Date
|
Hours
|
Work Log Summary
|
Details
|
11-25-2022
|
25.00
|
Winterization Kit
|
Details
|
|
|
07-10-2010
|
0.00
|
First flight of C-FZUM
|
Details
|
|
|
07-06-2010
|
0.00
|
Special Certificate of Airworthiness received
|
Details
|
|
|
07-05-2010
|
2.50
|
Final inspection snag rectification
|
Details
|
|
|
07-03-2010
|
4.00
|
Final inspection
|
Details
|
|
|
06-26-2010
|
2.50
|
Final inspection preparations
|
Details
|
|
|
06-19-2010
|
4.50
|
Ignition wiring securing...
|
Details
|
|
|
06-12-2010
|
6.50
|
Weight and balance
|
Details
|
|
|
06-05-2010
|
5.00
|
Magneto reinstallation...
|
Details
|
|
|
05-28-2010
|
4.00
|
Seat belt installation...
|
Details
|
|
|
05-20-2010
|
3.50
|
Upholestry installation...
|
Details
|
|
|
05-18-2010
|
0.00
|
Ignition system news
|
Details
|
|
|
05-11-2010
|
0.00
|
RV Transition Training completed
|
Details
|
|
|
05-07-2010
|
4.00
|
Engine starting troubleshooting continued
|
Details
|
|
|
05-01-2010
|
4.00
|
Engine starting troubleshooting continued
|
Details
|
|
|
04-29-2010
|
4.00
|
Engine starting troubleshooting
|
Details
|
|
|
04-24-2010
|
4.00
|
Engine kick back troubleshooting
|
Details
|
|
|
04-23-2010
|
5.00
|
Oil system plug installation...
|
Details
|
|
|
04-17-2010
|
5.00
|
Engine run preparations...
|
Details
|
|
|
04-13-2010
|
2.00
|
Engine ignition system timing set up
|
Details
|
|
|
04-09-2010
|
6.00
|
Placard installation...
|
Details
|
|
|
04-07-2010
|
4.00
|
First aid kit retainer bracket riveting...
|
Details
|
|
|
04-06-2010
|
3.00
|
First aid kit mounting
|
Details
|
|
|
04-05-2010
|
5.00
|
Right tank reinstallation
|
Details
|
|
|
03-31-2010
|
1.00
|
Right fuel tank resealing
|
Details
|
|
|
03-27-2010
|
4.50
|
Baggage comparment tie down installation...
|
Details
|
|
|
03-26-2010
|
4.00
|
Cabin floor installation...
|
Details
|
|
|
03-24-2010
|
0.50
|
Right fuel tank leak check
|
Details
|
|
|
03-23-2010
|
1.00
|
New BNC connector installed in right fuel tank
|
Details
|
|
|
03-17-2010
|
2.00
|
Fairing installation
|
Details
|
|
|
03-11-2010
|
1.00
|
Right fuel tank defective BNC connector removal
|
Details
|
|
|
03-10-2010
|
1.00
|
Right fuel tank opening
|
Details
|
|
|
03-09-2010
|
4.00
|
Autopilot controller connector jumper installed...
|
Details
|
|
|
03-06-2010
|
4.50
|
Display Software update...
|
Details
|
|
|
03-01-2010
|
0.00
|
Final inspection request filed
|
Details
|
|
|
02-26-2010
|
4.50
|
Display System Instrument Calibration inputed...
|
Details
|
|
|
02-19-2010
|
5.50
|
Fuel quantity indicating system calibration
|
Details
|
|
|
02-12-2010
|
8.00
|
Rudder fairing installation...
|
Details
|
|
|
02-05-2010
|
8.00
|
Lighting, flap, aileron, AOA and brake system work
|
Details
|
|
|
02-02-2010
|
7.75
|
Autopilot, display and lighting connected
|
Details
|
|
|
01-28-2010
|
8.50
|
Wing and empenage attachment completed...
|
Details
|
|
|
01-23-2010
|
5.25
|
Moving fuselage to the airport
|
Details
|
|
|
01-20-2010
|
5.00
|
Taking parts to the airport
|
Details
|
|
|
01-19-2010
|
3.00
|
Component packing for moving
|
Details
|
|
|
01-11-2010
|
3.25
|
Canopy finishing...
|
Details
|
|
|
01-10-2010
|
7.50
|
Fire extinguisher installation...
|
Details
|
|
|
01-04-2010
|
3.00
|
Cowling iterations carried out
|
Details
|
|
|
01-03-2010
|
9.50
|
Propeller installation...
|
Details
|
|
|
01-02-2010
|
2.75
|
XM antenna installation...
|
Details
|
|
|
01-01-2010
|
10.00
|
Finishing odds and ends
|
Details
|
|
|
12-12-2009
|
1.00
|
Engine cooling air intake rings painting
|
Details
|
|
|
12-11-2009
|
9.00
|
Multiple firewall forward items secured...
|
Details
|
|
|
12-10-2009
|
8.00
|
Engine cowling and fairings paint touch up...
|
Details
|
|
|
12-09-2009
|
2.25
|
Cowling accent color painting
|
Details
|
|
|
12-08-2009
|
5.00
|
Engine cowling painting continued
|
Details
|
|
|
12-07-2009
|
2.00
|
Upper engine colwing painting...
|
Details
|
|
|
12-06-2009
|
1.50
|
Upper engine cowling UV blocker application...
|
Details
|
|
|
12-05-2009
|
2.25
|
Upper engine cowling priming...
|
Details
|
|
|
12-03-2009
|
7.00
|
Lower engine cowling painting...
|
Details
|
|
|
12-02-2009
|
8.75
|
Sanding lower engine cowling...
|
Details
|
|
|
12-01-2009
|
4.00
|
Lower engine cowling sanding
|
Details
|
|
|
11-30-2009
|
4.50
|
Engine cowling outer face sanding...
|
Details
|
|
|
11-29-2009
|
2.00
|
Upper cowling sanding
|
Details
|
|
|
11-28-2009
|
1.25
|
Engine cowl micro application and sanding
|
Details
|
|
|
11-27-2009
|
1.00
|
Wing to body fairing painting...
|
Details
|
|
|
11-26-2009
|
2.00
|
Wing to body fairings primed...
|
Details
|
|
|
11-25-2009
|
5.50
|
Wing to body fairing cleaning, etching....
|
Details
|
|
|
11-24-2009
|
5.50
|
Gear leg fairing repaint
|
Details
|
|
|
11-23-2009
|
3.50
|
Landing and taxi light connectors added
|
Details
|
|
|
11-22-2009
|
6.75
|
Flap & elavator tab safetying....
|
Details
|
|
|
11-21-2009
|
2.00
|
Fairing painting
|
Details
|
|
|
11-20-2009
|
1.00
|
Gear leg & intersection fairing UV blocker
|
Details
|
|
|
11-19-2009
|
2.50
|
Gear leg & intersection fairing sanding/ priming
|
Details
|
|
|
11-18-2009
|
2.75
|
Wheel fairing painting
|
Details
|
|
|
11-17-2009
|
2.75
|
Fairing paint preparations continued...
|
Details
|
|
|
11-16-2009
|
3.00
|
Fairing and cowling paint preparation
|
Details
|
|
|
11-15-2009
|
4.00
|
Nose wheel fairing preparation...
|
Details
|
|
|
11-14-2009
|
6.00
|
Engine induction filter assembly installation
|
Details
|
|
|
11-13-2009
|
2.00
|
Main wheel fairing painting
|
Details
|
|
|
11-11-2009
|
1.25
|
Main wheel fairing UV blocker applied
|
Details
|
|
|
11-10-2009
|
2.75
|
Main wheel fairing sanding and priming
|
Details
|
|
|
11-08-2009
|
4.50
|
Wheel fairing preparation continued
|
Details
|
|
|
11-06-2009
|
3.00
|
Wheel fairing sanding and priming
|
Details
|
|
|
10-31-2009
|
4.50
|
Gear leg upper intersection fairing preparations
|
Details
|
|
|
10-30-2009
|
1.00
|
Wheel fairing epoxy coating applied
|
Details
|
|
|
10-29-2009
|
3.00
|
Wheel fairing paint preparation
|
Details
|
|
|
10-21-2009
|
1.75
|
Wing tip fairings painted
|
Details
|
|
|
10-20-2009
|
3.00
|
Wing tip fairing primer and UV blocker applied
|
Details
|
|
|
10-19-2009
|
2.00
|
Primed wing tip fairings
|
Details
|
|
|
10-18-2009
|
1.50
|
Wing fairing paint preparation
|
Details
|
|
|
10-16-2009
|
5.25
|
Elevator painting & gear fairing preparation
|
Details
|
|
|
10-15-2009
|
6.00
|
Elevator priming & gear leg intersection fairings
|
Details
|
|
|
10-14-2009
|
1.75
|
Elevator paint preparations continued
|
Details
|
|
|
10-13-2009
|
3.00
|
Elevator painting preparations
|
Details
|
|
|
10-12-2009
|
1.75
|
Horizontal stabilizer painting
|
Details
|
|
|
10-11-2009
|
2.00
|
Horizontal stabilizer priming...
|
Details
|
|
|
10-10-2009
|
9.25
|
Tying up firewall forward loose ends
|
Details
|
|
|
10-09-2009
|
2.75
|
Rudder and vertical stabilizer continued...
|
Details
|
|
|
10-08-2009
|
4.00
|
Rudder and vertical stabilizer priming...
|
Details
|
|
|
10-07-2009
|
2.50
|
Rudder & vertical stabilizer cleaning, etching...
|
Details
|
|
|
10-05-2009
|
3.00
|
Ailerons and flaps painted
|
Details
|
|
|
10-04-2009
|
3.25
|
Flap and aileron priming...
|
Details
|
|
|
10-03-2009
|
9.25
|
Post paint engine reinstallation
|
Details
|
|
|
10-02-2009
|
9.45
|
Fuselage accent stripe and registration painting
|
Details
|
|
|
10-01-2009
|
8.75
|
Fuselage painting...
|
Details
|
|
|
09-30-2009
|
7.50
|
Fuselage priming...
|
Details
|
|
|
09-29-2009
|
8.00
|
Fuselage preparation for painting
|
Details
|
|
|
09-28-2009
|
7.25
|
Forward cabin covers, canopy, paint planning
|
Details
|
|
|
09-27-2009
|
10.00
|
Firewall preparation prior to painting...
|
Details
|
|
|
09-26-2009
|
5.00
|
Firewall sealant application
|
Details
|
|
|
09-25-2009
|
5.50
|
Engine removal prior to painting fuselage
|
Details
|
|
|
09-24-2009
|
5.50
|
Right wing painting, engine alternate air intake
|
Details
|
|
|
09-23-2009
|
8.75
|
Engine intake alternate air selector valve prep...
|
Details
|
|
|
09-22-2009
|
6.50
|
Wing repainting & engine air filter preparation
|
Details
|
|
|
09-21-2009
|
6.50
|
Wing painting & engine air intake work
|
Details
|
|
|
09-20-2009
|
7.75
|
Cabin heat muff installation...
|
Details
|
|
|
09-19-2009
|
10.00
|
Engine exhaust and ignition lead securing...
|
Details
|
|
|
09-18-2009
|
4.00
|
Cowling engine cooling intake ring sanding...
|
Details
|
|
|
09-17-2009
|
2.00
|
Riveted cowling forward flange nut plates...
|
Details
|
|
|
09-16-2009
|
7.50
|
Engine baffle and pleunum installation...
|
Details
|
|
|
09-15-2009
|
8.25
|
Lower cowling air exit attach bracket
|
Details
|
|
|
09-14-2009
|
2.25
|
Cowling oil filler door completed...
|
Details
|
|
|
09-13-2009
|
3.00
|
Upper cowling oil filler door installation
|
Details
|
|
|
09-12-2009
|
3.00
|
Upper cowling oil filler door fabrication
|
Details
|
|
|
09-11-2009
|
1.50
|
Cowling engine combustion air inlet bonded...
|
Details
|
|
|
09-10-2009
|
5.00
|
Engine baffle trimming...
|
Details
|
|
|
09-09-2009
|
7.00
|
Cowling fastener retainer strip riveting...
|
Details
|
|
|
09-08-2009
|
20.00
|
Cowling installation
|
Details
|
|
|
09-02-2009
|
7.00
|
Lower cowling fitting
|
Details
|
|
|
09-01-2009
|
7.50
|
Prop installation and upper cowling fitting
|
Details
|
|
|
08-30-2009
|
5.75
|
Wiring securing and protecting...
|
Details
|
|
|
08-28-2009
|
2.25
|
Component aluminium protective vinyl removal
|
Details
|
|
|
08-27-2009
|
0.50
|
Forward upper fuselage access panel gasket trim
|
Details
|
|
|
08-26-2009
|
1.50
|
Left and right navigation light installation
|
Details
|
|
|
08-25-2009
|
8.50
|
Tail fairing retaining screw anchor nuts...
|
Details
|
|
|
08-24-2009
|
4.75
|
Aft nav and strobe light wiring continued...
|
Details
|
|
|
08-23-2009
|
3.50
|
Fuel tank vent line reinstallation...
|
Details
|
|
|
08-22-2009
|
5.75
|
Fuselage upper forward skin riveting...
|
Details
|
|
|
08-18-2009
|
3.25
|
Horizontal to vertical stab fairing iterations
|
Details
|
|
|
08-17-2009
|
5.25
|
Stabilzer fairing fitting
|
Details
|
|
|
08-16-2009
|
3.50
|
Elevator trim wiring & stab fairing installation
|
Details
|
|
|
08-15-2009
|
5.50
|
ELT antenna installation...
|
Details
|
|
|
08-14-2009
|
6.00
|
ELT remote control panel wiring
|
Details
|
|
|
08-11-2009
|
1.00
|
Post paint instrument panel repopulation
|
Details
|
|
|
08-10-2009
|
1.50
|
Post paint instrument panel repopulation
|
Details
|
|
|
08-09-2009
|
8.00
|
Instrument panel removal and painting...
|
Details
|
|
|
08-08-2009
|
4.75
|
ELT installation...
|
Details
|
|
|
08-07-2009
|
4.00
|
Aft Nav light and ELT installation
|
Details
|
|
|
08-05-2009
|
1.50
|
EFIS harness installation completed
|
Details
|
|
|
08-04-2009
|
1.50
|
Left EFIS wiring harness installation continued
|
Details
|
|
|
08-03-2009
|
2.50
|
EFIS harness installation...
|
Details
|
|
|
07-15-2009
|
5.75
|
AOA system tubing installation...
|
Details
|
|
|
07-14-2009
|
2.75
|
Forward upper deck access panel installation
|
Details
|
|
|
07-07-2009
|
10.25
|
AOA flap switch wiring...
|
Details
|
|
|
07-06-2009
|
3.50
|
Elevator trim wiring installation...
|
Details
|
|
|
07-05-2009
|
9.00
|
Control stick to systems interface wiring
|
Details
|
|
|
07-03-2009
|
1.25
|
Autopilot installation continued
|
Details
|
|
|
07-02-2009
|
2.75
|
Autopilot installation continued
|
Details
|
|
|
07-01-2009
|
2.50
|
Autopilot installation continued
|
Details
|
|
|
06-30-2009
|
6.50
|
Autopilot installation
|
Details
|
|
|
06-28-2009
|
7.00
|
Pitot plumbing installation
|
Details
|
|
|
06-27-2009
|
2.00
|
Transponder antenna coaxial cable fabrication...
|
Details
|
|
|
06-21-2009
|
5.00
|
Pitot/Static manifold installation...
|
Details
|
|
|
06-14-2009
|
8.25
|
Transponder antenna installation
|
Details
|
|
|
06-11-2009
|
3.00
|
Strobe light circuit wiring
|
Details
|
|
|
06-10-2009
|
8.75
|
Canopy wiring disconnect installed...
|
Details
|
|
|
06-08-2009
|
1.75
|
Ray Allen trim servo wiring connector
|
Details
|
|
|
06-07-2009
|
6.00
|
Flap position switch installation...
|
Details
|
|
|
06-05-2009
|
3.50
|
Flap position switch installation
|
Details
|
|
|
05-29-2009
|
6.00
|
Stick grip wiring and installation
|
Details
|
|
|
05-21-2009
|
5.25
|
Wiring continued...
|
Details
|
|
|
05-20-2009
|
7.25
|
Glareshield lighting wiring continued...
|
Details
|
|
|
05-19-2009
|
4.00
|
Magnetometer installation...
|
Details
|
|
|
05-18-2009
|
4.00
|
Transponder back shell installation...
|
Details
|
|
|
05-17-2009
|
1.00
|
Landing and taxi light wiring continued
|
Details
|
|
|
05-16-2009
|
1.50
|
Landing light and taxi light circuit wiring
|
Details
|
|
|
05-15-2009
|
1.50
|
Buss switch reorientation
|
Details
|
|
|
05-13-2009
|
6.50
|
GPS and Transponder installation
|
Details
|
|
|
05-12-2009
|
10.75
|
Communications radio installation
|
Details
|
|
|
05-10-2009
|
3.25
|
Audio panel mount fabrication
|
Details
|
|
|
05-08-2009
|
1.25
|
Fuel pump electrical circuit wired
|
Details
|
|
|
05-07-2009
|
1.25
|
Starter solenoid ground circuit rewiring
|
Details
|
|
|
05-06-2009
|
3.50
|
Flap circuit wiring...
|
Details
|
|
|
05-05-2009
|
6.75
|
Magnetometer installation...
|
Details
|
|
|
05-03-2009
|
9.00
|
Magnetometer installation...
|
Details
|
|
|
04-27-2009
|
4.00
|
Primer, starter...wiring
|
Details
|
|
|
04-26-2009
|
1.00
|
Master and starter solenoid diodes installed
|
Details
|
|
|
04-26-2009
|
6.50
|
Electrical system control and indication wiring
|
Details
|
|
|
04-19-2009
|
4.75
|
Magnetometer installation
|
Details
|
|
|
04-19-2009
|
4.00
|
Comm radio antenna installation
|
Details
|
|
|
04-18-2009
|
3.75
|
Wiring continued...
|
Details
|
|
|
04-17-2009
|
5.50
|
Engine wiring continued
|
Details
|
|
|
04-16-2009
|
5.00
|
Wiring continued...
|
Details
|
|
|
04-12-2009
|
1.50
|
Prop control cable firewall shield installed...
|
Details
|
|
|
04-10-2009
|
3.75
|
Wiring continued...
|
Details
|
|
|
04-08-2009
|
8.25
|
Engine harness preparation
|
Details
|
|
|
04-07-2009
|
5.25
|
Wiring preparations
|
Details
|
|
|
04-06-2009
|
7.50
|
Engine primer installation
|
Details
|
|
|
04-04-2009
|
5.75
|
Electrical and fuel system fitting
|
Details
|
|
|
04-03-2009
|
2.75
|
Wiring installation
|
Details
|
|
|
04-02-2009
|
4.75
|
Engine control cable installation...
|
Details
|
|
|
04-02-2009
|
2.00
|
Engine control cable installation
|
Details
|
|
|
04-01-2009
|
6.00
|
Map box, park brake cable and heater control cable
|
Details
|
|
|
03-31-2009
|
6.75
|
Panel switch installation...
|
Details
|
|
|
03-29-2009
|
1.00
|
Panel switch hole drilling
|
Details
|
|
|
03-28-2009
|
2.50
|
Panel switch and indicator light holes drilled
|
Details
|
|
|
03-27-2009
|
1.00
|
Mounted lights dimmer...
|
Details
|
|
|
03-26-2009
|
6.50
|
Engine manifold pressure transducer installation..
|
Details
|
|
|
03-25-2009
|
8.00
|
Fuel and electrical system component installation
|
Details
|
|
|
03-24-2009
|
4.75
|
Engine fuel flow transducer mounting
|
Details
|
|
|
03-23-2009
|
2.50
|
Engine manifold pressure manifold completed
|
Details
|
|
|
03-19-2009
|
2.50
|
Electrical components installation...
|
Details
|
|
|
03-18-2009
|
7.50
|
Electrical component mount assembly continued
|
Details
|
|
|
03-17-2009
|
5.00
|
Electrical system component mount fabricated
|
Details
|
|
|
03-11-2009
|
2.50
|
Electrical harness snap bushings installed
|
Details
|
|
|
03-07-2009
|
3.00
|
Rudder lower fairing installation
|
Details
|
|
|
03-02-2009
|
2.00
|
Fuel flow transducer mount fabricated
|
Details
|
|
|
03-01-2009
|
6.75
|
Main alternator installation...
|
Details
|
|
|
02-27-2009
|
2.00
|
Back up alternator installation...
|
Details
|
|
|
02-25-2009
|
0.00
|
Electrical system order arrives
|
Details
|
|
|
02-21-2009
|
3.00
|
Engine to firewall ground cable installation...
|
Details
|
|
|
02-20-2009
|
1.75
|
Fuel pump overflow line installed...
|
Details
|
|
|
02-19-2009
|
3.25
|
Fabricated panel extension
|
Details
|
|
|
02-06-2009
|
6.50
|
Wing tip fairing completion
|
Details
|
|
|
02-05-2009
|
2.50
|
Oil pressure restrictor fitting installation...
|
Details
|
|
|
02-05-2009
|
1.75
|
Fuel line installation...
|
Details
|
|
|
01-20-2009
|
3.00
|
Oil and fuel pressure transducer installation...
|
Details
|
|
|
01-20-2009
|
1.50
|
EGT and CHT probe installation
|
Details
|
|
|
01-19-2009
|
2.00
|
Engine exhaust system fitting
|
Details
|
|
|
01-12-2009
|
3.00
|
Radio stack support installation
|
Details
|
|
|
12-20-2008
|
6.00
|
Fuel line and electrical cable installation
|
Details
|
|
|
12-13-2008
|
10.00
|
Main wheel fairing preparation
|
Details
|
|
|
12-06-2008
|
2.50
|
Engine mounting
|
Details
|
|
|
12-04-2008
|
1.50
|
Instrument panel second display hole cut
|
Details
|
|
|
12-03-2008
|
4.00
|
Nose wheel fairing iterations
|
Details
|
|
|
11-28-2008
|
5.75
|
Instrument panel support rib and display install
|
Details
|
|
|
11-23-2008
|
1.50
|
Landing gear fairing support bracket installation
|
Details
|
|
|
11-22-2008
|
5.00
|
Propeller governor installation...
|
Details
|
|
|
11-16-2008
|
1.00
|
Carburetor installation
|
Details
|
|
|
11-15-2008
|
5.75
|
Wheel fairing bracket alodining and priming...
|
Details
|
|
|
11-07-2008
|
5.00
|
Engine baffle preparation
|
Details
|
|
|
11-05-2008
|
1.50
|
Engine baffle preparation
|
Details
|
|
|
11-02-2008
|
4.00
|
Engine baffle preparation
|
Details
|
|
|
10-20-2008
|
0.00
|
Aero Sport Power engine arrives
|
Details
|
|
|
10-19-2008
|
1.75
|
Cowling mounting flange preparation continued
|
Details
|
|
|
10-18-2008
|
4.75
|
Cowling mounting flange preparation
|
Details
|
|
|
10-10-2008
|
0.00
|
The propeller arrives
|
Details
|
|
|
10-03-2008
|
3.50
|
Instrument panel preparation
|
Details
|
|
|
10-02-2008
|
4.00
|
Radio stack installation preparations
|
Details
|
|
|
09-27-2008
|
6.25
|
Landing gear fairing preparation
|
Details
|
|
|
08-31-2008
|
2.25
|
Landing gear fairing preparation
|
Details
|
|
|
08-30-2008
|
4.00
|
Main wheel fairing preparation
|
Details
|
|
|
08-16-2008
|
3.50
|
Main wheel fairing opening trimming
|
Details
|
|
|
08-15-2008
|
4.75
|
Nose gear fairing installation
|
Details
|
|
|
07-28-2008
|
0.00
|
Oshkosh 2008
|
Details
|
|
|
07-28-2008
|
0.00
|
Oshkosh 2008
|
Details
|
|
|
06-26-2008
|
8.00
|
Right wheel, leg and intersection fairing ...
|
Details
|
|
|
06-25-2008
|
6.00
|
Main wheel fairing installation
|
Details
|
|
|
06-20-2008
|
3.00
|
Main wheel fairing installation preparation
|
Details
|
|
|
06-19-2008
|
2.75
|
Gear leg fairing hinge installation
|
Details
|
|
|
06-18-2008
|
5.25
|
Brake line and gear leg fairing installation
|
Details
|
|
|
06-17-2008
|
4.25
|
Main and nose gear installation
|
Details
|
|
|
06-16-2008
|
1.50
|
Nose gear preparations
|
Details
|
|
|
06-15-2008
|
2.00
|
Right wheel and brake assembly mounting
|
Details
|
|
|
06-14-2008
|
3.75
|
Left wheel and brake assembly mounting
|
Details
|
|
|
06-12-2008
|
2.25
|
Canopy latch handle knob installation...
|
Details
|
|
|
06-11-2008
|
0.75
|
Flap fitting rivet replacing
|
Details
|
|
|
06-10-2008
|
5.00
|
Aileron trim installation completed
|
Details
|
|
|
06-09-2008
|
6.00
|
Rear window and aileron trim installation
|
Details
|
|
|
06-08-2008
|
6.00
|
Wing root fairing anchor nut installation
|
Details
|
|
|
06-07-2008
|
8.50
|
Floor, baggage bulkhead and seat back installation
|
Details
|
|
|
06-02-2008
|
8.00
|
F-774 upper skin and rollover bar installation
|
Details
|
|
|
06-01-2008
|
6.25
|
Wing to fuselage fairing and flap installation
|
Details
|
|
|
05-31-2008
|
8.00
|
Wing to fuselage mating
|
Details
|
|
|
05-26-2008
|
3.75
|
Fuselage support saw horse fabrication...
|
Details
|
|
|
05-25-2008
|
6.50
|
Canopy lift strut and control stick installation
|
Details
|
|
|
05-18-2008
|
7.50
|
Canopy latch installation continued
|
Details
|
|
|
04-27-2008
|
7.50
|
Canopy to forward skin fiberglassing
|
Details
|
|
|
04-23-2008
|
1.50
|
Riveted aileron up stops
|
Details
|
|
|
04-23-2008
|
4.00
|
Canopy to forward skin fiberglassing
|
Details
|
|
|
04-20-2008
|
2.00
|
Canopy side skirt riveting...
|
Details
|
|
|
04-17-2008
|
1.00
|
Canopy forward skin painting...
|
Details
|
|
|
04-16-2008
|
3.50
|
Wing tip fairing, canopy and wing to body fairing
|
Details
|
|
|
04-15-2008
|
4.00
|
Wing to body fairing...
|
Details
|
|
|
04-14-2008
|
6.75
|
Wing tip fairing fitting
|
Details
|
|
|
04-12-2008
|
0.75
|
Wing tip fairing fitting
|
Details
|
|
|
04-11-2008
|
2.25
|
Wing tip fairing fitting
|
Details
|
|
|
04-10-2008
|
1.75
|
Left wing tip fairing fitting
|
Details
|
|
|
04-08-2008
|
4.25
|
Right flap installation
|
Details
|
|
|
04-07-2008
|
5.00
|
Aileron and flap installation
|
Details
|
|
|
04-06-2008
|
7.00
|
Aileron installation and rigging
|
Details
|
|
|
04-02-2008
|
3.25
|
Static line and baggage area covers installation
|
Details
|
|
|
03-31-2008
|
2.25
|
Fabricated the elevator push tube tunnel cover
|
Details
|
|
|
03-29-2008
|
8.25
|
Canopy skin installation...
|
Details
|
|
|
03-28-2008
|
5.00
|
Canopy side skirt installation
|
Details
|
|
|
03-27-2008
|
7.25
|
Canopy preparations
|
Details
|
|
|
03-26-2008
|
4.00
|
Canopy preparations
|
Details
|
|
|
03-25-2008
|
5.75
|
Canopy preparations
|
Details
|
|
|
03-24-2008
|
3.25
|
Canopy preparations
|
Details
|
|
|
03-17-2008
|
1.75
|
Panel mounted map box installation
|
Details
|
|
|
03-16-2008
|
2.25
|
Canopy fitting and trimming
|
Details
|
|
|
03-15-2008
|
7.25
|
Fitting the plexiglass canopy
|
Details
|
|
|
03-14-2008
|
3.75
|
Canopy component cleaning, abrading...
|
Details
|
|
|
03-13-2008
|
6.50
|
Canopy reinforcement brace
|
Details
|
|
|
03-06-2008
|
7.50
|
Canopy frame preparations
|
Details
|
|
|
03-05-2008
|
4.25
|
Canopy frame finishing
|
Details
|
|
|
03-04-2008
|
5.00
|
Forward canopy frame fitting
|
Details
|
|
|
03-04-2008
|
3.25
|
Aft canopy frame preparations
|
Details
|
|
|
03-02-2008
|
1.75
|
Forward canopy fitting
|
Details
|
|
|
03-01-2008
|
1.50
|
Canopy forward frame and skin preparation
|
Details
|
|
|
02-28-2008
|
6.00
|
Canopy release mechanism
|
Details
|
|
|
02-26-2008
|
11.75
|
Canopy latch and static system installation
|
Details
|
|
|
02-24-2008
|
2.00
|
Canopy latch side handle installation
|
Details
|
|
|
02-20-2008
|
6.25
|
Forward upper fueslage riveting, canopy latch...
|
Details
|
|
|
02-19-2008
|
4.75
|
Forward upper fuselage structure riveting
|
Details
|
|
|
02-18-2008
|
2.50
|
Fresh air vent NACA scoop installation
|
Details
|
|
|
02-17-2008
|
9.25
|
Park brake valve and brake line installation
|
Details
|
|
|
02-09-2008
|
5.75
|
Firewall preparation
|
Details
|
|
|
02-08-2008
|
3.75
|
Map box installation
|
Details
|
|
|
02-06-2008
|
3.00
|
Map box preparation
|
Details
|
|
|
02-04-2008
|
2.50
|
Heat valve, pressure transducer manifold install
|
Details
|
|
|
02-03-2008
|
1.50
|
Gascolator installation
|
Details
|
|
|
02-02-2008
|
7.25
|
Battery box, contactors and breather tube clamp
|
Details
|
|
|
02-01-2008
|
3.75
|
Forward upper fuselage component priming...
|
Details
|
|
|
01-31-2008
|
9.00
|
Forward upper fuselage preparation
|
Details
|
|
|
01-29-2008
|
1.75
|
Dismantle forward deck components
|
Details
|
|
|
01-28-2008
|
1.50
|
Dimpling forward upper skin
|
Details
|
|
|
01-26-2008
|
5.25
|
Forward deck installation
|
Details
|
|
|
01-19-2008
|
2.25
|
Sub panel work continued
|
Details
|
|
|
01-19-2008
|
2.00
|
Finishing kit inventory
|
Details
|
|
|
01-12-2008
|
5.25
|
Rollover bar, flap channel and instrument panel wo
|
Details
|
|
|
01-11-2008
|
3.00
|
Rollover bar riveting
|
Details
|
|
|
01-10-2008
|
1.25
|
Rollover bar component priming
|
Details
|
|
|
01-09-2008
|
5.50
|
Rollover Bar Component Cleaning, Abrading and alod
|
Details
|
|
|
01-03-2008
|
2.75
|
More fuel lines and brake line installation
|
Details
|
|
|
01-02-2008
|
2.50
|
Fuel line installation
|
Details
|
|
|
01-02-2008
|
1.75
|
Firewall forward kit inventory
|
Details
|
|
|
12-19-2007
|
3.75
|
Instrument panel considerations
|
Details
|
|
|
12-15-2007
|
3.00
|
Fuel vent line installation
|
Details
|
|
|
12-14-2007
|
3.00
|
Cabin and baggage are floor and side panel instal
|
Details
|
|
|
12-13-2007
|
5.50
|
Empennage fairing installation
|
Details
|
|
|
12-12-2007
|
2.25
|
Systems installation
|
Details
|
|
|
12-11-2007
|
3.00
|
Empenage component mounting
|
Details
|
|
|
12-04-2007
|
4.50
|
Vertical stabilizer mounting
|
Details
|
|
|
12-02-2007
|
1.00
|
Vertical stabalizer mounting preparations
|
Details
|
|
|
12-01-2007
|
7.75
|
Elevator and horizontal stabilizer installation
|
Details
|
|
|
11-30-2007
|
9.50
|
Cabin and baggage floor rib anchor nut installatio
|
Details
|
|
|
11-24-2007
|
8.25
|
Wing lower skin riveting
|
Details
|
|
|
11-20-2007
|
2.00
|
Elevator control rod installation
|
Details
|
|
|
11-19-2007
|
2.25
|
Left elevator closure
|
Details
|
|
|
11-18-2007
|
2.25
|
Right elevator closure
|
Details
|
|
|
11-17-2007
|
5.25
|
Right wing lower skin riveting
|
Details
|
|
|
11-16-2007
|
5.50
|
MD-RA precover inspection and empennage closing
|
Details
|
|
|
11-10-2007
|
5.50
|
Roll over bar installation and aft fuselage riveti
|
Details
|
|
|
11-10-2007
|
3.00
|
Forward deck preperation
|
Details
|
|
|
11-08-2007
|
4.00
|
Roll over bar installation
|
Details
|
|
|
11-06-2007
|
3.00
|
Roll over bar mount angle drilling
|
Details
|
|
|
11-01-2007
|
8.75
|
Fuselage roll over bar fabrication
|
Details
|
|
|
10-30-2007
|
1.75
|
Shoulder harness wear block installation
|
Details
|
|
|
10-28-2007
|
4.25
|
Landing gear mount installation
|
Details
|
|
|
10-26-2007
|
5.00
|
Flap drives system and landing gear mount prepara
|
Details
|
|
|
10-25-2007
|
4.00
|
Seat assembly and forward cabin cover riveting
|
Details
|
|
|
10-24-2007
|
7.75
|
Priming seat components, forward cabin covers...
|
Details
|
|
|
10-23-2007
|
5.75
|
Seat component deburring, edge finishing...
|
Details
|
|
|
10-19-2007
|
2.50
|
Forward cabin cover fitting
|
Details
|
|
|
10-13-2007
|
8.00
|
Seat bottom panel hinge drilling and seat back pre
|
Details
|
|
|
10-12-2007
|
2.25
|
F-757T plate riveting and seat bottom preparation
|
Details
|
|
|
10-11-2007
|
3.00
|
Riveting upper aft fuselage parts
|
Details
|
|
|
10-10-2007
|
2.25
|
Priming upper aft fuselage skins, etc...
|
Details
|
|
|
10-09-2007
|
2.50
|
Cleaning, abrading and aloding aft fuselage parts
|
Details
|
|
|
10-08-2007
|
4.25
|
Aft fuselage upper skin edge finishing, deburring.
|
Details
|
|
|
10-07-2007
|
3.25
|
F-706 bulkhead anchor nut installation
|
Details
|
|
|
10-06-2007
|
9.75
|
Aft fuselage upper skin installation
|
Details
|
|
|
10-05-2007
|
4.00
|
Stub spar and leg installation
|
Details
|
|
|
10-05-2007
|
4.25
|
Priming cabin and baggage area parts...
|
Details
|
|
|
10-04-2007
|
2.25
|
Cleaning, abrading and aloding fuselage parts
|
Details
|
|
|
10-03-2007
|
2.50
|
Edge finishing, riveting and F-695 gusset installa
|
Details
|
|
|
10-02-2007
|
3.00
|
Edge finishing floor panels
|
Details
|
|
|
10-01-2007
|
2.25
|
Riveting aft canopy deck area
|
Details
|
|
|
09-29-2007
|
8.25
|
Fuselage riveting
|
Details
|
|
|
09-28-2007
|
1.00
|
Gear leg to gear mount match drilling
|
Details
|
|
|
09-26-2007
|
1.50
|
Step installation preparation
|
Details
|
|
|
09-22-2007
|
5.00
|
Forward fuselage riveting
|
Details
|
|
|
09-21-2007
|
7.50
|
Forward fuselage re-assembly
|
Details
|
|
|
09-20-2007
|
2.50
|
Riveting various forward fuselage parts
|
Details
|
|
|
09-19-2007
|
1.25
|
Attached anchor nuts to fuselage ribs...
|
Details
|
|
|
09-18-2007
|
2.00
|
Priming F-770, F-772 fuselage skins
|
Details
|
|
|
09-15-2007
|
6.25
|
Forward fuselage pre-riveting preparations
|
Details
|
|
|
09-14-2007
|
8.25
|
Forward fuselage component preparations
|
Details
|
|
|
09-12-2007
|
3.00
|
Edge finishing and dimpling ribs...
|
Details
|
|
|
09-11-2007
|
1.50
|
F-718, F-717 countersinking...
|
Details
|
|
|
09-10-2007
|
2.00
|
Longeron countersinking.
|
Details
|
|
|
09-07-2007
|
5.75
|
Gear leg mount installation
|
Details
|
|
|
09-06-2007
|
2.50
|
Deburring and edge finishing of the F-772 forward
|
Details
|
|
|
09-05-2007
|
1.50
|
Deburring and edge finishing of the left F-770
|
Details
|
|
|
09-04-2007
|
1.50
|
F-770 forward side skin deburring and edge finishi
|
Details
|
|
|
09-01-2007
|
7.75
|
Baggage area framing, step tube mount drilling...
|
Details
|
|
|
08-31-2007
|
5.00
|
Auxiliary fuel pump doubler and floor stiffener in
|
Details
|
|
|
08-25-2007
|
7.00
|
Fuselage forward bulkhead installation
|
Details
|
|
|
08-24-2007
|
4.50
|
F-717 longeron completed and match drilled
|
Details
|
|
|
08-23-2007
|
2.75
|
F-719B angle clip completion, F719 installation...
|
Details
|
|
|
08-22-2007
|
2.25
|
Auxilary longeron installation
|
Details
|
|
|
08-21-2007
|
1.50
|
F-704-L attach strap fabrication
|
Details
|
|
|
08-20-2007
|
2.50
|
Firewall installation
|
Details
|
|
|
08-11-2007
|
8.50
|
F-770 forward side skin bending
|
Details
|
|
|
08-08-2007
|
2.50
|
Match drilling F-770 forward side skins
|
Details
|
|
|
08-07-2007
|
3.50
|
F-718 longeron and F-770 side skin installation
|
Details
|
|
|
08-04-2007
|
3.50
|
Aft fuselage assembly riveting...
|
Details
|
|
|
08-03-2007
|
2.00
|
Notching F-718 longeron and trim conopy decks
|
Details
|
|
|
08-02-2007
|
10.00
|
Fuselage center section outer rib fitting
|
Details
|
|
|
07-19-2007
|
8.00
|
Cleaning, abrading, alodining, priming and rivetin
|
Details
|
|
|
07-18-2007
|
3.25
|
Fribracated various fuselage compontents
|
Details
|
|
|
07-17-2007
|
7.75
|
Aft fuselage assembly riveting
|
Details
|
|
|
07-16-2007
|
3.00
|
Fuselage center section riveting
|
Details
|
|
|
07-15-2007
|
2.00
|
Center section bagage rib riveting.
|
Details
|
|
|
07-14-2007
|
1.25
|
Center section seat rib riveting
|
Details
|
|
|
07-11-2007
|
8.75
|
Rudder/brake pedal installation
|
Details
|
|
|
07-10-2007
|
6.25
|
Fabricated rudder stops and riveted bulkheads...
|
Details
|
|
|
07-09-2007
|
2.25
|
Fuselage center section parts priming
|
Details
|
|
|
07-08-2007
|
6.75
|
Cleaning and alodining fuselage center section par
|
Details
|
|
|
07-06-2007
|
2.75
|
Fuselage center section dimpling and deburring
|
Details
|
|
|
07-05-2007
|
2.00
|
Center section rib edge finishing and deburring
|
Details
|
|
|
07-04-2007
|
2.00
|
Center fuselage preparation
|
Details
|
|
|
07-02-2007
|
6.00
|
Match drilling, deburring,edge finishing and dimpl
|
Details
|
|
|
06-30-2007
|
9.25
|
Alodining and priming and center fuselage prep
|
Details
|
|
|
06-29-2007
|
1.50
|
Cleaning and abrading aft fuselage parts
|
Details
|
|
|
06-28-2007
|
3.00
|
Firewall riveting
|
Details
|
|
|
06-27-2007
|
1.25
|
Riveting the F-705 bulkhead
|
Details
|
|
|
06-26-2007
|
1.00
|
F-705 bulkhead assembling
|
Details
|
|
|
06-25-2007
|
3.00
|
Alodining and priming
|
Details
|
|
|
06-24-2007
|
3.75
|
Cleaning and abrading of aft fuselage parts
|
Details
|
|
|
06-22-2007
|
3.00
|
Aft fuselage assembly deburring and dimpling
|
Details
|
|
|
06-21-2007
|
1.50
|
Aft fuselage assembly deburring and edge finishing
|
Details
|
|
|
06-20-2007
|
1.50
|
Aft fuselage assembly deburring and edge finishing
|
Details
|
|
|
06-16-2007
|
6.00
|
Aft fuselage assembly match drilling
|
Details
|
|
|
06-12-2007
|
1.50
|
Match drill J-channel to aft fuselage assembly
|
Details
|
|
|
06-08-2007
|
2.00
|
Assembling aft fuselage assembly
|
Details
|
|
|
06-07-2007
|
4.75
|
F-718 Longeron Bending, J channel trimming
|
Details
|
|
|
06-06-2007
|
8.25
|
F-707 to F-12 bulkhead preparation
|
Details
|
|
|
06-05-2007
|
4.50
|
F-705 and F-706 bulkhead preparation
|
Details
|
|
|
06-04-2007
|
5.00
|
F-705 Bulkhead preparation
|
Details
|
|
|
06-03-2007
|
7.50
|
F-705 and F-705 bulkhead preparation
|
Details
|
|
|
06-02-2007
|
8.25
|
F-704 Center Section Bulkhead Preparation
|
Details
|
|
|
06-01-2007
|
7.50
|
Firewall preparation
|
Details
|
|
|
05-31-2007
|
2.50
|
Firewall component assembling.
|
Details
|
|
|
05-30-2007
|
5.00
|
Fuselage kit unpacking and inventory
|
Details
|
|
|
03-11-2007
|
1.00
|
Riveted on flap braces
|
Details
|
|
|
03-05-2007
|
2.00
|
Aileron rigging
|
Details
|
|
|
03-03-2007
|
10.50
|
Control tubes, left wing skin and aileron riveting
|
Details
|
|
|
03-02-2007
|
4.00
|
Aileron push tube construction
|
Details
|
|
|
02-28-2007
|
1.75
|
Cut and drilled aileron control rods
|
Details
|
|
|
02-27-2007
|
1.25
|
Right aileron hinge bracket and gap fairing riveti
|
Details
|
|
|
02-26-2007
|
1.50
|
Clecoe on left wing upper skins
|
Details
|
|
|
02-25-2007
|
1.50
|
Riveted the left wing leading edge to the spar
|
Details
|
|
|
02-25-2007
|
3.00
|
Left and right aileron assembling
|
Details
|
|
|
02-24-2007
|
4.00
|
Left wing leading edge riveting
|
Details
|
|
|
02-23-2007
|
7.00
|
Left wing skin preparation
|
Details
|
|
|
02-22-2007
|
5.75
|
Flap brace and aileron fairing preparation
|
Details
|
|
|
02-22-2007
|
3.50
|
Cleaning, abrading and alodining
|
Details
|
|
|
02-17-2007
|
3.00
|
Closing the left wing tank
|
Details
|
|
|
02-16-2007
|
3.50
|
Left wing leading edge deburring
|
Details
|
|
|
02-15-2007
|
6.50
|
Left wing leading end finishing
|
Details
|
|
|
02-14-2007
|
6.25
|
Left wing skin debur, edge finish and dimple
|
Details
|
|
|
02-09-2007
|
5.75
|
Installed right fuel tank, removed left wing skins
|
Details
|
|
|
02-08-2007
|
4.00
|
Right wing tank sealing and left lower skin
|
Details
|
|
|
02-07-2007
|
1.75
|
Left wing tank sealing
|
Details
|
|
|
02-07-2007
|
2.00
|
Left wing tank fuel quantity indication installati
|
Details
|
|
|
02-06-2007
|
1.50
|
Left wing tank sealing
|
Details
|
|
|
02-03-2007
|
5.25
|
Left wing tank sealing and riveting
|
Details
|
|
|
01-27-2007
|
4.25
|
Left wing tank preparation
|
Details
|
|
|
01-26-2007
|
4.50
|
Left wing tank preparation
|
Details
|
|
|
01-25-2007
|
6.25
|
Left wing tank preparation
|
Details
|
|
|
01-06-2007
|
5.75
|
Left wing tank match drilling and deburring
|
Details
|
|
|
01-05-2007
|
4.00
|
Left wing tank Z bracket preparation
|
Details
|
|
|
01-04-2007
|
2.00
|
Left wing leading edge to fuel tank joint plate
|
Details
|
|
|
01-03-2007
|
2.00
|
Match drilled left wing leading edge
|
Details
|
|
|
01-02-2007
|
1.00
|
Clecoed left leading edge and left top skin
|
Details
|
|
|
01-01-2007
|
1.75
|
Rivet left wing rear spar
|
Details
|
|
|
12-31-2006
|
5.25
|
Right wing upper skin riveting
|
Details
|
|
|
12-30-2006
|
4.50
|
Finished sealing of right wing tank
|
Details
|
|
|
12-29-2006
|
2.00
|
Aileron component dimpling
|
Details
|
|
|
12-28-2006
|
1.75
|
Aileron component deburring and edge finishing
|
Details
|
|
|
12-27-2006
|
2.00
|
Aileron skin match drilling
|
Details
|
|
|
12-26-2006
|
2.25
|
Aileron assembly
|
Details
|
|
|
12-25-2006
|
2.00
|
Aileron Spar preparation
|
Details
|
|
|
12-21-2006
|
5.75
|
Started on the ailerons
|
Details
|
|
|
12-20-2006
|
2.50
|
Reriveted leading edge rib flanges
|
Details
|
|
|
12-19-2006
|
1.50
|
Right wing tank sealing
|
Details
|
|
|
12-15-2006
|
2.75
|
Right wing tank sealing
|
Details
|
|
|
12-14-2006
|
2.50
|
Right tank sealing
|
Details
|
|
|
12-11-2006
|
1.25
|
Cleco cleaning and fuel access panel drilling
|
Details
|
|
|
12-09-2006
|
5.00
|
Right wing fuel tank work
|
Details
|
|
|
12-08-2006
|
2.50
|
Right wing tank preparations
|
Details
|
|
|
12-07-2006
|
2.00
|
Landing light installation
|
Details
|
|
|
12-06-2006
|
2.00
|
Right wing landing light
|
Details
|
|
|
12-05-2006
|
2.00
|
Landing light installation
|
Details
|
|
|
12-03-2006
|
2.00
|
Making a manometer
|
Details
|
|
|
12-02-2006
|
8.00
|
Right wing tank sealing
|
Details
|
|
|
12-01-2006
|
3.50
|
Riveting
|
Details
|
|
|
11-30-2006
|
1.25
|
Riveting
|
Details
|
|
|
11-29-2006
|
1.75
|
Riveting
|
Details
|
|
|
11-28-2006
|
1.75
|
Flap assembling and riveting
|
Details
|
|
|
11-27-2006
|
2.50
|
Priming flap compontents, flap assembly fixture
|
Details
|
|
|
11-26-2006
|
4.00
|
Cleaning, abrading and alodining
|
Details
|
|
|
11-23-2006
|
1.75
|
Countersinking and dimpling
|
Details
|
|
|
11-22-2006
|
1.75
|
Deburring and edge finishing
|
Details
|
|
|
11-21-2006
|
1.00
|
Deburring left flap components
|
Details
|
|
|
11-20-2006
|
1.25
|
Flap actuation input rod attach plate and angle
|
Details
|
|
|
11-18-2006
|
9.50
|
Rivet leading edge, build flaps
|
Details
|
|
|
11-17-2006
|
3.50
|
Dimpling of right aft spar, nut plates and rivetin
|
Details
|
|
|
11-16-2006
|
2.25
|
Priming right wing parts
|
Details
|
|
|
11-15-2006
|
3.00
|
Cleaning, abrading and alodining.
|
Details
|
|
|
11-14-2006
|
1.50
|
Deburring and countersinking
|
Details
|
|
|
11-13-2006
|
1.00
|
Edge finishing and dimpling
|
Details
|
|
|
11-12-2006
|
1.25
|
Deburring
|
Details
|
|
|
11-11-2006
|
2.50
|
Deburring, edge finishing and dimpling
|
Details
|
|
|
11-10-2006
|
2.00
|
Deburring, edge finishing and dimpling
|
Details
|
|
|
11-09-2006
|
2.25
|
Deburring, dimpling and edge finishing
|
Details
|
|
|
11-08-2006
|
1.50
|
Dimpling right wing tank skin and skin stiffeners
|
Details
|
|
|
11-07-2006
|
2.00
|
Right tank deburring edge finishing
|
Details
|
|
|
11-06-2006
|
1.00
|
Tank drain, pitot tube opening and rib engraving
|
Details
|
|
|
11-05-2006
|
2.25
|
Right fuel tank access and filler neck
|
Details
|
|
|
11-04-2006
|
2.50
|
Tank inboard rib bracket and fuel quantity capacit
|
Details
|
|
|
11-04-2006
|
2.50
|
Right wing tank installation
|
Details
|
|
|
11-03-2006
|
1.00
|
Right tank inboard forward attach bracket
|
Details
|
|
|
10-28-2006
|
3.25
|
Right wing tank preperations
|
Details
|
|
|
10-27-2006
|
2.00
|
Z bracket edge finishing and tank skin stiffeners
|
Details
|
|
|
10-26-2006
|
1.75
|
Right fuel tank attachments
|
Details
|
|
|
10-25-2006
|
5.00
|
Match drilling right leading and fuel tank
|
Details
|
|
|
10-24-2006
|
6.00
|
Right wing skin match drilling
|
Details
|
|
|
10-18-2006
|
2.50
|
Right wing upper skin installation
|
Details
|
|
|
10-17-2006
|
0.75
|
Right wing spar sag removal
|
Details
|
|
|
10-16-2006
|
1.00
|
Replaced bad rivet on aft spar
|
Details
|
|
|
10-14-2006
|
8.00
|
Right wing main rib riveting
|
Details
|
|
|
10-13-2006
|
2.25
|
Wing assembly fixture work
|
Details
|
|
|
10-13-2006
|
1.00
|
Left wing aft spar doubler riveting
|
Details
|
|
|
10-12-2006
|
4.00
|
Left wing rib, aft spar priming, plus...
|
Details
|
|
|
10-11-2006
|
3.50
|
Left wing rib and aft spar cleaning, abrading and
|
Details
|
|
|
10-10-2006
|
1.50
|
Aft spar doubler riveting
|
Details
|
|
|
10-09-2006
|
2.00
|
Right wing rib and spar priming
|
Details
|
|
|
10-08-2006
|
3.50
|
Right wing rib anti-corrosion treatment
|
Details
|
|
|
10-07-2006
|
4.25
|
Deburring wing rib flange holes
|
Details
|
|
|
10-07-2006
|
2.50
|
Deburring right wing rib to spar attaching holes
|
Details
|
|
|
10-06-2006
|
5.50
|
Wing rib flange fluting and straightening
|
Details
|
|
|
09-29-2006
|
3.50
|
Wing rib flange edge finishing
|
Details
|
|
|
09-25-2006
|
1.00
|
Wing rib relief notch edge finishing
|
Details
|
|
|
09-24-2006
|
2.00
|
Wing rib edge finishing
|
Details
|
|
|
09-22-2006
|
3.00
|
Wing rib lightening hole and flange edge finishing
|
Details
|
|
|
09-21-2006
|
1.00
|
Wing rib edge finishing
|
Details
|
|
|
09-20-2006
|
1.00
|
Edge finishing of wing ribs and aileron hinge brac
|
Details
|
|
|
09-16-2006
|
2.25
|
Wing Tie Down and Elevator Bellcrank Installation
|
Details
|
|
|
09-16-2006
|
1.00
|
Flap Brace Preparation
|
Details
|
|
|
09-16-2006
|
6.25
|
Aft Spar Preparation
|
Details
|
|
|
09-15-2006
|
7.50
|
Main Spar Preparation
|
Details
|
|
|
09-14-2006
|
5.00
|
Wing Spar Flange Anchor Nut Installation
|
Details
|
|
|
09-13-2006
|
3.25
|
Main Spar Flange Anchor Nut installation
|
Details
|
|
|
09-12-2006
|
2.00
|
Wing Main Spar Flange preparation
|
Details
|
|
|
09-07-2006
|
0.50
|
Completing wing kit inventory
|
Details
|
|
|
09-06-2006
|
1.50
|
Carry out inventory
|
Details
|
|
|
09-05-2006
|
3.00
|
Wing kit arrives
|
Details
|
|
|
09-01-2006
|
0.00
|
ABF Freight Sytems and CCRA visit
|
Details
|
|
|
08-31-2006
|
0.00
|
ABF Freight Systems called
|
Details
|
|
|
08-29-2006
|
0.00
|
Letter from Van's
|
Details
|
|
|
08-07-2006
|
0.00
|
Letter from Van's
|
Details
|
|
|
07-10-2006
|
0.00
|
Wing Kit order faxed to Vans
|
Details
|
|
|
03-26-2006
|
6.00
|
Left elevator and tab riveting
|
Details
|
|
|
03-25-2006
|
6.00
|
Right HS skin riveting and rudder trailing edge ri
|
Details
|
|
|
03-23-2006
|
9.00
|
Rudder trailing edge
|
Details
|
|
|
03-22-2006
|
2.75
|
Rudder assembly
|
Details
|
|
|
03-21-2006
|
1.50
|
Rudder spar doubler plate installation
|
Details
|
|
|
03-18-2006
|
11.00
|
HS and VS assembly
|
Details
|
|
|
03-17-2006
|
3.25
|
Finish riveting elevator skin stiffeners
|
Details
|
|
|
03-16-2006
|
3.50
|
Finish priming parts, start riveting skin stiffene
|
Details
|
|
|
03-15-2006
|
5.00
|
Priming parts
|
Details
|
|
|
03-01-2006
|
5.00
|
Clean, abrade and alodine elevator & rudder frames
|
Details
|
|
|
02-28-2006
|
5.00
|
Clean, abrade and alodine Rudder skins
|
Details
|
|
|
02-27-2006
|
5.00
|
Clean, abrade and alodine HS and VS skins
|
Details
|
|
|
02-22-2006
|
3.50
|
Edge finishing
|
Details
|
|
|
02-21-2006
|
5.50
|
Identification marking
|
Details
|
|
|
02-20-2006
|
5.50
|
Identification mark rudder components...
|
Details
|
|
|
02-06-2006
|
1.75
|
Elevator tab preparation
|
Details
|
|
|
02-06-2006
|
5.00
|
Build elevator trim tab
|
Details
|
|
|
02-05-2006
|
7.00
|
Left elevator frame and horn preperation.
|
Details
|
|
|
02-04-2006
|
7.50
|
Right elevator frame and horn preperation.
|
Details
|
|
|
02-03-2006
|
1.25
|
Debur and dimple Elevator skins and skin stiffener
|
Details
|
|
|
02-02-2006
|
1.75
|
Match drill and debur elevator skin stiffeners
|
Details
|
|
|
02-01-2006
|
1.00
|
Elevator skin stiffener edge finishing
|
Details
|
|
|
01-31-2006
|
1.25
|
Trim and edge finish elevator skin stiffeners
|
Details
|
|
|
01-29-2006
|
5.00
|
Elevator skin stiffeners
|
Details
|
|
|
01-28-2006
|
1.00
|
Rudder trailing edge wedge
|
Details
|
|
|
01-26-2006
|
5.00
|
Rudder preparation
|
Details
|
|
|
01-25-2006
|
2.00
|
Build rudder skeleton
|
Details
|
|
|
01-23-2006
|
1.50
|
Rudder skin stiffeners
|
Details
|
|
|
01-21-2006
|
5.75
|
Rudder skin stiffeners
|
Details
|
|
|
01-20-2006
|
2.25
|
Deburing VS parts
|
Details
|
|
|
01-19-2006
|
2.00
|
Match drill VS spars, ribs and skin
|
Details
|
|
|
01-18-2006
|
1.00
|
VS spar, spar dounbler and rib preparation
|
Details
|
|
|
01-18-2006
|
2.00
|
Dimple left HS frame and skin
|
Details
|
|
|
01-17-2006
|
1.00
|
Dimpled right HS skin
|
Details
|
|
|
01-16-2006
|
1.00
|
Dimpled right HS skin
|
Details
|
|
|
01-13-2006
|
0.75
|
Deburring HS parts
|
Details
|
|
|
01-13-2006
|
1.25
|
Deburring
|
Details
|
|
|
01-12-2006
|
6.00
|
Right HS preparation
|
Details
|
|
|
01-11-2006
|
6.25
|
HS preparation
|
Details
|
|
|
01-05-2006
|
5.00
|
Horizontal Stabilizer Spar assembly
|
Details
|
|
|
01-04-2006
|
1.75
|
Inventory Empennage Kit
|
|
|