Norris's RV Construction
Work Logs Found: 108
Category Work Time: 464 Hours
 Date
Hours
Work Log Summary

Details

 08-24-2015
4.00
Set up and sand wing for paint.

 08-14-2015
4.00
Finished R. wing tip
     

 08-13-2015
4.50
Continue working on R. wing tip

 08-12-2015
4.50
Continue working on bonding and sanding R. wingtip

 08-10-2015
1.00
Installing lens in R wingtip
     

 08-03-2015
3.00
Complete R wing riveting. Work on R. wing tip.

 07-31-2015
4.00
Finish riviting on bottom skin and work on wing ti

 07-30-2015
3.00
Riveting R. wing bottom skin

 07-29-2015
5.50
Install plexiglass on Left wingtip. Start R. wingt
       

 07-28-2015
7.00
L. wing tip. Landing and position light and attach
     

 07-27-2015
3.00
Continue riveting bottom skin

 07-16-2015
5.00
Started riveting R. wing outside bottom skin
     

 07-15-2015
3.00
Begin installing the Right wing botto
     

 07-14-2015
2.50
Install Aileeron and flap gap fairing

 06-25-2015
3.00
Filling and sanding the L wing tip
     

 06-24-2015
3.00
Continue fiberglassing plus work on R wing wiring

 06-23-2015
1.00
Fiberglassing in new (larger) light cutout
     

 06-17-2015
3.00
Fitting L wing tip and fitting landing light conve

 06-16-2015
7.00
Finished and installed all aileron push rods
       

 06-15-2015
2.00
Continue makingaileron push pull rods

 06-12-2015
3.00
Continued making aileron pushrods

 06-11-2015
1.50
Started making the aileron push rods.

 06-11-2015
5.00
Finally got the aileron clamped and riveted
     

 06-10-2015
6.00
Riveting R aileron

 06-09-2015
7.00
Working on Right aileron

 06-05-2015
5.00
Completed the Left Aileron
     

 06-04-2015
7.00
Half way through the left aileron

 06-03-2015
5.00
Assemble both ailerons
     

 06-02-2015
2.00
Started on the ailerons

 06-02-2015
6.00
Completed both flaps
     

 06-01-2015
6.00
R. wing flap - assembled, drilled, disassembled,de

 05-29-2015
2.00
Finish riveting the Left Flap
     

 05-28-2015
4.00
Continue riveting the L wing flap
     

 05-27-2015
6.00
Started riveting the flap together

 05-26-2015
2.50
countersinking and dimpling L wing flap
     

 05-15-2015
7.00
Working on assemblying part for the flaps
     

 05-14-2015
2.00
Preping parts for flaps

 05-12-2015
1.50
Preping parts

 05-11-2015
4.00
Install R. wing tank on the right wing spar.
       

 05-06-2015
5.00
Riveted the back and Z brackets on the R fuel tank

 05-05-2015
7.00
Finished installing ribs and fuel tank level float
     

 05-04-2015
3.50
Finished riveting in all the ribs except the inboa
     

 05-01-2015
3.00
Rivet ribs in R fuel tank

 04-30-2015
6.50
R. fuel tank - rivet flanges, fuel cap, and fuel d
       

 04-23-2015
3.00
dimpling fuel tank skin and preparing parts.

 04-22-2015
7.00
Preping parts for the R. fuel tank

 04-21-2015
1.50
Rivet the R. outboard leading edge to the main spa
     

 04-21-2015
1.50
Prep R wing leading edge for riveting to wing.

 04-17-2015
6.00
Riveted R. wing outboard leading eadge
     

 04-16-2015
6.00
Preping R outboard leading edge for riveting

 04-14-2015
7.50
Rivet top skin to R. Wing. cleko outboard forward.
       

 04-13-2015
8.00
R. wing top skin preped and ready to rivet
     

 04-10-2015
2.50
Finished riveting the rear spar to the R. wing
     

 04-09-2015
4.50
Prepare and cleko rear spar to R. wing
     

 04-07-2015
5.00
Finished rib install. Made parts for rear spar.

 04-06-2015
2.00
bolt and rivet ribs to main spar
     

 04-03-2015
2.50
Install ribs in left wing
     

 04-02-2015
3.00
Preping ribs for install to main spar

 04-01-2015
7.00
Finish readying spar and start readying ribs
     

 03-31-2015
4.50
Install nutplates and counersink R. wing main spar
       

 03-27-2015
3.00
R wing spar J strips and countersinking

 03-26-2015
2.50
Finish L wing. Start on R. wing spar

 03-25-2015
2.00
Finished l wing
     

 03-24-2015
6.50
Continue riviting on the bottom skin - left wing
     

 03-23-2015
8.00
Pitot static and begin riveting lower skin
Details
     

 03-13-2015
3.00
Dimple outer lower wing skin and readfy for riveti

 03-10-2015
4.00
Start dimpling bottom skins and design AHRS base.
Details

 03-06-2015
8.00
Started preparing the bottom skin for install
     

 02-20-2015
4.00
Attach fuel tank to left wing

 02-19-2015
7.00
Wing leading edge
Details
     

 02-18-2015
4.00
Riveting the L wing outboard leading edge
     

 02-06-2015
1.00
Final work on Left wing tank. Next - install on wi

 02-05-2015
1.00
Pressure test the left wing tank. Tested OK.
     

 02-03-2015
2.00
Repaired Leak in Left wing fuel tank

 02-02-2015
2.00
Testing fuel tank for leaks and found one.

 01-30-2015
8.00
Finish sealing the L tank
     

 01-29-2015
6.00
Continue riveting and sealing the L fuel tank
     

 01-28-2015
3.00
Continue riveting L wing tank

 01-27-2015
8.00
Sealing L wing tank

 01-22-2015
6.50
Installed access plate and built a work table
Details
       

 01-12-2015
3.50
Dimpling the tank skin.

 01-08-2015
6.00
Continue preparing parts for the L wing

 01-07-2015
6.00
prep of Zee subassembly, j channels L wing tank
     

 01-06-2015
3.50
Continue prepping parts ofr the L fuel tank
     

 01-05-2015
3.00
prepare ribs for R wing fuel tank

 01-02-2015
8.00
Prepraring the L forward wing skins

 12-31-2014
2.00
Continue preping L Outboard forward ribs

 12-29-2014
8.50
Finish riveting Top L wing skin
     

 12-26-2014
5.00
Rivety most of top skin on L wing
       

 12-24-2014
5.00
Started preparing outboard leading edge of L wing

 12-19-2014
3.00
Finished dimpling and preping. Cleko'd skins on.
Details
       

 12-18-2014
2.00
continue prep and dimple

 12-17-2014
4.00
prep and dimple upper skins

 12-16-2014
7.00
Prepare L wing top skin for installation
     

 12-15-2014
5.00
L wing rear spar

 12-15-2014
2.50
Install left wing rear spar
     

 12-12-2014
6.00
Preping the left wing rear spar

 12-11-2014
4.00
Bolted and rivited aft ribs to L main spar
     

 12-10-2014
7.00
install grommets and start rib install

 12-09-2014
5.50
Finish rib prep and install on mai
     

 12-08-2014
4.50
Preping ribs

 12-04-2014
4.50
Finished L main spar and started wing ribs.
Details

 11-19-2014
1.00
Finished installing nutplates on L main spar
       

 11-17-2014
1.50
Coutersinking and start riviting nut plates

 11-05-2014
4.00
Countersinking rivet and screw holes in the left s
     

 11-04-2014
3.50
Finish match drill J strips on left wing. Drill #4

 10-31-2014
1.50
Start match drill J strips

 10-30-2014
5.00
Inventory and store wing parts and start
     