Work Logs Found:
89
Category Work Time:
686 Hours
Date
Hours
Work Log Summary
Details
01-01-2016
4.00
Throttle quadrant
Details
12-26-2015
8.00
Adapter
Details
12-19-2015
8.00
Gear doors
Details
12-12-2015
8.00
Spinner
Details
12-05-2015
8.00
Fuel system
Details
11-28-2015
8.00
Baffles
Details
11-21-2015
8.00
Antenna
Details
11-14-2015
8.00
Hoses.
Details
11-07-2015
8.00
Toe brakes.
Details
10-31-2015
8.00
Installed components.
Details
10-24-2015
8.00
Installed components.
Details
10-17-2015
8.00
Sensors
Details
10-10-2015
8.00
Wiring
Details
10-03-2015
8.00
Wiring.
Details
09-26-2015
9.00
Wiring.
Details
09-19-2015
8.00
Wiring
Details
09-12-2015
10.00
Fabricated a battery box from 1/2" faom and West S
09-05-2015
8.00
Fabricated the exhaust pipe for the right side.
Details
08-29-2015
8.00
Fabricated the exhaust pipe for the left side.
08-22-2015
8.00
Installed the hydraulic pump in the rear fuselage.
08-15-2015
8.00
Fabricated the left side dash panel and installed
08-08-2015
8.00
Installed the windshield with structural adhesive
08-01-2015
10.00
Installed the Dynon 100 on the pilot site of the d
07-25-2015
32.00
Intalled the upper wing skins on the outer wing pa
07-18-2015
8.00
Outer wings
Details
07-05-2015
8.00
Inner wing leading edge
Details
07-04-2015
6.00
Closed up the tanks with the top skins
Details
07-03-2015
4.00
Installed fuel senders in outer wing tanks
Details
06-27-2015
10.00
Finished forming the cowling
06-20-2015
8.00
Started work on the engine cowling. Put foam arou
01-09-2015
11.00
Re-built the engine mount
Details
10-24-2014
14.00
Build the wiring panels
Details
10-11-2014
23.00
Constructed the flaps
Details
06-20-2013
6.00
Moved the aircraft to a new hangar I just finshed
05-15-2011
4.00
Began fabricating brackets and misc harware for at
12-23-2010
4.00
Gluing up stringers over the main gear and fabrica
06-28-2010
6.00
Various items on the aircraft (small things). It'
10-02-2009
8.00
Fabricated the aluminum covers for the hinge holes
09-18-2009
4.50
Installed the side fuselage skins permanently. Th
09-04-2009
6.00
Fabricated engine mounts and installed the engine.
08-17-2009
4.00
Worked on engine mount.
08-16-2009
6.00
Worked on engine mount.
07-26-2009
8.00
Manufacturing the engine mount (now that I have th
07-25-2009
6.00
Engine
Details
06-28-2009
10.00
Tidying up little details all over the aircraft.
05-15-2009
8.50
Began fabrication of the engine rubber mounts.
Details
04-16-2009
4.50
Cabin doors
Details
03-26-2009
6.50
Cabin doors
Details
03-25-2009
8.00
Cabin doors.
Details
03-23-2009
6.00
Installed the rear windows.
Details
02-28-2009
4.00
Fabricated and installed the anchor cables.
Details
02-26-2009
8.50
Fabricated the canopy door frames (curved layups).
02-12-2009
3.50
Installed upholstery in the baggage compartment.
02-11-2009
8.00
Fitted rear windows in the fuselage.
Details
11-05-2008
4.00
Fabricated the up-hook.
Details
11-03-2008
6.00
Fabricated firewall upper panel.
Details
10-29-2008
9.00
Installed flap motor.
Details
10-28-2008
4.00
Fitted the trim motor.
Details
10-04-2008
4.50
Fabricated and fitted the control sticks.
09-28-2008
3.00
Shaving and sanding foam on the tail.
09-21-2008
10.00
Fabricated tie down.
Details
09-20-2008
8.00
Varnished.
Details
09-13-2008
6.50
Brake lines.
Details
09-12-2008
8.00
Completed installation of the control cables.
Details
09-11-2008
8.00
Continued installing control cables.
Details
09-10-2008
4.00
Fabricating and mounting control cables.
09-07-2008
3.00
Comm antenna.
Details
08-15-2008
2.00
Made a list.
Details
07-19-2008
2.00
MDRA inspection.
Details
07-16-2008
4.00
Worked on the tail, mounting the elevator and alli
07-06-2008
2.50
Fitting components to the firewall. Fabricating b
07-01-2008
2.00
Firewall.
Details
06-28-2008
1.00
Filled out and sent request for inspection from MD
06-18-2008
4.00
Sorted out the hardware.
Details
06-18-2008
6.50
Finished engine mount and installed the front gear
06-17-2008
9.50
Assembled wood structure.
Details
06-16-2008
7.00
Worked on the wood structure for the tail.
06-16-2008
8.00
Trimmed the openings.
Details
06-15-2008
2.00
Trimmed windows.
Details
06-14-2008
8.00
Trimmed plexiglass for windows.
06-13-2008
1.00
Installed shimmy damper on front gear.
06-12-2008
8.00
Manufactured brake lines.
Details
06-11-2008
7.50
Manufactured hydraulic lines.
06-10-2008
6.50
Fabricated hydraulic lines.
06-08-2008
8.00
Attached the landing gear.
06-08-2008
53.00
Assembly
Details
06-07-2008
8.00
Assembling parts.
Details
05-20-2008
8.00
Inventoried all of the parts I just purchased.
05-15-2008
10.00
Purchased partial kit (parts)
Details
SITE NAVIGATION
Contact Builder
Barracuda Home
Category
# Logs
# Hours
All
89
687
Avionics
11
92
Brakes
2
16
Center section
4
73
Cowling
2
18
Empennage
5
28
Engine
14
102
Fuselage
21
137
Hydraulics
4
30
Landing gear
6
34
Miscellaneous
11
56
Prop
1
8
Shop Supplies
1
4
Wings
7
89