Details
 

 08-08-2022
3.50
Rudder started
Details
 

 05-08-2022
1.90
Completed tail cone assembly
Details
     

 05-07-2022
2.30
Begin debur, prime and final rivet operation
Details
       

 04-29-2022
2.10
Enlarged rivet holes in tail cone
Details
 

 04-16-2022
3.50
More on tail cone
Details
 

 04-14-2022
2.80
Fitted banjo to tail cone
Details
     

 04-05-2022
1.10
More detail work on VT spar
Details










Copyright © 2001-2024 Matronics. All Rights Reserved.