Pauls Web Site
RV-6A
Fuselage
Work Logs Found:
94
Category Work Time:
384 Hours
Date
Hours
Work Log Summary
Details
08-04-2019
40.00
Ready for the DAR inspection
Details
08-03-2019
4.00
Determined weight and balance.
Details
06-29-2019
8.00
Aircraft on gear
Details
06-09-2019
2.00
Removed gear
Details
06-02-2019
1.00
Installed the nameplate
Details
05-12-2019
2.00
Rudder cable fairings
Details
03-17-2019
8.00
Installing fuselage access door
Details
03-11-2019
3.00
Finished skin over avionics
Details
03-10-2019
7.00
Installing top skin
Details
03-09-2019
3.00
Getting top skin ready to install
Details
03-07-2019
2.00
Cut access door behind firewall
Details
02-19-2019
2.00
Oil door and firewall insulation
Details
02-17-2019
16.00
Front storage locker
Details
07-29-2018
0.00
More baggage light pictures
Details
07-29-2018
3.00
Completed baggage light
Details
07-15-2018
4.00
Heater cable bracket
Details
03-04-2018
3.00
Installed fuse block for heated seat and fuel pump
Details
03-03-2018
5.00
Installed pilot heated seat wiring
Details
02-24-2018
3.00
Fabricated hole saw
Details
01-17-2018
7.00
Installed Pilot stick grip
Details
01-16-2018
8.00
Installing the Infinity grips
Details
01-13-2018
8.00
Trimming down the baffles
Details
07-07-2017
0.00
More pictures of glareshield trim
07-07-2017
0.50
Installed top skin in preparation for cowl work
Details
06-18-2017
3.00
Rudder pedals
Details
06-11-2017
3.00
Reinstalled rudder pedals
Details
06-11-2017
0.00
More pictures of the air vent installation
Details
06-11-2017
3.00
Installed air ducts
Details
06-10-2017
4.00
Installed brake and heater cables
Details
06-10-2017
2.00
Fabricated brackets for side air vents
Details
05-11-2017
2.00
Painting the side rails
Details
05-11-2017
2.00
Almost 14 mod installation
Details
05-10-2017
3.00
Installing Almost 14 mod
Details
04-04-2017
5.00
Fuel vent lines installed
Details
04-01-2017
12.00
Installed brake lines
Details
04-01-2017
12.00
Installed brake lines
Details
03-26-2017
4.00
Glareshield trim
Details
03-04-2017
7.00
Instrument panel
Details
01-25-2017
2.00
Finished parking brake
Details
01-24-2017
4.00
Parking brake fabricated
Details
01-21-2017
2.00
Installed heater valve
Details
01-15-2017
3.00
Fuel tubing completed
Details
01-15-2017
3.00
Fuel lines to right wing
Details
01-09-2017
2.00
Right side fuel line
Details
01-08-2017
6.00
Fabricated fuel return line
Details
01-06-2017
3.00
Installed fuel supply to firewall
Details
01-03-2017
2.00
Installed deadening material below fuel pumps
Details
01-02-2017
6.00
Fuel system penetrations
Details
12-17-2016
4.00
Wired fuel pumps
Details
11-24-2016
3.00
Installed fuel line to prefilter
Details
11-23-2016
1.00
Worked on duplex fuel valve
Details
11-22-2016
3.00
Maintenance brackets for fuel pumps
Details
11-20-2016
4.00
Painted the firewall support angles
Details
11-19-2016
3.00
Modified fuel pump position on center support
Details
11-12-2016
5.00
Changing color of front interior
Details
11-12-2016
0.50
Andair parts
Details
11-06-2016
5.00
Worked on fuel center console
Details
11-06-2016
2.00
Fitting fuel valve
Details
10-30-2016
5.00
Finished tubing between filters and fuel pumps
Details
10-29-2016
4.00
Working of fuel system
Details
07-10-2016
1.50
Painted underside of rear top skin
Details
04-30-2016
1.00
Visitor stopped by
Details
03-26-2016
1.00
Installed Pilot seat
Details
03-26-2016
5.00
Finished the seat belt 5th point hardware
Details
03-25-2016
6.00
Installing 5th point seat belt harness
Details
03-20-2016
1.00
Ready for help with top skin
Details
03-20-2016
2.00
Finished top skin
Details
03-19-2016
3.00
Riveting top skin
Details
03-19-2016
1.00
Rivet training for my wife
Details
03-08-2016
2.00
Preparing to rivet top skin
Details
01-05-2016
2.00
Installed F-6111
Details
01-04-2016
2.00
Installed baggage panels
Details
01-01-2016
2.00
Studying Van's manual
Details
11-25-2015
1.00
Rudder wire routing
Details
10-27-2015
4.00
Wired pitch trim
Details
10-25-2015
4.00
Revised flap position sensor brackets
Details
10-25-2015
2.00
Installed tail position/strobe light
Details
10-09-2015
2.00
Dimpled skin and installed plate nuts
Details
10-04-2015
1.00
Slotted hole in F-604A
Details
10-04-2015
3.00
Reinstalled wooded spars
Details
09-27-2015
5.00
Fixing minor things
Details
09-25-2015
4.00
Lowered the fuselage
Details
05-17-2015
6.00
Installing main gear
Details
03-29-2015
3.00
Installed fuel supply and return fuselage fittings
Details
03-29-2015
1.00
Fabricated fuel vent inlets
Details
03-08-2015
5.00
Installed last two seat ribs
Details
03-07-2015
5.00
Worked on center tunnel
Details
03-06-2015
4.00
Working on center tunnel
Details
01-11-2015
8.00
Replaced connecting rods
Details
01-06-2015
4.00
Installed flap position sensor
Details
12-26-2014
2.00
Flap potentiometer bracket
Details
12-23-2014
3.00
Started installing flap motor
Details
12-13-2014
8.00
Installing Control Column
Details
09-06-2014
5.00
Fuselage in Shop
Details
SITE NAVIGATION
Contact Builder
RV-6A Home
Category
# Logs
# Hours
All
579
2177
Avionics
91
534
Canopy
63
202
Empennage
28
104
Engine
99
363
Fuselage
94
384
Gear
62
174
Miscellaneous
22
40
None
2
Wings
118
376