Date
|
Hours
|
Work Log Summary
|
Details
|
08-30-2012
|
0.00
|
Project Update
|
Details
|
|
|
12-18-2011
|
2.00
|
Completed tailcone stinger fairing
|
Details
|
|
|
12-17-2011
|
3.00
|
Completed carb balance and static RPM check
|
Details
|
|
|
12-10-2011
|
6.00
|
Initial fitting of tailcone stinger
|
Details
|
|
|
12-04-2011
|
5.00
|
More final assembly tasks
|
Details
|
|
|
12-03-2011
|
6.00
|
More final assembly tasks
|
Details
|
|
|
11-27-2011
|
6.00
|
Installed wing root fairings
|
Details
|
|
|
11-26-2011
|
6.00
|
Completed wiring, plumbing + more taxi tests
|
Details
|
|
|
11-25-2011
|
3.00
|
Weighing the Aircraft
|
Details
|
|
|
11-24-2011
|
2.00
|
Scale Calibration 2
|
Details
|
|
|
11-23-2011
|
1.00
|
Scale Calibration 1
|
Details
|
|
|
11-20-2011
|
4.00
|
Aileron rigging
|
Details
|
|
|
11-12-2011
|
4.00
|
First engine start and initial taxi tests
|
Details
|
|
|
11-11-2011
|
4.00
|
Set propeller pitch and tracking
|
Details
|
|
|
11-11-2011
|
4.00
|
Serviced Rotax oil and coolant systems
|
Details
|
|
|
11-10-2011
|
4.00
|
Flap rigging
|
Details
|
|
|
11-10-2011
|
4.00
|
Final fuel system integraton and testing 2
|
Details
|
|
|
11-09-2011
|
8.00
|
Final fuel system integraton and testing 1
|
Details
|
|
|
11-08-2011
|
8.00
|
Wing-to-fuselage wiring
|
Details
|
|
|
11-07-2011
|
6.00
|
Flap / Aileron Installation 2
|
Details
|
|
|
11-06-2011
|
6.00
|
Flap / Aileron Installation 1
|
Details
|
|
|
11-05-2011
|
4.00
|
Mounted wings to forward carry-through spar
|
Details
|
|
|
10-30-2011
|
12.00
|
Tail Surface Rigging
|
Details
|
|
|
10-16-2011
|
4.00
|
Horizontal Stabilator Installation
|
Details
|
|
|
10-15-2011
|
6.00
|
Vertical Stablizer and Rudder Installation
|
Details
|
|
|
09-26-2011
|
16.00
|
Canopy and WIndshield Installation
|
Details
|
|
|
09-11-2011
|
10.00
|
Windshield & Canopy Continued
|
Details
|
|
|
09-09-2011
|
2.00
|
New canopy attach angles
|
Details
|
|
|
09-04-2011
|
6.00
|
Glareshield covering
|
Details
|
|
|
09-02-2011
|
6.00
|
Initinal windshield fitting
|
Details
|
|
|
09-01-2011
|
2.00
|
Completed cowling installation
|
Details
|
|
|
08-24-2011
|
2.00
|
Installed oil door in top cowling
|
Details
|
|
|
08-21-2011
|
8.00
|
Installed cowling fasteners and assembled spinner
|
Details
|
|
|
08-20-2011
|
6.00
|
Final fitting / trimming of cowling
|
Details
|
|
|
08-14-2011
|
6.00
|
Fitting of top cowl
|
Details
|
|
|
08-13-2011
|
6.00
|
Fitting of bottom cowl
|
Details
|
|
|
08-07-2011
|
6.00
|
Riveted top forward fuselage skin
|
Details
|
|
|
08-06-2011
|
2.00
|
Serviced brake system
|
Details
|
|
|
08-06-2011
|
2.00
|
Performed leak check on fuselage fuel system
|
Details
|
|
|
08-05-2011
|
8.00
|
Completed engine installation
|
Details
|
|
|
07-31-2011
|
2.00
|
Engine tachometer and alternator connections
|
Details
|
|
|
07-31-2011
|
6.00
|
Engine cooling system plumbing
|
Details
|
|
|
07-30-2011
|
5.00
|
Engine duct work
|
Details
|
|
|
07-30-2011
|
3.00
|
Completed exhaust system installation
|
Details
|
|
|
07-29-2011
|
2.00
|
Rotax ignition wiring
|
Details
|
|
|
07-28-2011
|
6.00
|
Seats 2 of 2
|
Details
|
|
|
07-27-2011
|
6.00
|
Seats 1 of 2
|
Details
|
|
|
07-25-2011
|
6.00
|
Wirrig of battery, starter, fuel pump, engine send
|
Details
|
|
|
07-24-2011
|
6.00
|
Installation of senders, fuel pump, exhaust system
|
Details
|
|
|
07-23-2011
|
4.00
|
Connected throttle and choke cables
|
Details
|
|
|
07-22-2011
|
8.00
|
Engine installation 2
|
Details
|
|
|
07-17-2011
|
4.00
|
Exterior brake line installation
|
Details
|
|
|
07-15-2011
|
6.00
|
Engine installation 1
|
Details
|
|
|
07-12-2011
|
3.00
|
Fuselage final assembly - riveted foward side skin
|
Details
|
|
|
07-10-2011
|
3.00
|
Mounted oil tank, oil vent, and fuel drains
|
Details
|
|
|
07-10-2011
|
3.00
|
Fuselage final assembly - cleco'd forward skins
|
Details
|
|
|
07-09-2011
|
6.00
|
Prep & prime forward fuselage parts
|
Details
|
|
|
07-08-2011
|
3.00
|
Replaced brake pressure lines
|
Details
|
|
|
07-08-2011
|
1.00
|
Installed fuselage fuel lines
|
Details
|
|
|
07-08-2011
|
2.00
|
Fitted center tunnel cover
|
Details
|
|
|
07-08-2011
|
2.00
|
Fabricated and installed UAT mounting bracket
|
Details
|
|
|
07-04-2011
|
4.00
|
Fuselage final assembly - center skins & steps
|
Details
|
|
|
07-03-2011
|
6.00
|
Fuselage final assembly - tailcone top skins
|
Details
|
|
|
07-03-2011
|
6.00
|
Fuselage final assembly - nose gear
|
Details
|
|
|
06-27-2011
|
2.00
|
Fitting of closeout bulkhead
|
Details
|
|
|
06-26-2011
|
2.00
|
Performed pitch bungee modification
|
Details
|
|
|
06-26-2011
|
6.00
|
Fuselage wiring 3
|
Details
|
|
|
06-26-2011
|
6.00
|
Fuselage final assembly - seat skins
|
Details
|
|
|
06-26-2011
|
6.00
|
Fuselage final assembly - main landing gear
|
Details
|
|
|
06-19-2011
|
3.00
|
Fuselage wiring 2
|
Details
|
|
|
06-19-2011
|
4.00
|
Fuselage final assembly - joined center fuselage t
|
Details
|
|
|
06-19-2011
|
1.00
|
Fitting of pitch servo
|
Details
|
|
|
06-12-2011
|
3.00
|
Installation of roll servo
|
Details
|
|
|
06-12-2011
|
6.00
|
Fuselage wiring 1
|
Details
|
|
|
06-10-2011
|
4.00
|
Fuselage final assembly - fairleads, fuel selector
|
Details
|
|
|
06-05-2011
|
6.00
|
Fuselage final assembly - rudder cables, sticks, e
|
Details
|
|
|
06-04-2011
|
4.00
|
Fuselage final assembly - forward fuselage belly s
|
Details
|
|
|
05-30-2011
|
3.00
|
Fuselage - prep for final assembly
|
Details
|
|
|
05-29-2011
|
5.00
|
Forward fuselage disassembly
|
Details
|
|
|
05-28-2011
|
5.00
|
Installed static system and wiring in tailcone
|
Details
|
|
|
05-27-2011
|
6.00
|
Fitting tailcone to center fuselage
|
Details
|
|
|
05-22-2011
|
6.00
|
Fitting of flap torque tube mechanism
|
Details
|
|
|
05-22-2011
|
1.00
|
Antenna relocation
|
Details
|
|
|
05-21-2011
|
6.00
|
Fitting of seat and baggage skins
|
Details
|
|
|
05-07-2011
|
2.00
|
Fuselage fuel system completed
|
Details
|
|
|
05-01-2011
|
6.00
|
Misc. fuselage tasks 2
|
Details
|
|
|
04-30-2011
|
8.00
|
Misc. fuselage tasks 1
|
Details
|
|
|
04-29-2011
|
6.00
|
Drillig forward fuselage
|
Details
|
|
|
04-17-2011
|
8.00
|
Joining Forward & Center Fuselage 2
|
Details
|
|
|
04-16-2011
|
6.00
|
Joining Forward & Center Fuselage 1
|
Details
|
|
|
04-11-2011
|
1.00
|
Engine Delivery and Visual Inspection
|
Details
|
|
|
04-08-2011
|
3.00
|
Center fuselage assembly - side skins
|
Details
|
|
|
04-03-2011
|
8.00
|
Center fuselage assembly - belly skin
|
Details
|
|
|
03-27-2011
|
10.00
|
Tailcone side and aft bulkhead assembly (2 of 2)
|
Details
|
|
|
03-20-2011
|
6.00
|
Tailcone side and aft bulkhead assembly (1 of 2)
|
Details
|
|
|
03-19-2011
|
10.00
|
Prep and prime taillcone side skin parts
|
Details
|
|
|
03-18-2011
|
4.00
|
Doubler for LH side skin corner stiffener
|
Details
|
|
|
03-13-2011
|
8.00
|
Fitted LH tailcone side skin and closeout skin
|
Details
|
|
|
03-06-2011
|
1.00
|
Fitted RH tailcone side skin to belly skin
|
Details
|
|
|
03-06-2011
|
1.50
|
Continued work on LH tailcone side skin
|
Details
|
|
|
03-05-2011
|
2.00
|
Fitted parts to LH tailcone side skin
|
Details
|
|
|
03-05-2011
|
3.00
|
Continued work on RH tailcone side skin
|
Details
|
|
|
03-04-2011
|
6.00
|
Fitted parts to RH tailcone side skin
|
Details
|
|
|
02-27-2011
|
5.00
|
Bending the tailcone side skins
|
Details
|
|
|
02-13-2011
|
5.00
|
Riveting parts to belly skin
|
Details
|
|
|
02-12-2011
|
2.00
|
Fitting of tailcone belly skin parts
|
Details
|
|
|
02-06-2011
|
2.00
|
Fitting of comm antennas on belly skin
|
Details
|
|
|
02-03-2011
|
1.50
|
Transponder antenna installation
|
Details
|
|
|
02-03-2011
|
1.50
|
Drilling of center fuselage skins
|
Details
|
|
|
02-02-2011
|
2.00
|
Fitting of stabilator trim servo
|
Details
|
|
|
01-30-2011
|
3.00
|
Tailcone bulkhead
|
Details
|
|
|
01-30-2011
|
2.00
|
Control sticks
|
Details
|
|
|
01-23-2011
|
8.00
|
Forward fuselage wiring 3
|
Details
|
|
|
01-13-2011
|
8.00
|
Forward fuselage wiring 2
|
Details
|
|
|
01-08-2011
|
6.00
|
Forward fuselage wiring 1
|
Details
|
|
|
01-07-2011
|
4.00
|
Fuselage plumbing
|
Details
|
|
|
01-02-2011
|
6.00
|
Fitting of rudder pedals
|
Details
|
|
|
01-01-2011
|
4.00
|
Forward fuselage floorboard assembly
|
Details
|
|
|
12-27-2010
|
2.00
|
Drilling gear attach blocks
|
Details
|
|
|
12-26-2010
|
4.00
|
Drilling of Forward Longerons
|
Details
|
|
|
12-19-2010
|
2.00
|
Bending of Forward Longerons
|
Details
|
|
|
12-10-2010
|
5.00
|
More firewall work
|
Details
|
|
|
12-01-2010
|
12.00
|
Forward Fuselage / Firewall Assembly
|
Details
|
|
|
11-25-2010
|
2.00
|
ELT Mounting
|
Details
|
|
|
11-20-2010
|
6.00
|
Fuselage Center Section Assembly
|
Details
|
|
|
11-14-2010
|
2.00
|
Center section frame parts prep & prime #1
|
Details
|
|
|
11-13-2010
|
3.00
|
Cabin sidewall rib modification
|
Details
|
|
|
11-11-2010
|
3.00
|
Wiring of control sticks
|
Details
|
|
|
11-11-2010
|
3.00
|
Test fit of side skins
|
Details
|
|
|
11-07-2010
|
20.00
|
Switch / circuit breaker sub-panel
|
Details
|
|
|
11-01-2010
|
2.50
|
Fuselage center section - baggage rib assembly
|
Details
|
|
|
10-24-2010
|
3.00
|
Fuselage center section - seat rib assembly
|
Details
|
|
|
10-20-2010
|
1.50
|
RH wing moved to storage
|
Details
|
|
|
10-11-2010
|
6.00
|
RH wing - wing tip assembly
|
Details
|
|
|
10-11-2010
|
2.50
|
RH flap - final assembly
|
Details
|
|
|
10-10-2010
|
2.00
|
RH flap - initial skin fitting 2
|
Details
|
|
|
10-09-2010
|
8.00
|
RH wing - final assembly 3
|
Details
|
|
|
10-03-2010
|
6.00
|
RH wing - final assembly 2
|
Details
|
|
|
10-02-2010
|
6.00
|
RH wing - final assembly 1
|
Details
|
|
|
10-01-2010
|
2.50
|
RH wing - frame prep for final assembly
|
Details
|
|
|
10-01-2010
|
1.50
|
RH flap - initial fitting of skin 1
|
Details
|
|
|
09-26-2010
|
2.50
|
RH wing - fitting of pitot / AOA probe
|
Details
|
|
|
09-25-2010
|
3.00
|
RH wing - fitting of torque angle & landing light
|
Details
|
|
|
09-22-2010
|
6.00
|
RH wing - fitting of leading edge skin (2 of 2)
|
Details
|
|
|
09-19-2010
|
3.00
|
RH wing - fitting of leading edge skin (1 of 2)
|
Details
|
|
|
09-12-2010
|
5.00
|
RH wing - fitting of upper aft skin
|
Details
|
|
|
09-10-2010
|
4.00
|
RH wing - fitting of lower aft skin
|
Details
|
|
|
09-09-2010
|
4.00
|
RH wing rear spar and frame assembly
|
Details
|
|
|
09-08-2010
|
8.00
|
RH wing - ribs assembled to main spar
|
Details
|
|
|
09-03-2010
|
3.00
|
Completion of LH flap
|
Details
|
|
|
08-28-2010
|
2.50
|
LH wing final assembly - wing tip (2 of 2)
|
Details
|
|
|
08-25-2010
|
3.00
|
LH wing final assembly - wing tip (1 of 2)
|
Details
|
|
|
08-22-2010
|
3.00
|
LH wing final assembly - top skin riveting
|
Details
|
|
|
08-22-2010
|
3.00
|
LH wing final assembly - bottom skin riveting
|
Details
|
|
|
08-20-2010
|
5.00
|
LH wing final assembly - leading edge
|
Details
|
|
|
08-15-2010
|
8.00
|
LH wing final assembly - upper aft skin
|
Details
|
|
|
08-13-2010
|
2.00
|
Plumbing and pressure test of LH fuel tank
|
Details
|
|
|
08-01-2010
|
8.00
|
LH wing final assembly - lower aft skin
|
Details
|
|
|
07-25-2010
|
5.00
|
LH wing frame prep
|
Details
|
|
|
07-23-2010
|
3.00
|
LH wing wiring
|
Details
|
|
|
07-19-2010
|
2.00
|
LH wing - fuel filler and sender holes
|
Details
|
|
|
07-17-2010
|
1.00
|
LH landing light lens
|
Details
|
|
|
07-17-2010
|
6.00
|
Fitting of LH landing light
|
Details
|
|
|
07-11-2010
|
2.00
|
LH wing - completed drilling of skins
|
Details
|
|
|
07-05-2010
|
1.50
|
LH wing - fuel tank bay torque angle
|
Details
|
|
|
07-05-2010
|
3.00
|
LH wing - fitting of wing tip skins
|
Details
|
|
|
07-05-2010
|
3.00
|
LH wing - completed fitting of leading edge
|
Details
|
|
|
07-04-2010
|
3.00
|
LH wing - continued fitting of leading edge
|
Details
|
|
|
07-03-2010
|
12.00
|
LH Wing Construction Resumes
|
Details
|
|
|
06-27-2010
|
1.50
|
Fitting of LH flap skin (2)
|
Details
|
|
|
06-27-2010
|
1.50
|
Final assembly of RH flap frame
|
Details
|
|
|
06-26-2010
|
4.00
|
Fitting of LH flap skin (1)
|
Details
|
|
|
06-25-2010
|
3.00
|
Final assembly of LH flap frame
|
Details
|
|
|
06-25-2010
|
2.50
|
Completed initial assembly of RH flap frame
|
Details
|
|
|
06-20-2010
|
5.00
|
RH aileron final assembly
|
Details
|
|
|
06-19-2010
|
6.00
|
RH aileron frame assembly & skin fitting
|
Details
|
|
|
06-18-2010
|
1.50
|
Completed drilling of RH aileron frame
|
Details
|
|
|
06-13-2010
|
3.50
|
LH Aileron Completed
|
Details
|
|
|
06-12-2010
|
6.00
|
LH Aileron Frame Assembly & Skin Fitting
|
Details
|
|
|
06-11-2010
|
5.00
|
More Aileron and Flap Work
|
Details
|
|
|
06-05-2010
|
5.00
|
Initial Assembly of LH Aileron Frame
|
Details
|
|
|
05-01-2010
|
2.50
|
Inventory of Remaining Airframe Parts
|
Details
|
|
|
04-04-2010
|
3.00
|
LH wing - leading edge
|
Details
|
|
|
04-04-2010
|
2.50
|
LH wing - fitting of upper aft skin complete
|
Details
|
|
|
04-03-2010
|
5.00
|
LH wing - fitting of top aft skin
|
Details
|
|
|
04-02-2010
|
5.00
|
LH wing - lower aft skin fitting completed
|
Details
|
|
|
01-16-2009
|
1.50
|
Setting angle of Rib #7
|
Details
|
|
|
01-15-2009
|
0.25
|
Vertical Stabilizer Hinge Bushing
|
Details
|
|
|
01-15-2009
|
1.00
|
Vertical Stabilizer Front Spar
|
Details
|
|
|
01-15-2009
|
3.00
|
The crate arrives!!
|
Details
|
|
|
01-14-2009
|
0.00
|
|
Details
|
|