Date
|
Hours
|
Work Log Summary
|
Details
|
03-21-2016
|
0.00
|
Airworthiness Inspection
|
Details
|
|
|
03-15-2016
|
0.49
|
Data plate
|
Details
|
|
|
03-08-2016
|
0.00
|
Weight and Balance
|
Details
|
|
|
03-07-2016
|
0.50
|
Stickers
|
Details
|
|
|
03-03-2016
|
0.50
|
Co-pilot stick
|
Details
|
|
|
03-02-2016
|
2.50
|
Wing tips installed, aircraft complete
|
Details
|
|
|
03-01-2016
|
6.00
|
Install cowl and fairings, install spinner
|
Details
|
|
|
02-29-2016
|
5.00
|
Calibrate compass, install interior
|
Details
|
|
|
02-26-2016
|
3.00
|
Paint cowl and fairings
|
Details
|
|
|
02-25-2016
|
4.00
|
Prime cowling and farings
|
Details
|
|
|
02-24-2016
|
4.00
|
Sand cowling halves
|
Details
|
|
|
02-23-2016
|
4.50
|
Fuel pump cover, fairings and cowl
|
Details
|
|
|
02-22-2016
|
5.00
|
Wiring a few more sensors
|
Details
|
|
|
02-20-2016
|
2.00
|
Radio cable, taxi tests
|
Details
|
|
|
02-19-2016
|
2.00
|
Engine run
|
Details
|
|
|
02-17-2016
|
4.00
|
First engine start, adjustments and mag timing
|
Details
|
|
|
02-16-2016
|
4.00
|
Prime fiberglass, test radio
|
Details
|
|
|
02-12-2016
|
4.00
|
Sand fiberglass parts
|
Details
|
|
|
02-11-2016
|
4.00
|
Cowl, cabin panels
|
Details
|
|
|
02-10-2016
|
4.50
|
Cowling, inlet fittings
|
Details
|
|
|
02-09-2016
|
5.50
|
Wiring debug
|
Details
|
|
|
02-08-2016
|
5.00
|
Cowl
|
Details
|
|
|
02-03-2016
|
6.00
|
Wing root fairings, wing walk material, cowl inlet
|
Details
|
|
|
02-02-2016
|
4.00
|
Tailwheel, canopy, cowl
|
Details
|
|
|
02-01-2016
|
6.00
|
Mag timing, fuel system flush
|
Details
|
|
|
01-30-2016
|
1.50
|
N numbers applied
|
Details
|
|
|
01-29-2016
|
5.00
|
Tanks screws, prop unwrapped
|
Details
|
|
|
01-28-2016
|
2.00
|
Tank screws
|
Details
|
|
|
01-27-2016
|
6.50
|
ELT, rear panel, seat belts
|
Details
|
|
|
01-26-2016
|
4.00
|
Troubleshooting, GPS aquisition
|
Details
|
|
|
01-25-2016
|
6.00
|
Troubleshooting
|
Details
|
|
|
01-21-2016
|
5.00
|
Wiring debug
|
Details
|
|
|
01-20-2016
|
5.00
|
Skyview first power-up
|
Details
|
|
|
01-19-2016
|
6.50
|
Oil drain, vent, panel, EFIS installed
|
Details
|
|
|
01-18-2016
|
5.50
|
Aileron rigging, flaps installed
|
Details
|
|
|
01-14-2016
|
2.00
|
|
Details
|
|
|
01-13-2016
|
3.00
|
Vent hole prep, spinner bulkhead and cowl fitting
|
Details
|
|
|
01-12-2016
|
3.00
|
Right fuel tank
|
Details
|
|
|
01-11-2016
|
7.00
|
Wing bolts torqued, gusset bolts, left tank
|
Details
|
|
|
01-08-2016
|
4.00
|
Wings and prop
|
Details
|
|
|
01-06-2016
|
3.00
|
Gear dampeners, Flap hinge wires
|
Details
|
|
|
01-05-2016
|
5.00
|
Battery wire, wingtip wiring
|
Details
|
|
|
12-30-2015
|
2.50
|
Brake fluid charge, bulkhead bolts
|
Details
|
|
|
12-29-2015
|
2.00
|
Main bulkhead gussets
|
Details
|
|
|
12-28-2015
|
6.00
|
Battery, pitot and mast
|
Details
|
|
|
12-21-2015
|
4.00
|
Empennage fairings, wingtip lights
|
Details
|
|
|
12-18-2015
|
6.00
|
Install Skyview panel modules, wiring
|
Details
|
|
|
12-17-2015
|
6.00
|
Panel install
|
Details
|
|
|
12-16-2015
|
6.50
|
Intersection fairing platenuts, panel install
|
Details
|
|
|
12-15-2015
|
7.50
|
Prime and paint moldings and empennage fairings
|
Details
|
|
|
12-14-2015
|
6.50
|
Canopy moldings
|
Details
|
|
|
12-11-2015
|
4.00
|
Fiberglass, doghouse
|
Details
|
|
|
12-10-2015
|
4.50
|
Fiberglass work
|
Details
|
|
|
12-09-2015
|
5.00
|
Cowl, moldings, fairings
|
Details
|
|
|
12-08-2015
|
5.50
|
Cowl and base molding
|
Details
|
|
|
12-07-2015
|
6.50
|
Cowl and other stuff
|
Details
|
|
|
12-04-2015
|
6.00
|
Base and canopy top molding
|
Details
|
|
|
12-03-2015
|
5.50
|
Canopy base and top molding
|
Details
|
|
|
12-02-2015
|
5.50
|
Base molding, cowl hinge, slider latch
|
Details
|
|
|
12-01-2015
|
5.50
|
Plenum seals, canopy base molding
|
Details
|
|
|
11-30-2015
|
4.50
|
Base molding prep, intersection fairings
|
Details
|
|
|
11-23-2015
|
4.50
|
Empennage fairing, plenum
|
Details
|
|
|
11-20-2015
|
6.00
|
Canopy, plenum
|
Details
|
|
|
11-19-2015
|
5.00
|
Canopy
|
Details
|
|
|
11-18-2015
|
6.00
|
Canopy
|
Details
|
|
|
11-17-2015
|
6.50
|
Canopy, windscrren
|
Details
|
|
|
11-16-2015
|
3.00
|
Prep dash for paint
|
Details
|
|
|
11-12-2015
|
5.00
|
Canopy preparation
|
Details
|
|
|
11-11-2015
|
6.50
|
Vent ducts, canopy skirt, anchor blocks
|
Details
|
|
|
11-10-2015
|
6.00
|
Upper cowl rework
|
Details
|
|
|
11-09-2015
|
6.50
|
Cowl oil door
|
Details
|
|
|
11-06-2015
|
6.50
|
Windscreen, induction, rear skirt
|
Details
|
|
|
11-05-2015
|
6.00
|
Rivet cowl hinges, rivet forward top skin, fit win
|
Details
|
|
|
11-04-2015
|
5.50
|
Induction system, cowling
|
Details
|
|
|
11-03-2015
|
5.50
|
Induction, Ignition wires, top cowl
|
Details
|
|
|
11-02-2015
|
6.00
|
Foreward top skin, cowling
|
Details
|
|
|
10-30-2015
|
6.00
|
Foreward top skin, top cowl
|
Details
|
|
|
10-29-2015
|
6.00
|
Cowl hinges, top skin
|
Details
|
|
|
10-28-2015
|
6.00
|
Baffles
|
Details
|
|
|
10-27-2015
|
6.50
|
Baffles
|
Details
|
|
|
10-26-2015
|
7.00
|
Baffles
|
Details
|
|
|
10-21-2015
|
5.00
|
GPS mount, hinge pins
|
Details
|
|
|
10-20-2015
|
6.00
|
Insulation, baffle seals
|
Details
|
|
|
10-19-2015
|
6.50
|
Baffles, insulation
|
Details
|
|
|
10-15-2015
|
5.50
|
Cowl
|
Details
|
|
|
10-14-2015
|
5.50
|
Engine cowling
|
Details
|
|
|
10-13-2015
|
6.50
|
Engine cowling
|
Details
|
|
|
10-12-2015
|
6.00
|
Baffles, prop spacer, lower cowl
|
Details
|
|
|
10-08-2015
|
3.00
|
Baffles
|
Details
|
|
|
10-07-2015
|
6.00
|
Baffles
|
Details
|
|
|
10-06-2015
|
5.00
|
Foreward top skin, prop spacer
|
Details
|
|
|
10-05-2015
|
4.50
|
Electric cable, sniffle valve
|
Details
|
|
|
10-01-2015
|
6.00
|
Prop control instaled
|
Details
|
|
|
09-25-2015
|
6.00
|
Air induction alternate air door
|
Details
|
|
|
09-24-2015
|
4.00
|
Air induction
|
Details
|
|
|
09-23-2015
|
6.00
|
Panel frame and brackets, mount toggle switches to
|
Details
|
|
|
09-22-2015
|
4.50
|
Prop control cable, baffles
|
Details
|
|
|
09-17-2015
|
6.00
|
Prop control, baffles, oil cooler
|
Details
|
|
|
09-16-2015
|
4.00
|
Tach cover, Red Cube, baffles
|
Details
|
|
|
09-02-2015
|
5.50
|
Mixture control, CHT wiring, cabin heat hose
|
Details
|
|
|
09-01-2015
|
5.00
|
Red cube, exhaust, EGT probes
|
Details
|
|
|
08-31-2015
|
5.00
|
Control cables, alternator fuse block
|
Details
|
|
|
08-27-2015
|
6.50
|
Exhaust system
|
Details
|
|
|
08-26-2015
|
2.00
|
Invert fuel spider
|
Details
|
|
|
08-25-2015
|
6.00
|
MAP, CHT, EMS harness
|
Details
|
|
|
08-24-2015
|
7.00
|
Baffling baffles, MAP sensors, ground strap
|
Details
|
|
|
08-21-2015
|
6.00
|
Engine baffles
|
Details
|
|
|
08-20-2015
|
5.00
|
Engine Baffles
|
Details
|
|
|
08-19-2015
|
4.50
|
EI harness, oli hoses
|
Details
|
|
|
08-18-2015
|
5.50
|
Electroair wiring harness
|
Details
|
|
|
08-17-2015
|
6.00
|
Porp goveror, oil pressure fitting
|
Details
|
|
|
08-13-2015
|
5.50
|
Fuel vent, oli tank bracket, engine controls
|
Details
|
|
|
08-12-2015
|
6.50
|
Electric Ignition controller mount
|
Details
|
|
|
08-11-2015
|
5.50
|
Oil & fuel systems
|
Details
|
|
|
08-05-2015
|
6.50
|
Christen inverted oil system
|
Details
|
|
|
08-04-2015
|
6.50
|
Mount engine, alternator, fule injection
|
Details
|
|
|
08-03-2015
|
8.00
|
Mount ignition coil, hoist engine
|
Details
|
|
|
07-30-2015
|
5.00
|
Wheel pants, emp. fairing, engine delivery
|
Details
|
|
|
07-29-2015
|
5.00
|
Wheel/Intersection fairings
|
Details
|
|
|
07-28-2015
|
5.00
|
Glass whlle and intersection fairings
|
Details
|
|
|
07-27-2015
|
4.50
|
Left wheel fairing, lower intersection fairings
|
Details
|
|
|
07-24-2015
|
2.00
|
Wheel fairing
|
Details
|
|
|
07-23-2015
|
4.00
|
Wheel fairings
|
Details
|
|
|
07-22-2015
|
7.00
|
Canopy
|
Details
|
|
|
07-21-2015
|
5.50
|
Canopy
|
Details
|
|
|
07-20-2015
|
7.00
|
Canopy side skins
|
Details
|
|
|
07-16-2015
|
4.50
|
Canopy
|
Details
|
|
|
07-15-2015
|
5.50
|
Right wheel fairing
|
Details
|
|
|
07-14-2015
|
4.50
|
Left wheel fairing
|
Details
|
|
|
07-13-2015
|
6.00
|
Leg fairing alignment, wing tips
|
Details
|
|
|
07-08-2015
|
5.00
|
Taxi/Landing lights, wheel pant
|
Details
|
|
|
07-07-2015
|
5.00
|
Wingtip lighting
|
Details
|
|
|
07-06-2015
|
4.50
|
Wing tip lights
|
Details
|
|
|
06-29-2015
|
5.00
|
Wing tip
|
Details
|
|
|
06-25-2015
|
6.50
|
Leg fairing and wingtips
|
Details
|
|
|
06-24-2015
|
6.00
|
Brake line, fairings
|
Details
|
|
|
06-23-2015
|
5.50
|
Antennae, Brake line
|
Details
|
|
|
06-22-2015
|
6.50
|
Install landing gear
|
Details
|
|
|
06-18-2015
|
2.50
|
Firewall recess, battery box, tunnel cover
|
Details
|
|
|
06-17-2015
|
4.00
|
Firewall recess
|
Details
|
|
|
06-16-2015
|
6.00
|
Panel prep, Capacitance to Voltage couplings
|
Details
|
|
|
06-15-2015
|
6.50
|
Panel, Cabin Heat control, Keyed ignition
|
Details
|
|
|
06-10-2015
|
6.50
|
Dynon Skyview wiring
|
Details
|
|
|
06-09-2015
|
7.00
|
Dynon Skyview wiring
|
Details
|
|
|
06-08-2015
|
6.00
|
Dynon Skyview wiring
|
Details
|
|
|
06-04-2015
|
6.50
|
Left panel prep
|
Details
|
|
|
06-03-2015
|
6.50
|
Panel cut-outs
|
Details
|
|
|
06-02-2015
|
6.00
|
Center panel, stick grips
|
Details
|
|
|
06-01-2015
|
6.00
|
ADAHRS, panel
|
Details
|
|
|
05-28-2015
|
5.00
|
Drill and attach platenuts
|
Details
|
|
|
05-28-2015
|
6.00
|
Ammeter shunt, wiring
|
Details
|
|
|
05-26-2015
|
5.00
|
Wiring harness
|
Details
|
|
|
05-20-2015
|
4.00
|
Install pitch AP servo,
|
Details
|
|
|
05-19-2015
|
5.50
|
Brake assembly, Dynon installation started
|
Details
|
|
|
05-18-2015
|
0.01
|
Dynon Skyview delivery
|
Details
|
|
|
05-13-2015
|
4.00
|
Wheels and brakes
|
Details
|
|
|
05-12-2015
|
2.50
|
Rudder bolts, engine mount
|
Details
|
|
|
05-11-2015
|
4.50
|
VS/HSTips install
|
Details
|
|
|
05-07-2015
|
5.50
|
Prime and paint fiberglass tips
|
Details
|
|
|
05-06-2015
|
5.00
|
Fiberglass work
|
Details
|
|
|
05-05-2015
|
4.00
|
Fiberglass work
|
Details
|
|
|
05-04-2015
|
2.50
|
Fiberglass tips
|
Details
|
|
|
05-02-2015
|
2.00
|
Tail light adapter
|
Details
|
|
|
04-29-2015
|
8.00
|
Wing tips
|
Details
|
|
|
04-28-2015
|
6.50
|
Fibergalss tips
|
Details
|
|
|
04-27-2015
|
3.50
|
Elevator tips
|
Details
|
|
|
04-20-2015
|
4.50
|
PTT wiring, fuel pump wiring
|
Details
|
|
|
04-16-2015
|
2.50
|
Fuel pump plumbing
|
Details
|
|
|
04-15-2015
|
6.50
|
Aileron trim, tailwheel link, fuel pump installati
|
Details
|
|
|
04-14-2015
|
6.00
|
Install and rig elevators, replace VS, revise pane
|
Details
|
|
|
04-13-2015
|
4.00
|
Elevator trim wiring, attach elevators
|
Details
|
|
|
04-10-2015
|
3.00
|
Empennage fairing, elevator trim
|
Details
|
|
|
04-08-2015
|
2.50
|
Empennage fairing
|
Details
|
|
|
04-07-2015
|
7.00
|
Empennage attached
|
Details
|
|
|
04-06-2015
|
6.50
|
Antenna
|
Details
|
|
|
04-03-2015
|
3.00
|
Brake lines, wiring
|
Details
|
|
|
04-02-2015
|
5.00
|
Parking brake, paint, antenna doublers
|
Details
|
|
|
04-01-2015
|
2.50
|
Rudder cables, parking brake
|
Details
|
|
|
03-31-2015
|
5.00
|
|
Details
|
|
|
03-30-2015
|
7.00
|
Wiring and plumbing
|
Details
|
|
|
03-26-2015
|
6.50
|
Panel, wiring
|
Details
|
|
|
03-25-2015
|
6.50
|
Wiring, aileron trim installed
|
Details
|
|
|
03-24-2015
|
6.50
|
Rivet front deck,throttle quadrant, run wires, fi
|
Details
|
|
|
03-23-2015
|
6.00
|
Begin riveting of forward deck
|
Details
|
|
|
03-20-2015
|
3.50
|
Battery box
|
Details
|
|
|
03-19-2015
|
6.00
|
Heater control, battery box, solenoid mounts
|
Details
|
|
|
03-18-2015
|
5.00
|
Side rails, brake lines, roll bar
|
Details
|
|
|
03-17-2015
|
4.00
|
Reinstall cabin parts
|
Details
|
|
|
03-16-2015
|
6.00
|
Paint cabin
|
Details
|
|
|
03-15-2015
|
5.00
|
Paint cabin interior
|
Details
|
|
|
03-12-2015
|
4.00
|
Prime interior panels
|
Details
|
|
|
03-11-2015
|
0.00
|
Build paint booth
|
Details
|
|
|
03-10-2015
|
5.00
|
Platenuts, front deck
|
Details
|
|
|
03-09-2015
|
5.00
|
Mask cabin interior
|
Details
|
|
|
03-04-2015
|
4.00
|
Prep work, remove wings
|
Details
|
|
|
03-03-2015
|
5.50
|
Scuff cabin interior
|
Details
|
|
|
03-02-2015
|
6.50
|
Platenuts, prep for cabin paint
|
Details
|
|
|
02-25-2015
|
5.50
|
Root fairings
|
Details
|
|
|
02-24-2015
|
2.00
|
Wing root fairing
|
Details
|
|
|
02-23-2015
|
6.50
|
Flap actuator, wing attach, right tank
|
Details
|
|
|
02-19-2015
|
5.00
|
Wiring harnesses
|
Details
|
|
|
02-18-2015
|
5.00
|
Wiring harness
|
Details
|
|
|
02-16-2015
|
5.50
|
Fit flaps and pushrods
|
Details
|
|
|
02-12-2015
|
5.00
|
Set wing incidence, control rigging
|
Details
|
|
|
02-11-2015
|
6.00
|
Fit fuel pump covers, fit wings
|
Details
|
|
|
02-10-2015
|
5.50
|
Fuel tank attach brackets
|
Details
|
|
|
02-09-2015
|
5.50
|
Engine mount, plumbings
|
Details
|
|
|
02-06-2015
|
2.00
|
Roll bar installation
|
Details
|
|
|
02-04-2015
|
6.50
|
Fuselage odds and ends
|
Details
|
|
|
02-03-2015
|
6.00
|
Fuel Pump cover, Parking brake, Fuel lines and ven
|
Details
|
|
|
02-02-2015
|
6.00
|
Slider, fuel pump mount
|
Details
|
|
|
01-28-2015
|
6.00
|
Top skin dimpled, slider frame installation.
|
Details
|
|
|
01-27-2015
|
6.50
|
Drill top skin, roll bar
|
Details
|
|
|
01-26-2015
|
6.00
|
Panel frame, top skin
|
Details
|
|
|
01-24-2015
|
5.00
|
Rear baggage panels, instrument panel
|
Details
|
|
|
01-22-2015
|
8.00
|
Cowl hinges. parking brake, rear wall
|
Details
|
|
|
01-21-2015
|
7.00
|
Cowl hinges, brake reservoir, Vertical Power brack
|
Details
|
|
|
01-20-2015
|
4.00
|
Empennage fairining fittings
|
Details
|
|
|
01-19-2015
|
6.00
|
Odds and ends at tail section
|
Details
|
|
|
01-17-2015
|
1.00
|
Inventory hardware bag
|
Details
|
|
|
01-16-2015
|
4.50
|
Elevator pushrods, unpack finishing kit
|
Details
|
|
|
01-15-2015
|
0.00
|
Starting to look like an airplane!!
|
Details
|
|
|
01-15-2015
|
8.00
|
Fitting empennage
|
Details
|
|
|
01-14-2015
|
3.50
|
VHorizontal and Vertical stabilizers
|
Details
|
|
|
01-13-2015
|
6.00
|
Front deck, HS drilled
|
Details
|
|
|
01-12-2015
|
5.50
|
Front deck, fuel valve
|
Details
|
|
|
01-07-2015
|
5.00
|
Aileron trim, shoulder harness brackets
|
Details
|
|
|
01-06-2015
|
7.50
|
Aileron trim, rivet top skins
|
Details
|
|
|
01-05-2015
|
5.00
|
Top skins
|
Details
|
|
|
01-03-2015
|
3.00
|
Static run and wiring
|
Details
|
|
|
01-02-2015
|
3.00
|
Static tubing, AP servo bracket
|
Details
|
|
|
12-27-2014
|
4.00
|
Top skins
|
Details
|
|
|
12-24-2014
|
2.00
|
Flap motor plate rework
|
Details
|
|
|
12-22-2014
|
2.00
|
Flap actuator
|
Details
|
|
|
12-20-2014
|
2.50
|
Flap actuator
|
Details
|
|
|
12-19-2014
|
6.00
|
Flap actuator
|
Details
|
|
|
12-09-2014
|
2.00
|
Seat Backs
|
Details
|
|
|
12-08-2014
|
9.00
|
Seat backs. flap actuator
|
Details
|
|
|
12-04-2014
|
7.00
|
Forward cabin covers
|
Details
|
|
|
12-03-2014
|
7.50
|
Seat backs, forward covers
|
Details
|
|
|
12-02-2014
|
2.50
|
Seat backs
|
Details
|
|
|
12-01-2014
|
5.00
|
Forward seat floors and tunnel cover
|
Details
|
|
|
11-26-2014
|
5.00
|
Aft seat floor
|
Details
|
|
|
11-25-2014
|
6.00
|
Floors
|
Details
|
|
|
11-24-2014
|
6.00
|
Inside fuselage
|
Details
|
|
|
11-21-2014
|
6.00
|
Fit top skins
|
Details
|
|
|
11-20-2014
|
3.00
|
Bellcrank, gussets
|
Details
|
|
|
11-19-2014
|
5.00
|
Skins, side plate, deck, gusset, more
|
Details
|
|
|
11-18-2014
|
6.00
|
Side rail, side skin, canopy deck, gussets
|
Details
|
|
|
11-17-2014
|
6.00
|
Aft deck, side rails
|
Details
|
|
|
11-13-2014
|
3.00
|
Aft deck
|
Details
|
|
|
11-12-2014
|
5.00
|
Complete side skins, "Roll over the Canoe" !!!!
|
Details
|
|
|
11-11-2014
|
5.00
|
Rivet side skins
|
Details
|
|
|
11-10-2014
|
8.00
|
Rivet side skins
|
Details
|
|
|
11-08-2014
|
3.00
|
Prep
|
Details
|
|
|
11-07-2014
|
5.00
|
Prep for side skin riveting
|
Details
|
|
|
10-30-2014
|
2.00
|
Right side skin
|
Details
|
|
|
10-29-2014
|
7.00
|
Prep side skins
|
Details
|
|
|
10-28-2014
|
5.50
|
Aft to Center fuselage
|
Details
|
|
|
10-23-2014
|
6.00
|
Complete prep, begin reassembly
|
Details
|
|
|
10-22-2014
|
6.50
|
Fuselage parts prep
|
Details
|
|
|
10-21-2014
|
7.00
|
Center fuselage prep
|
Details
|
|
|
10-20-2014
|
6.00
|
Foreward fuselage prep, bkkae master cylinders
|
Details
|
|
|
10-17-2014
|
6.00
|
Disassembly and final prep
|
Details
|
|
|
10-16-2014
|
5.00
|
Foreward fuselage disassembly
|
Details
|
|
|
10-09-2014
|
4.50
|
Rudder pedals
|
Details
|
|
|
10-08-2014
|
6.50
|
Floor stiffeners, baggage area, rudder pedals
|
Details
|
|
|
10-07-2014
|
5.50
|
Longerons for left side, forward bulkhead, gear we
|
Details
|
|
|
10-06-2014
|
6.50
|
Reinforcement angles, brake pedals
|
Details
|
|
|
10-02-2014
|
7.00
|
Forward fuselage
|
Details
|
|
|
10-01-2014
|
6.00
|
Forward fuselage
|
Details
|
|
|
09-30-2014
|
0.00
|
Tailcone completed view
|
Details
|
|
|
09-30-2014
|
5.50
|
Drill side skins and longerons
|
Details
|
|
|
09-29-2014
|
5.00
|
Forward side skins
|
Details
|
|
|
09-26-2014
|
8.00
|
Aft fuselage rivet, join to center section
|
Details
|
|
|
09-25-2014
|
6.00
|
Aft fuselage riveting
|
Details
|
|
|
09-24-2014
|
0.00
|
New hangar ready for building!
|
Details
|
|
|
09-24-2014
|
3.00
|
Aft fuselage assembly
|
Details
|
|
|
09-16-2014
|
0.00
|
Hangar move
|
Details
|
|
|
09-15-2014
|
0.00
|
Start move to new hangar
|
Details
|
|
|
09-15-2014
|
2.50
|
Drill seat and baggage floors
|
Details
|
|
|
09-11-2014
|
2.50
|
Center and aft fuselage
|
Details
|
|
|
09-10-2014
|
3.50
|
Rivet center fuselage bottom skin
|
Details
|
|
|
09-10-2014
|
0.00
|
Hangar floor surfacing
|
Details
|
|
|
09-10-2014
|
1.50
|
Aft fuselage assembly
|
Details
|
|
|
09-09-2014
|
0.00
|
New Hangar leased
|
Details
|
|
|
09-09-2014
|
4.00
|
Center fuselage assembly
|
Details
|
|
|
09-08-2014
|
6.00
|
Assemble center fuselage
|
Details
|
|
|
09-03-2014
|
5.00
|
Center fuselage
|
Details
|
|
|
09-02-2014
|
6.00
|
Center fuselage prep
|
Details
|
|
|
08-27-2014
|
7.00
|
Center fusleage
|
Details
|
|
|
08-26-2014
|
7.00
|
Aft and Center fuselage
|
Details
|
|
|
08-25-2014
|
6.50
|
Aft Fuselage
|
Details
|
|
|
08-14-2014
|
6.00
|
Aft fuselage
|
Details
|
|
|
08-13-2014
|
5.50
|
Aft Fuselage
|
Details
|
|
|
08-12-2014
|
7.50
|
Rear fuselage initial assembly
|
Details
|
|
|
08-11-2014
|
7.00
|
710-712 bulkheads, longerons
|
Details
|
|
|
08-07-2014
|
5.50
|
Bulkheads 706, 707, and 708
|
Details
|
|
|
08-06-2014
|
6.50
|
F-705 Bulkhead completed
|
Details
|
|
|
08-05-2014
|
7.50
|
F-705 Bulkhead
|
Details
|
|
|
08-04-2014
|
6.50
|
Center section bulkheads completed
|
Details
|
|
|
08-01-2014
|
0.50
|
Alodine parts
|
Details
|
|
|
07-31-2014
|
7.00
|
F704 Center section bulkhead
|
Details
|
|
|
07-28-2014
|
3.00
|
F-704 Bulkhead
|
Details
|
|
|
07-23-2014
|
5.50
|
Assemble and rivet firewall
|
Details
|
|
|
07-22-2014
|
6.50
|
Firewall work continued
|
Details
|
|
|
07-21-2014
|
6.50
|
Fuselage work begins!!!
|
Details
|
|
|
07-16-2014
|
7.00
|
Fuselage kit delivery!
|
Details
|
|
|
07-14-2014
|
1.00
|
Trim servo
|
Details
|
|
|
07-09-2014
|
2.50
|
SB 2014-1-31 completed
|
Details
|
|
|
07-09-2014
|
0.50
|
Rudder hinges
|
Details
|
|
|
07-09-2014
|
0.00
|
|
Details
|
|
|
07-08-2014
|
5.00
|
HS SB
|
Details
|
|
|
07-07-2014
|
4.00
|
HS SB
|
Details
|
|
|
07-01-2014
|
3.00
|
S.B 14-01-31 Horizontal stabilizer spar
|
Details
|
|
|
06-30-2014
|
2.00
|
Bottom skins finished!
|
Details
|
|
|
06-25-2014
|
6.00
|
Bottom skins
|
Details
|
|
|
06-24-2014
|
5.00
|
Bottom skins
|
Details
|
|
|
06-23-2014
|
4.50
|
Bottom skins
|
Details
|
|
|
06-19-2014
|
4.00
|
Left wing bottom skins
|
Details
|
|
|
06-18-2014
|
4.00
|
Bottom left skins
|
Details
|
|
|
06-17-2014
|
5.00
|
Aileron stops, wiring, bottom skin
|
Details
|
|
|
06-11-2014
|
6.00
|
Drill left flap hinge, rivet brace, dimple skins
|
Details
|
|
|
06-10-2014
|
7.50
|
Ailerons and flaps
|
Details
|
|
|
06-09-2014
|
9.00
|
Dimple skins, mount aileron and flap
|
Details
|
|
|
06-05-2014
|
4.50
|
Prep wing bottom skins
|
Details
|
|
|
06-04-2014
|
7.00
|
Completed left flap and pushrods
|
Details
|
|
|
06-03-2014
|
6.50
|
Stall warning, mount tank, left flap
|
Details
|
|
|
06-02-2014
|
7.00
|
Flaps
|
Details
|
|
|
05-29-2014
|
3.00
|
Right flap work
|
Details
|
|
|
05-28-2014
|
5.50
|
Tank test. flaps
|
Details
|
|
|
05-28-2014
|
0.50
|
Tank test
|
Details
|
|
|
05-27-2014
|
8.00
|
Tank pressure test, wing wiring, flaps
|
Details
|
|
|
05-21-2014
|
7.00
|
TANKS ARE FINISHED!!!
|
Details
|
|
|
05-20-2014
|
6.00
|
Tank baffles installed
|
Details
|
|
|
05-19-2014
|
6.00
|
Tank leak test, Flaps
|
Details
|
|
|
05-19-2014
|
1.00
|
Preliminary tank test
|
Details
|
|
|
05-15-2014
|
2.00
|
Aileron pushrods, Flaps
|
Details
|
|
|
05-15-2014
|
2.00
|
Access covers installed
|
Details
|
|
|
05-14-2014
|
4.00
|
Fuel senders, end rib fillets
|
Details
|
|
|
05-13-2014
|
2.50
|
Tank angles and nose reinforcements
|
Details
|
|
|
05-12-2014
|
5.50
|
Outside ribs riveted
|
Details
|
|
|
05-12-2014
|
0.00
|
Hanagar steel
|
Details
|
|
|
05-07-2014
|
5.50
|
Tank outer ribs
|
Details
|
|
|
05-06-2014
|
5.50
|
Hodgepdge
|
Details
|
|
|
05-06-2014
|
0.00
|
First steel!
|
Details
|
|
|
05-05-2014
|
0.00
|
New hangar progress
|
Details
|
|
|
05-05-2014
|
7.00
|
Interior rib prep, sealant
|
Details
|
|
|
05-02-2014
|
4.00
|
Right tank work
|
Details
|
|
|
05-01-2014
|
5.00
|
Rivet right tank ribs
|
Details
|
|
|
05-01-2014
|
0.00
|
Hangar steel delivered
|
Details
|
|
|
04-29-2014
|
6.00
|
Rivet right tank ribs
|
Details
|
|
|
04-28-2014
|
4.00
|
Assemble inner ribs to skin with sealant
|
Details
|
|
|
04-24-2014
|
5.00
|
Rivet tank stiffeners
|
Details
|
|
|
04-24-2014
|
0.00
|
New hangar pad
|
Details
|
|
|
04-22-2014
|
5.00
|
Tank prep work completed
|
Details
|
|
|
04-22-2014
|
0.00
|
New hangar pad poured
|
Details
|
|
|
04-21-2014
|
0.00
|
New hangar
|
Details
|
|
|
04-21-2014
|
5.00
|
Completed ailerons
|
Details
|
|
|
04-16-2014
|
4.50
|
Ailerons, left assembled
|
Details
|
|
|
04-15-2014
|
6.00
|
Ailerons
|
Details
|
|
|
04-14-2014
|
6.00
|
Ailerons
|
Details
|
|
|
04-09-2014
|
3.00
|
Rivet aileron stiffeners
|
Details
|
|
|
04-07-2014
|
5.00
|
Ailerons and bellcranks
|
Details
|
|
|
03-31-2014
|
5.50
|
Rivet top skins, aileron brackets
|
Details
|
|
|
03-14-2014
|
1.00
|
Wing trailing edge skin
|
Details
|
|
|
03-09-2014
|
4.00
|
Rivet tops skins on right wing
|
Details
|
|
|
03-08-2014
|
2.00
|
Prepare tank skin
|
Details
|
|
|
03-08-2014
|
1.00
|
Mounted elevator trim servo
|
Details
|
|
|
03-08-2014
|
2.00
|
Deburr and dimple skin
|
Details
|
|
|
02-25-2014
|
2.50
|
Right leading edge, dimple skins
|
Details
|
|
|
02-24-2014
|
2.50
|
Attach right leading edge
|
Details
|
|
|
02-20-2014
|
1.50
|
Soldering tank sender wires
|
Details
|
|
|
02-05-2014
|
3.00
|
Rivet leading edge, countersink spar
|
Details
|
|
|
02-01-2014
|
2.50
|
Assemble right leading edge
|
Details
|
|
|
01-27-2014
|
3.50
|
Right leading edge prep
|
Details
|
|
|
01-20-2014
|
2.50
|
Deburr and dimple wing skeleton
|
Details
|
|
|
01-16-2014
|
1.50
|
Leading edge prep
|
Details
|
|
|
01-13-2014
|
3.00
|
Remake left tank attach angle
|
Details
|
|
|
01-04-2014
|
2.50
|
Rework
|
Details
|
|
|
12-30-2013
|
2.00
|
Rib and stiffener prep
|
Details
|
|
|
12-27-2013
|
2.00
|
Tank misc.
|
Details
|
|
|
12-27-2013
|
4.00
|
Assemble elevators to vertical stabilizer
|
Details
|
|
|
12-23-2013
|
3.50
|
Tank prep
|
Details
|
|
|
12-21-2013
|
6.00
|
More tank prep
|
Details
|
|
|
12-18-2013
|
3.50
|
Tank prep
|
Details
|
|
|
12-03-2013
|
3.50
|
Drill right leading edge and tank
|
Details
|
|
|
11-26-2013
|
4.25
|
Right fuel tank assembly
|
Details
|
|
|
11-23-2013
|
6.00
|
Right wing skins and leading edge
|
Details
|
|
|
11-18-2013
|
2.00
|
Fitting of right wing skins
|
Details
|
|
|
11-14-2013
|
2.00
|
Right wing skeleton
|
Details
|
|
|
11-12-2013
|
2.50
|
Assemble right wing skeleton
|
Details
|
|
|
11-10-2013
|
5.00
|
Left wing to cradle, start on right
|
Details
|
|
|
11-07-2013
|
1.50
|
Completed riveting left top skin
|
Details
|
|
|
11-04-2013
|
2.25
|
Left top outboard wing skin
|
Details
|
|
|
11-03-2013
|
4.50
|
Rivet left inboard skin
|
Details
|
|
|
11-02-2013
|
4.50
|
Rivet left top wing skins
|
Details
|
|
|
10-30-2013
|
2.00
|
Rivet left leading edge ribs to spar
|
Details
|
|
|
10-28-2013
|
2.00
|
Rivet leading edge to spar
|
Details
|
|
|
10-26-2013
|
5.00
|
Prep left wing skeleton
|
Details
|
|
|
10-24-2013
|
2.00
|
Rivet left leading edge
|
Details
|
|
|
10-21-2013
|
2.00
|
Rivet left leading edge
|
Details
|
|
|
10-13-2013
|
6.00
|
Prep leading edge
|
Details
|
|
|
10-07-2013
|
2.50
|
Tank fittings, capacitive plates
|
Details
|
|
|
10-03-2013
|
3.00
|
Left tank prep
|
Details
|
|
|
10-01-2013
|
2.50
|
Left fuel tank fitting
|
Details
|
|
|
09-29-2013
|
4.50
|
Fuel tank assembly
|
Details
|
|
|
09-28-2013
|
2.00
|
Fitting tank attach angles
|
Details
|
|
|
09-25-2013
|
2.75
|
Left Wing Leading edge
|
Details
|
|
|
09-23-2013
|
2.25
|
Fit and drill left wing skins
|
Details
|
|
|
09-22-2013
|
4.50
|
Wing skeleton and skins
|
Details
|
|
|
09-16-2013
|
2.50
|
Stall Warning
|
Details
|
|
|
09-11-2013
|
1.50
|
Rivet front spar
|
Details
|
|
|
09-04-2013
|
3.75
|
Wing skeleton
|
Details
|
|
|
09-03-2013
|
2.50
|
Deburr rib edges
|
Details
|
|
|
09-02-2013
|
1.50
|
Prep wing ribs
|
Details
|
|
|
08-29-2013
|
3.00
|
Prepare wing ribs
|
Details
|
|
|
08-26-2013
|
2.50
|
Rivet rear wing spars
|
Details
|
|
|
08-22-2013
|
3.00
|
Prep wing spar parts, assemble rear wing spars
|
Details
|
|
|
08-19-2013
|
3.00
|
Rear spar
|
Details
|
|
|
08-18-2013
|
5.00
|
Wing tie downs
|
Details
|
|
|
08-01-2013
|
0.50
|
Alodine tie down parts
|
Details
|
|
|
07-31-2013
|
3.00
|
Tie downs
|
Details
|
|
|
07-29-2013
|
3.00
|
Countersink spars, fabricate tie downs
|
Details
|
|
|
07-28-2013
|
2.50
|
Countersink and prime holes
|
Details
|
|
|
07-17-2013
|
2.50
|
Right wing platenuts
|
Details
|
|
|
07-16-2013
|
2.50
|
Spar prep
|
Details
|
|
|
07-15-2013
|
2.50
|
Spar prep work
|
Details
|
|
|
07-11-2013
|
3.00
|
Spar inspection, set up
|
Details
|
|
|
07-10-2013
|
3.00
|
Finished elevators, tail is complete!
|
Details
|
|
|
07-04-2013
|
1.50
|
Inventory wing hardware
|
Details
|
|
|
07-02-2013
|
2.50
|
Inventory wing kits
|
Details
|
|
|
07-02-2013
|
0.50
|
Fabricate eye bushing installation tool
|
Details
|
|
|
07-01-2013
|
3.50
|
Elevator leading edges
|
Details
|
|
|
06-26-2013
|
2.50
|
Roll elevator leading edge
|
Details
|
|
|
06-25-2013
|
2.50
|
Rivet and attach trim tab
|
Details
|
|
|
06-19-2013
|
3.00
|
Trim servo and trim tab
|
Details
|
|
|
06-17-2013
|
3.00
|
Rivet left elevator
|
Details
|
|
|
06-13-2013
|
1.00
|
Wing kit delivery
|
Details
|
|
|
06-13-2013
|
4.50
|
Left elevator
|
Details
|
|
|
06-10-2013
|
2.75
|
Assemble left elevator
|
Details
|
|
|
06-04-2013
|
2.50
|
Complere right elevator
|
Details
|
|
|
06-03-2013
|
2.00
|
Trim counterweight, right elevator rivet
|
Details
|
|
|
05-30-2013
|
3.00
|
Drill right elevator skins, rivet skeleton
|
Details
|
|
|
05-28-2013
|
2.00
|
Drill right rudder
|
Details
|
|
|
05-23-2013
|
6.00
|
Elevator stiffeners, bend TE and right elevator as
|
Details
|
|
|
05-22-2013
|
7.00
|
Elevator stiffeners
|
Details
|
|
|
05-20-2013
|
2.50
|
Elevator stiffeners
|
Details
|
|
|
05-13-2013
|
2.50
|
Complete rudder
|
Details
|
|
|
05-09-2013
|
2.50
|
Complete rudder trailing edge, bend leading edge
|
Details
|
|
|
05-06-2013
|
2.00
|
Rework rudder bottom, epoxy trailing edge
|
Details
|
|
|
05-05-2013
|
4.00
|
Rivet rudder
|
Details
|
|
|
05-02-2013
|
3.00
|
Prepare rudder skins, rivet skeleton base
|
Details
|
|
|
04-29-2013
|
2.50
|
Rudder continues
|
Details
|
|
|
04-25-2013
|
4.00
|
Tech Counselor, Rudder work
|
Details
|
|
|
04-22-2013
|
2.50
|
Assembled rudder
|
Details
|
|
|
04-08-2013
|
2.50
|
Rudder stiffeners
|
Details
|
|
|
04-04-2013
|
2.50
|
Prepared rudder stiffeners
|
Details
|
|
|
04-02-2013
|
2.25
|
Rivet vertical stabilizer
|
Details
|
|
|
03-30-2013
|
4.50
|
VS assembly
|
Details
|
|
|
03-29-2013
|
3.00
|
Prepared VS parts
|
Details
|
|
|
03-24-2013
|
2.75
|
Rivet HS skins to rear spar and ribs
|
Details
|
|
|
03-23-2013
|
4.50
|
Rivet right HS skin
|
Details
|
|
|
03-17-2013
|
6.00
|
Rivet main spar and left HS
|
Details
|
|
|
03-13-2013
|
2.50
|
Finished rear HS spar
|
Details
|
|
|
03-11-2013
|
2.50
|
Rivet rear spar
|
Details
|
|
|
03-07-2013
|
0.50
|
Clean and prime parts
|
Details
|
|
|
03-06-2013
|
3.50
|
Replacement parts arrive, complete HS drilling
|
Details
|
|
|
03-05-2013
|
2.00
|
Vertical stabilizer
|
Details
|
|
|
03-02-2013
|
4.00
|
Right HS assembly
|
Details
|
|
|
03-02-2013
|
0.00
|
DRDT-2
|
Details
|
|
|
02-28-2013
|
3.00
|
Left HS assembled
|
Details
|
|
|
02-25-2013
|
2.50
|
Front Spar
|
Details
|
|
|
02-20-2013
|
0.50
|
Primed rear spar reinforcements
|
Details
|
|
|
02-18-2013
|
2.00
|
Elevator bearing, rear spar
|
Details
|
|
|
02-17-2013
|
4.00
|
Rear Spar assembly
|
Details
|
|
|
02-16-2013
|
0.00
|
Tools inventoried and put away
|
Details
|
|
|
02-16-2013
|
0.00
|
Shop readied
|
Details
|
|
|
02-16-2013
|
3.00
|
Parts inventoried
|
Details
|
|
|
02-15-2013
|
0.00
|
Delivery!!
|
Details
|
|
|
02-11-2013
|
0.00
|
First orders
|
Details
|
|
|
02-10-2013
|
0.00
|
Sportair Workshop
|
Details
|
|