Work Logs Found: 116
Category Work Time: 255 Hours
 Date
Hours
Work Log Summary

Details

 11-27-2011
1.50
Center Section odds and ends before mating to tail
Details
       

 11-26-2011
1.50
Manual Aileron Trim Assembly
Details
       

 11-23-2011
1.00
Manual Aileron Trim bracket installation
Details
       

 11-23-2011
0.75
Manual Aileron Trim bracket installation
Details
       

 11-23-2011
0.50
Manual Aileron Trim bracket Installation
Details
       

 11-23-2011
0.25
Manual Aileron Trim bracket Installation
Details
     

 11-19-2011
1.50
Crotch Strap bracket installation
Details
       

 11-19-2011
3.00
Center Section - Drilling Plate Nut Holes #2
Details
     

 11-19-2011
3.00
Center Section - Drilling Plate Nut Holes #1
Details
       

 11-15-2011
1.50
Center Section - Back Drilling F-715 Rib
Details
     

 11-13-2011
1.00
Center Section - Fitting F-715 Ribs
Details
       

 10-30-2011
2.00
Center Section Assembly
Details

 10-29-2011
1.50
Primed the center section ribs and bottom skin
Details

 10-28-2011
1.00
Debur center section parts
Details

 04-06-2010
1.50
Wing Skin Preparation and Assembly
Details

 02-21-2010
6.00
Left Aileron Deburring, Scuffing, Dimpling and Cou
       

 11-05-2009
0.00
3x Rivet Gun Settings
Details

 04-26-2009
5.00

Details

 04-24-2009
2.00

Details

 04-23-2009
1.50

Details

 04-22-2009
1.20
Fitted Fuel Cap Flange
Details

 04-19-2009
4.00
More fabricating
Details

 04-09-2009
0.00
Deciding on which fuel sending unit and flop-tube
Details

 04-08-2009
2.00
Finished up drilling an start T-405 fabrication
Details

 04-07-2009
1.50
Countersinking Tank skin to baffle
Details

 04-05-2009
1.50
Final sized drilling of Tank skin and ribs
Details

 04-04-2009
3.00
Drilling tank attach points to wing spar
Details

 03-31-2009
0.50
Don't worry about the Tank/LE gap
Details

 03-30-2009
2.00
Fuel Tank to Leading Edge gap
Details

 03-29-2009
6.00
Fitting the Fuel Tank Skins
Details
       

 03-23-2009
1.50
Tank Attach Brackets
Details
       

 03-02-2009
1.50
Primer delivered and wing stand work
Details

 02-24-2009
0.00
Ordered primer today
Details

 02-23-2009
1.50
Construct Fuel Tank/Leading Edge jig
Details

 02-09-2009
1.00
Start prepping ribs for primer
Details

 02-08-2009
2.00
Straightened up the shop
Details

 02-07-2009
3.50
More deburring - will it ever end
Details

 02-06-2009
2.50
Finished drilling and deburring wing ribs
Details

 02-02-2009
2.00
Wing Conduit hole
Details
       

 02-02-2009
2.00
Re-countersinked the tank mounting points
Details

 02-02-2009
1.50
Drilled conduit holes in ribs
Details

 02-01-2009
1.00
Finished up drilling ribs to spars
Details

 01-25-2009
2.50
Clecoed ribs to wing spars...signs of progress
Details

 01-24-2009
4.00
Finished straightening and fluting ribs
Details

 01-11-2009
4.00
Debur wing ribs and started straightening and flut
Details
       

 01-05-2009
4.00
Update the construction log
Details

 01-04-2009
1.00
Wing rib preparation
Details

 01-04-2009
2.00
Finished up the rear spar assembly
Details
       

 01-03-2009
2.00
Trimming Rear Spar Reinforcement/Doubler plates
Details
       

 01-02-2009
3.50
Finished up the rear spar assemblies
Details
       

 01-01-2009
3.00
Continued Rear Spar Assembly work
Details

 12-31-2008
5.00
Rear spar assembly
Details
       

 12-30-2008
5.00
Rivet tie down assembly and attach bell crank asse
Details
       

 12-29-2008
1.50
Riveted platenuts to left spar and installed the t
Details

 12-28-2008
2.00
Access plate preparation
Details
     

 12-27-2008
5.00
Right Wing Spar preparation
Details
       

 12-27-2008
2.00
Rearrange shop to accommodate wing build
Details

 12-26-2008
5.00
Counted bags of parts and fasteners and drilled 1s
Details
       

 12-24-2008
3.00
Open and inventory crate 2
Details
       

 12-23-2008
4.00
Finished up inventoring crate 1
Details
       

 12-22-2008
0.50
Santa's Sleigh (aka ABF) arrives bearing packages!
Details
       

 12-22-2008
3.00
Opening and inventory of kit
Details
       

 12-22-2008
0.00
Just a few more pics unloading the sleigh
Details
       

 11-30-2008
4.00
Drilled bolt holes in garage floor for wing stands
Details

 11-28-2008
2.00
Wing stand building material
Details

 11-25-2008
0.75
Rudder Rod-End Bearing Adjustment
Details

 11-23-2008
1.00
Elevator control horn alignment
Details

 11-22-2008
3.00
Finished leading edges and test fit to HS
Details

 11-18-2008
1.50
Elevator leading edge rolling part deaux
Details

 11-17-2008
2.00
Right Elevator edge rolling and hardware installat
Details

 11-15-2008
2.00
Rolled left elevator edges and attached hardware
Details

 11-15-2008
2.00
Helped fellow RV builder hang wings on his -7
Details

 11-13-2008
2.50
Trim tab hinge installation
Details
       

 11-12-2008
2.50
Trim Tab installation
Details
     

 11-10-2008
5.00
Closing up the Left Elevator
Details
       

 11-09-2008
1.50
The AN "Replacements"
Details
       

 11-01-2008
1.00
The "Home Depot Aircraft Supply" Solution
Details
       

 10-31-2008
0.00
Email to Van's on elevator rib attachment
Details

 10-30-2008
2.00
Riveted ribs to spar
Details

 10-29-2008
1.00
Primed counterbalance rib and end rib
Details

 10-27-2008
1.50
Fill and Redrill Counterweight
Details

 10-13-2008
0.00
Switched to Standard Build
Details
     

 09-28-2008
2.00
Primed and Riveted Stiffners on left elevator
Details

 09-27-2008
3.00
Right Elevator riveted
Details

 09-27-2008
0.00
Ordered the Quick Build Kit today
Details
     

 09-06-2008
1.00
Review the Empenage work
Details

 08-25-2008
1.00
More Rudder skin riveting
Details
     

 08-24-2008
5.00
Riveting the Rudder Skin to Rudder Skeleton
Details
       

 08-19-2008
1.50
Rudder Skeleton - Priming
Details

 06-29-2008
2.00
Rudder Spar to skin stiffener clearance issue
Details

 06-29-2008
1.50
Rudder Skeleton
Details

 06-23-2008
3.00
Riveted Rudder skins to stiffners
Details
       

 06-18-2008
1.50
Riveted VS Skin to VS skeleton
Details

 06-17-2008
1.50
Prime and riveted VS ribs and spars
Details

 06-16-2008
2.00
Riveted VS rear spar and spar stiffener
Details

 06-15-2008
5.50
Matched drilled and deburred the VS
Details

 06-14-2008
1.50
Started Vertical Stabilizer
Details

 06-14-2008
6.50
Finished the Horizontal Stabilizer
Details

 06-10-2008
2.00
Skin riveting continues...
Details

 06-09-2008
2.50
Began Riveting left HS stab
Details

 06-08-2008
1.50
Confidence building exercise
Details

 06-07-2008
4.00
First rib riveting effort
Details

 06-02-2008
1.50
Dimpling the understructure components
Details
     

 05-25-2008
3.50
Front Spar Assembly
Details

 05-16-2008
3.00
Front Spar Assembly
Details

 05-12-2008
2.50
Front Spar Assembly
Details

 05-10-2008
5.00
Rear Spar Assembly
Details
     

 05-02-2008
0.00
Tools arrived today
Details

 04-29-2008
0.00
Ordered Tools today...finally!
Details

 04-04-2008
12.00
Built shop tables
Details

 03-27-2008
0.90
Finished up the inventory today
Details

 03-26-2008
1.80
Inventory Continues!
Details
     

 03-25-2008
1.00
So many parts for tail feathers
Details
     

 03-25-2008
0.00
Houston, We have an Airplane...sort of!
Details
       

 03-21-2008
0.00
Received shipment notification via email
Details

 03-19-2008
0.00
Faxed Empenage order to Vans
Details