Work Logs Found: 924
Category Work Time: 2007 Hours
 Date
Hours
Work Log Summary

Details

 09-20-2022
6.50
DAR inspection!!
Details
     

 09-19-2022
5.00
recal W&B, calibrate fuel tank sensor
Details

 09-18-2022
6.50
perform weight and balance
Details
       

 09-17-2022
7.00
prep for weight and balance weighing
Details

 09-16-2022
5.00
cleanup wiring in instrument bay
Details
       

 09-15-2022
6.00
Tested pitot/static ports, reduce idle
Details
     

 09-14-2022
1.45
check static ports and pitot
Details

 09-13-2022
4.50
Installed nameplate and ELT
Details
       

 09-12-2022
4.00
Tightened canopy screws, ELT label
Details

 09-07-2022
2.50
Applied more placard items.
Details
     

 09-06-2022
1.50
Placard applying, taxiing, radio
Details
       

 09-05-2022
0.75
Fabricate flaperon skin adjust tool
Details

 08-24-2022
5.25
finished install of rear window
Details
       

 08-23-2022
2.50
ELT testing
Details
       

 08-17-2022
1.50
fixed ELT, installed some placards
Details
       

 08-16-2022
4.00
taxi, ELT work and rear window prep
Details
       

 08-15-2022
4.00
fairings, rear window work
Details
       

 08-14-2022
2.00
fairings sanding and finish priming
Details

 08-09-2022
2.30
Transition Training in RV-12
Details

 08-04-2022
8.00
taxi test, re-bleed right brake
Details

 08-03-2022
3.00
fit seat backs and bottoms
Details
       

 08-02-2022
2.00
install shoulder harnesses, other
Details
       

 08-01-2022
3.75
Install some seatbelts
Details
       

 07-31-2022
2.00
zeroed the ADAHRS
Details
     

 07-20-2022
2.00
put on cowls, show the plane
Details

 07-19-2022
2.25
wire-ties and RTV on the engine
Details
       

 07-18-2022
1.25
wire-tie and one RTV on the engine
Details

 07-17-2022
2.90
More taxi testing
Details

 07-16-2022
1.25
First time taxi testing
Details

 06-26-2022
1.75
torque the engine throttle cable clamps
Details

 06-25-2022
4.50
syncronized the engine carbs
Details

 06-23-2022
4.00
sand fit canopy, cotterpins on mains
Details
     

 06-22-2022
3.00
prime the enpennage fairings
Details
       

 06-21-2022
1.00
prep empenage fairings for prime
Details

 06-17-2022
1.75
blue wrap on crossover bar
Details
     

 06-16-2022
2.00
replaced valve cover bolt
Details

 06-13-2022
2.25
check engine lifters
Details

 06-04-2022
1.50
major engine run, very successful
Details

 06-02-2022
2.00
remove seat ramp, misc
Details

 05-31-2022
3.25
adjusted thottle cables, misc
Details
       

 05-29-2022
2.25
fixed EGT wiring, and misc
Details

 05-28-2022
2.00
first engine start!!
Details
     

 05-27-2022
2.00
tested fuel flow per PAP
Details

 05-25-2022
1.75
partial install of rear window
Details

 05-21-2022
2.50
added fuel for the first time
Details

 05-19-2022
1.50
get engine ready to run
Details

 05-18-2022
6.00
completed blue wrap on the rollbar
Details
       

 05-17-2022
2.00
apply more blue wrap
Details
     

 05-13-2022
2.00
torque seal and apply blue wrap
Details
     

 05-11-2022
2.75
screwed rear bulkhead plate, misc
Details
     

 05-10-2022
3.00
final tension of stab cables,misc.
Details
       

 05-09-2022
3.60
adjust horz. stab cables
Details

 05-06-2022
2.00
added more oil, install seat ramp
Details

 05-05-2022
1.25
added engine antifreeze
Details

 05-04-2022
3.00
reinstall fuel tank, filler tube
Details
       

 04-29-2022
1.25
finish clips on the last rib
Details
     

 04-28-2022
4.00
fabricate floor pads, drill rivets
Details
       

 04-27-2022
2.00
start on service bulletin
Details
     

 04-26-2022
2.40
perform SB 10-3-17 radiator clearance
Details

 04-24-2022
2.00
Engine oil purge
Details

 04-22-2022
1.50
safety wire oil tank drain, oil purge
Details
       

 04-21-2022
2.50
put wrap on center support of roll bar
Details
     

 04-20-2022
0.75
check 50/50 water vinegar, fire ext.
Details

 04-18-2022
1.00
Tested oil purge and vinegar cleaning
Details

 04-12-2022
6.50
bleed the brake lines
Details
     

 04-10-2022
3.25
attached the rudder cable links, stab cables
Details
       

 04-09-2022
2.50
fabricate rudder cable links
Details
       

 04-07-2022
1.50
work on rudder cable links
Details
       

 04-05-2022
1.25
trim the left flaperon
Details
     

 04-04-2022
1.60
remove plastic film, file left flaperon
Details
       

 04-03-2022
1.50
remove almost all remaining protective plastic
Details
     

 04-02-2022
1.50
open talcone fairing hole
Details

 03-29-2022
2.50
check horiz stab servo trim tab clearance
Details
     

 03-28-2022
1.25
torque stabilator bolts,
Details
       

 03-25-2022
3.00
stabilator install.
Details

 03-23-2022
1.00
Prep part for SB-00053
Details

 03-20-2022
1.75
Remove stabilator and reglue washers
Details

 03-02-2022
4.00
install wings, test lights, etc. check CO monitor
Details
       

 03-01-2022
2.50
prepare wings for install, CO monitor setup
Details

 02-15-2022
1.00
corrected trim servo wiring
Details

 02-12-2022
0.50
enlarge bottom tailcone fairing hole an slot
Details

 02-10-2022
2.50
install tailcone fairings, check clearance
Details

 02-08-2022
2.25
step drill 3/4" hole in bottom tailcone fairing
Details

 01-29-2022
1.50
Temporary install of horz stab
Details
       

 01-27-2022
1.00
Update Syview, install horiz stab counter weight
Details
       

 01-13-2022
0.50
Installed the vertical stabilizer leading edge pie
Details

 01-08-2022
1.00
installed rudder top bolt, torqued vert. stab bolt
Details
     

 01-06-2022
1.00
made bolt holding tool
Details
     

 01-04-2022
2.00
moved H. Stab to hangar, mounted V. Stab
Details
       

 01-01-2022
1.50
Happy New Year, glued washers to H. stab.
Details
       

 12-20-2021
2.00
move fuselage to the hangar
Details
       

 12-18-2021
1.50
Replace the instrument bay cover, test fans
Details

 12-16-2021
0.75
re-install top cowling, install screws in spinner
Details

 12-15-2021
2.00
verified wire tie, replace wing roller bushings
Details

 12-14-2021
1.50

Details

 12-09-2021
4.50
move the wings to the hangar
Details
       

 12-03-2021
1.00
install both cowlings
Details

 11-29-2021
1.50
calibrate AP servos
Details

 11-28-2021
2.00
connect battery and power-up avionics
Details
     

 11-27-2021
3.25
install comm radio antenna
Details
       

 11-14-2021
2.25
finalize aft window fit, safety wire air cleaners
Details
       

 11-10-2021
0.75
drill #27 rear edge of aft window
Details

 11-09-2021
3.50
drill and tap #36 holes, sanded window for gap fit
Details

 11-08-2021
3.25
finished drilling #30 and #40 holes in aft window
Details
       

 11-07-2021
5.25
fit and clamp aft window
Details
       

 11-06-2021
1.50
finish rivet turtle deck skins
Details

 11-05-2021
1.50
rivet turtle deck skins
Details

 11-04-2021
2.75
Install fuel tank, fuel lines, fuel sender wire
Details
       

 11-03-2021
2.35
install shoulder harness cables cleco left turtle
Details

 10-05-2021
1.50
Prepare for next steps, place fuel tank
Details

 10-02-2021
3.00
mount prop blades and adjust pitch
Details
     

 10-01-2021
1.00
mount propeller aft mount hub
Details

 09-30-2021
2.50
more spinner work plus rivetting
Details
       

 09-29-2021
2.75
more spinner work
Details

 09-27-2021
2.00
work on the spinner
Details

 09-26-2021
3.25
work on spinner gap spacers
Details
     

 09-25-2021
1.25
more spinner work
Details
     

 09-24-2021
3.75
finish spinner while mounted
Details
       

 09-23-2021
2.75
work on the spinner, mount prop blades
Details
     

 09-22-2021
4.00
pitot yube and spinner work
Details
       

 09-21-2021
2.50
work on pitot tube
Details
     

 09-19-2021
1.50
attached throttle cables
Details
       

 09-17-2021
0.03
attach choke cables to carb
Details
       

 09-16-2021
1.00
finished cable spacer, installed cushioned clamp
Details
     

 09-14-2021
5.50
work on engine throttle controls
Details
       

 09-13-2021
0.50
Look at engine controls details
Details

 09-11-2021
3.50
install choke in instrument panel
Details
       

 09-10-2021
1.50
install throttle cable in instrument panel
Details
     

 09-08-2021
2.25
finish oil hoses, start install of throttle
Details
     

 09-07-2021
2.75
talked to Vans on the oil hoses
Details
       

 09-03-2021
1.25
worked on fit of oil cooler and hose plaecment
Details

 09-02-2021
2.75
finish cowl heat shield foil, install oil hose
Details

 09-01-2021
1.50
attach two oil hoses finger tight
Details

 08-31-2021
1.50

Details
     

 08-30-2021
3.00
cut paper templates for foil cowl heat shield
Details

 08-29-2021
2.00
install EGT sensors
Details
       

 08-27-2021
2.75
torque exhaust tubes, RTV on retention springs
Details
       

 08-26-2021
2.25
partial install of muffler
Details
       

 08-25-2021
1.60
applied duct seals, install exhaust pipes
Details
       

 08-24-2021
1.50
cut cooling air duct seals
Details

 08-23-2021
1.00
sand repair some items on cowls
Details

 08-20-2021
2.25
fill gaps in cowl air duct, affix label on duct
Details

 08-19-2021
3.00
epoxy the colling duct and interface
Details
       

 08-18-2021
2.00
more sanding and fitting duct
Details

 08-16-2021
3.00
sand and fit the cooling duct for radiator clearan
Details
     

 08-15-2021
1.00
trim aft edge of cooling duct
Details

 08-14-2021
4.50
trim cooling for fit, test cleco, ready to trim
Details
       

 08-12-2021
1.50
drill oil cooler assy. mount holes in duct, rivet
Details
       

 08-11-2021
3.00
finish fabficating oil cooling box with radiator
Details
       

 08-10-2021
1.50
prepare and rivet top plate on cooling box
Details

 08-08-2021
1.25
fab wood plates, deburr cooling box parts
Details

 08-07-2021
1.00
mark scribe lines on cooling duct
Details

 08-06-2021
4.25
install heater cable onto heater door
Details
       

 08-05-2021
7.00
debur friction comb, apply wrap to instrument pane
Details
     

 08-04-2021
3.00
secure coolant hose to front gear leg
Details
       

 08-03-2021
5.25
sand cowling, install radiator and hoses
Details
       

 08-02-2021
3.80
epoxy scoop onto cowl, RTV cooling door
Details
       

 07-28-2021
2.65
work on top cowl scoop
Details
       

 07-27-2021
1.25
work on NACA template
Details

 07-26-2021
3.00
finish up bottom cowl close out and cut holes
Details
       

 07-22-2021
1.50
work on bottom cowl close out
Details
     

 07-21-2021
1.60
more work on oil door
Details
     

 07-20-2021
3.50
top cowling oil door work
Details
       

 07-09-2021
3.25
rivet front cowl rivuts, assemble oil door
Details

 07-08-2021
1.75
drill forward colwing holes to #19, rivet 2 knuckl
Details
       

 07-07-2021
3.00
finish riveting cowls
Details
       

 07-05-2021
2.25
more riveting
Details
       

 07-02-2021
4.00
rivet hinges onto the cowlings
Details
     

 07-01-2021
1.50
fabricate oil door and hinge pieces
Details

 06-27-2021
2.80
drill remaining cowling hinge holes
Details

 06-24-2021
3.50
sanded top and bottom cowls for better fit, drille
Details
       

 06-23-2021
7.50
attach mid cowl hinges, trim pins, sand to fit
Details

 06-22-2021
2.50
flute cowling hinges to match curves
Details

 06-19-2021
2.00
remarked hinges and reinstalled on fuselage
Details
       

 06-18-2021
4.25
fabricate and mark other cowling hinges
Details

 06-17-2021
1.25
layout holes on hinge pieces
Details
     

 06-16-2021
2.00
cut bend and grind hinge pins, re-install panel
Details

 06-15-2021
1.50
cut cowling hinges
Details

 06-11-2021
4.85
finish sanding bottom cowling, cut slot
Details
     

 06-10-2021
1.25
finish sanding top cowling
Details
     

 06-09-2021
4.00
work on cowling
Details

 06-08-2021
1.50
worked on getting ready for cowling work
Details

 06-07-2021
1.25
connect wires to voltage reg., order 3M Wrap
Details
       

 06-04-2021
1.50
reroute WH-P156 & WH-P761, safety wire plugs
Details
       

 06-02-2021
2.50
fabricate and install fuel drain hose and tube
Details
       

 06-01-2021
1.50
connect starter wires, connect man. press. hose
Details
       

 05-29-2021
5.25
connect sensors to the engine
Details
       

 05-27-2021
2.50
torqued engine bracket bolts,
Details

 05-25-2021
2.50
replace engine mount bracket per SB00023
Details

 04-29-2021
4.00
torqued engine bolts, fuel line install, ignition
Details
       

 04-27-2021
2.00
deburr holes, mount the engine
Details
       

 04-22-2021
0.75
made an extended tool for the deburr bit
Details
       

 04-21-2021
0.10
vans correspondence
Details

 04-06-2021
1.25
shorten the avionics dimmer pot shaft
Details

 03-29-2021
1.75
connect oil tank vent, cooling overflow bottle
Details
       

 03-25-2021
0.75
install oil tank assembly
Details
     

 03-24-2021
1.00
cut hoses for oil tank vent and coolant overflow
Details

 03-09-2021
2.75
drilled larger two engine mount holes
Details
     

 03-08-2021
1.50
redo placement of fuel line banjo bolts
Details
       

 03-07-2021
1.00
cut and mount carb drip tray dampeners
Details
       

 03-06-2021
1.00
final torqued the upper left engine mount
Details

 02-27-2021
0.50
finish riveting the cooling box
Details
       

 02-26-2021
1.50
Make new cooling box hinge, match drill, rivet
Details
       

 02-22-2021
0.75
drill #30 holes in cooling box hinge
Details

 02-18-2021
1.50
rivet colling box hinge and bracket to door
Details
     

 02-15-2021
1.00
countersink the hinge holes
Details

 02-11-2021
1.50
colling box parts
Details
       

 02-10-2021
1.25
Cooling hoses
Details

 01-29-2021
1.00
install ignition screw, modify 8mm hex wrench
Details
       

 01-20-2021
0.75
packed exhaust pieces to send to Vans
Details
     

 01-13-2021
2.25
install carb drip trays
Details
       

 12-29-2020
0.75
install regulator monitor wire
Details
       

 12-20-2020
1.00
work on voltage regulator mounting
Details
     

 12-15-2020
1.25
seal corners of carb drip trays
Details
     

 12-12-2020
1.50
work on voltage regulator mounting
Details

 12-11-2020
1.75
complete drip trays riveting, glue/clamp doubler
Details
     

 12-10-2020
1.75
partial assembly of carburetor drip trays
Details
     

 12-09-2020
1.00
paint tie-down rings, prime rivnuts
Details

 12-05-2020
1.00
cut and deburr carburetor drip pan pieces
Details

 12-02-2020
0.75
start prep of carb drip pan pieces
Details

 11-22-2020
1.75
wire some power wires
Details
       

 11-20-2020
1.25
replace connectors on EGT sensors, prime parts
Details
       

 11-18-2020
2.25
Install firewall forward wiring
Details
       

 11-14-2020
2.00
torque engine mount, install master relay, wiring
Details
       

 11-11-2020
4.50
INstall engine mount on the engine
Details
       

 11-09-2020
1.75
remove both carbs, cut lug on starter
Details
       

 11-08-2020
2.00
verify ignition coil spacing, start other engine m
Details
       

 11-04-2020
1.50
disconnect the Rotax ignition connectors, etc.
Details
       

 11-03-2020
2.00
redo safety wire on gascolator,install pitot exten
Details
       

 10-31-2020
3.25
firewall forward wiring
Details
       

 10-27-2020
2.80
Start install of engine wiring
Details
       

 10-24-2020
1.50
Got new prints, gathered engine parts
Details

 10-23-2020
3.00
Review engine drawings, order DynaVibe
Details

 10-22-2020
1.50
Review SD-00001 and engine drawings
Details

 10-16-2020
3.00
Received 912ULS powerplant kit
Details
       

 10-09-2020
1.25
work on redo of gascolator safety wiring
Details

 10-07-2020
1.00
painted both turtle deck skins
Details

 10-06-2020
1.00
Prepped right turtle deck skin and primed both
Details

 10-05-2020
0.50
prep turtle deck skins for painting
Details

 09-30-2020
0.50
paint fuel filler neck
Details

 09-29-2020
0.75
prime fule tank filler neck
Details

 09-13-2020
2.00
build the ELT GPS received test tool
Details
     

 09-11-2020
2.50
Install ELT remote nameplate, wire connector
Details
       

 09-10-2020
1.00
Investigate the ELT wiring
Details

 09-05-2020
2.00
Finish AP cutoff wiring, connect trim tab wiring
Details
       

 09-01-2020
1.50
install remote ELT
Details
       

 08-31-2020
2.50
clean-up the wiring behind the instrument panel
Details
       

 08-30-2020
4.50
misc avionics wiring and install
Details
       

 08-29-2020
3.75
Many items related to the avionics installation
Details
       

 08-28-2020
3.00
wire up the CO monitor wires to EMS connector
Details
     

 08-27-2020
1.00
mount the CO monitor module
Details
     

 08-26-2020
4.00
wire up GPS, install connector on CO monitor
Details
       

 08-25-2020
3.00
review CO monitor installation
Details

 08-24-2020
1.00
Review elec. schematics and connector changes
Details

 08-23-2020
0.25
tighten transponder antenna & connect cable
Details

 08-22-2020
2.75
finish countersink holes in instr. panels, rivnuts
Details

 08-19-2020
2.25
file and fit cutouts for AP Knob Panels
Details
       

 08-18-2020
2.75
cutout the holes for AP Knob Panles
Details
     

 08-17-2020
2.50
prep comm brackets and ADS-b brackets
Details
     

 08-15-2020
2.40
mount ELT antenna bracket, install stack angles
Details
       

 08-13-2020
3.00

Details
     

 08-12-2020
1.50
install xponder mount and xponder, connect ant.
Details
     

 08-11-2020
1.00
rivet rivnuts for starter module, prep xponder mou
Details
     

 08-10-2020
1.75
countersink Skyview panel and rivet doubler
Details

 08-08-2020
1.00
install EMS and Battery modules
Details
     

 08-07-2020
1.50
install ransponder antenna, ELT parts
Details
     

 08-06-2020
4.50
protect ADS-B antenna, deburr parts
Details
       

 08-05-2020
1.75
install ADS-B antenna
Details
       

 08-04-2020
3.50
prime rivnuts, install d-sub ADAHRS, install ADAHR
Details
       

 07-29-2020
1.75
fixed 2 cotter pins, misc. install 2 rear baggage
Details
       

 07-28-2020
1.50
received and inventoried Dynon Avionics
Details

 07-25-2020
1.50
finish installing rivnuts on tailcone for fairing
Details
       

 07-19-2020
7.25
remove stabilator, start installing rivnuts for fa
Details
     

 07-18-2020
5.50
file and sand stab. and fairing, final drill fairi
Details
       

 07-17-2020
2.50
install stabilator, drill remaining fairing holes
Details
       

 07-16-2020
2.75
clamp tailcone fairing, drill inboard holes in tai
Details
     

 07-15-2020
2.30
move stab. to side wall, install vertical stab. to
Details
     

 07-12-2020
1.00
move wings to basement, stabilator to garage
Details

 07-11-2020
1.00
move fuselage in the garage
Details

 07-08-2020
4.00
Rivet rivnuts to nose wheel fairing brkt, install
Details
       

 07-07-2020
2.50
Attach fairing brackets on nose fork
Details

 07-01-2020
1.75
installed wire connectors, ran control cables
Details
       

 06-30-2020
2.50
clean wiring, routed wiring in tailcone
Details
       

 06-29-2020
1.00
clean-up wire/tube bundles under 7 thru panel base
Details
       

 06-28-2020
1.00
finish routing the pitch trim/pitot tube thru pane
Details

 06-27-2020
3.00
Clean-up & run wiring and tube
Details

 06-26-2020
4.50
wiretie and RTV filter near fuel pump
Details
     

 06-23-2020
0.50

Details

 06-22-2020
4.00
run pitch trim cable & aft pitot tube further
Details

 06-21-2020
2.30
Run pitch trim cable & pitot tube through fuselage
Details

 06-20-2020
1.50
remove blue plastic from inside of turtle deck pie
Details
     

 06-19-2020
4.00
rivet the tailcone onto the fuselage
Details
       

 06-18-2020
3.00
wire tie fuel air vent, rivet shoulder harness lug
Details
       

 06-17-2020
3.00
drill and attach fuel line vent tubes
Details
     

 06-16-2020
2.75
bend tailcone tabs, cleco tailcone bottom
Details
       

 06-15-2020
2.50
install pitch servo, drill hole for AP stop switch
Details
       

 06-14-2020
0.30
attach pitch pushrod to servo
Details

 06-13-2020
3.25
Install roll servo
Details
       

 06-11-2020
2.00
make autopilot servo push rods
Details
     

 06-10-2020
2.50
countersink bottom fairing, rivet clamps
Details
       

 06-09-2020
0.75
sand empanage fairings to final fit
Details

 06-08-2020
2.00
countersink bottom fairing and rivet nut plates
Details
     

 06-07-2020
2.75
tempoary attachment and drill for fairing clamps
Details
       

 06-06-2020
3.00
finish sanding fairings, apply masking tape templa
Details
       

 06-05-2020
2.75
trim bottom and top tailcone fairings
Details
       

 06-04-2020
2.50
marked 3/4" masking tape for tailcone, fairings
Details
       

 06-03-2020
1.50
connect aft stabilator control cables
Details

 06-02-2020
3.00
deburr parts, review KAI
Details

 06-01-2020
1.50
remove fuel tank, review manual prints
Details

 05-31-2020
0.50
ordered Dynon Autopilot servos
Details

 05-29-2020
1.00
finish fuel vent line from tank
Details
       

 05-28-2020
3.25
rivet nut plates, check tank for leaks and sensor
Details
       

 05-27-2020
2.75
bend the fuel filler flange and drill for mounting
Details
     

 05-26-2020
2.50
review items, mount fuel tank - connect filler nec
Details
     

 05-25-2020
2.00
assemble the torque tubes
Details
       

 05-22-2020
2.50
drilled the remaining holes in the torque tubes
Details

 05-21-2020
2.00
mounted the wings, drilled the torque tubes
Details
       

 05-19-2020
2.00
file left wing bottom skin, fix wing fuselage roll
Details

 05-18-2020
1.50
filed bottom skin of right wing
Details

 05-16-2020
1.25
Reviewed Service Bull & Dir. marked file line rt w
Details

 05-15-2020
2.00
first wing test mount
Details
       

 05-14-2020
1.00
Review manual pages, attach 0.125 spacers
Details

 05-13-2020
1.50
canopy latch handle rotation tightening
Details
       

 05-09-2020
1.00
investigate cable attach process for rudder & stab
Details

 05-08-2020
1.75
filed parts for better wing fit, reverse connector
Details

 05-07-2020
1.75
figured out problem with wing connector
Details

 04-30-2020
2.00
test mount left wing onto fuselage
Details
       

 04-29-2020
1.50
re-hang stab. in basement, get ready for wing mtg.
Details

 04-26-2020
1.00
move wings from basement to garage
Details

 04-25-2020
1.40
attach stabilator trims
Details
       

 04-24-2020
1.00
make stabilator hinge wires
Details

 04-22-2020
2.75
assemble stab. trim pushrod assembly
Details
       

 04-21-2020
2.00
install connector on stab trim servo tray
Details
     

 04-19-2020
1.00
finish bushing on servo trim tray
Details

 04-18-2020
1.50
add bushings to servo tray and link
Details

 04-17-2020
2.00
prep parts for horiz. stab. trim control and servo
Details
       

 04-15-2020
1.75
separate and deburr F-1294C
Details

 04-14-2020
1.50
vert. stab. fiberglass tip trim to match rudder ti
Details
     

 04-13-2020
2.50
vertical stab. fiberglass tip preparation
Details

 04-12-2020
2.00
rudder fiberglass tip trim, drill, sand
Details
     

 04-11-2020
0.75
work on rudder fiberglass tip
Details

 04-10-2020
1.25
investigate brake line bleed process, etc.
Details

 04-09-2020
1.75
make 0.125" spacers for wing install
Details

 04-06-2020
1.25
assemble rudder rigging stop, other
Details
     

 04-03-2020
1.56
fabricate one fuel vent tube and start on other
Details
       

 04-02-2020
2.50
Assemble tow bar, work on fuel vent line items
Details
       

 04-01-2020
1.00
Check fuel tank vent instructions, debur part
Details

 03-31-2020
2.00
Fabricate temporary spacers and F-1258 parts
Details
       

 03-28-2020
1.00
re-insertion and gluing of stabilator bearings
Details

 03-27-2020
2.50
Remove the stabilator bearings per SB 16-08-01
Details

 03-26-2020
2.75
Install ADAHRS stiffener to tail cone
Details
       

 03-25-2020
1.00
Finish fabrication of winterization kit parts
Details
       

 03-24-2020
1.00
Finish fabrication of winterization kit, plus more
Details
     

 03-24-2020
0.50
Cut and install flaperon torque tube grommets
Details
     

 03-22-2020
1.00
start fabrication of winterization kit
Details

 03-21-2020
1.25
test pivot guides fit of flaperon torque tubes
Details

 03-11-2020
0.50
rough cut the wood for the rudder rigging
Details

 03-09-2020
0.75
Install rudder trim tab
Details
     

 03-05-2020
1.00
Inspect fuel tank
Details
       

 03-04-2020
1.50
Finish connection of AOA tube on fuselage
Details

 03-03-2020
1.75
Routed AOA tube through the fuselage
Details

 03-02-2020
0.50
Start rudder trim tab install by deburr tab
Details

 03-01-2020
0.50
start routing AOA tube in the fuselage
Details

 02-27-2020
1.25
Complete vent handle install
Details

 02-19-2020
2.00
Verify all Service Bulletins, ordered nose fork pa
Details

 02-18-2020
0.50
start install of fresh air vent handles
Details

 12-29-2019
2.50
finish SB 18-02-02, not installed on tale yet
Details
       

 12-28-2019
1.50
finish step 26, top only step 27
Details

 12-27-2019
1.20
partial step 26
Details

 12-22-2019
1.30
steps 22 - 25 top and bottom
Details
       

 12-21-2019
0.95
partial step 20, 21 and 22
Details

 12-20-2019
0.40
finish step 19
Details

 12-19-2019
1.00
partial step 19
Details
     

 12-18-2019
2.00
remove stabilator hinges and add doubler
Details
       

 12-17-2019
1.25
finish mods to WD-1208
Details
       

 12-16-2019
1.50
finish modification of WD-1207
Details
       

 12-11-2019
1.25
match drill #30 holes for HS-01232 doubler
Details
     

 12-05-2019
0.25
verify alum. tube fis properly in fitting
Details

 12-03-2019
1.75
modify fuselage AOA fittings and attach
Details
       

 12-02-2019
1.00
take down stabilator, update build log
Details

 12-01-2019
1.25
attach flaperon on left wing
Details
       

 11-30-2019
2.00
finish AOA in left wing, other mods
Details
     

 11-29-2019
1.25
install tube in fitting and install fitting
Details
       

 11-27-2019
1.75
run AOA tubing, make fitting, RTV
Details
     

 11-26-2019
2.10
Notification 16-12-14 steps 6,7,11
Details
     

 11-25-2019
0.75
Epoxy AOA rivet into left wing
Details
     

 11-23-2019
2.00
Install rivet for AOA in left wing
Details

 11-22-2019
0.40
look at AOA install plans
Details

 11-21-2019
2.75
installed wing doubler per SB 14-11-03
Details
     

 11-20-2019
0.75
moved completed right wing from table to wing slin
Details

 11-19-2019
1.50
Installed flaperon onto the right wing
Details
       

 11-18-2019
1.40
Investigate right wing tip light fit
Details

 11-17-2019
1.75
complete SB 14-11-03 mod on right wing
Details
     

 11-16-2019
4.00
SB 14-11-03 right wing doubler
Details

 11-15-2019
1.00
install steps with plugs
Details

 11-14-2019
1.00
install step plugs per Notification 19-10-16
Details
       

 11-13-2019
2.40
deburr all parts needed
Details

 11-12-2019
1.50
further check of interior plus download manuals
Details

 11-08-2019
1.90
fuel tank and interior investigation
Details

 11-07-2019
0.50
check pre-built fuel tank and note on 37B
Details

 11-06-2019
1.15
check vert stab, rudder and trim tabs
Details

 11-05-2019
1.00
further review of manual
Details

 11-03-2019
1.75
review what is left in the manual so far
Details

 10-29-2019
2.00
finish SB 18-02-03
Details
       

 10-27-2019
2.00
start SB 18-02-03 on Anti-servo tabs
Details

 10-24-2019
0.25
inspect canopy pivots
Details

 10-23-2019
1.50
add epoxy/flox to space fiberglass from fuselage
Details
       

 10-22-2019
1.00
file shop head on wing rivets
Details
     

 10-17-2019
0.75
update KitLog
Details

 10-16-2019
1.50
install LED shop lights
Details

 10-15-2019
0.75
Install LED lights
Details

 10-14-2019
0.50
figure out next construction steps
Details

 09-25-2019
0.33
enlarge fiberglass hole at canopy pivot point
Details

 09-23-2019
0.50
verify washer used on canopy hinge point
Details

 09-22-2019
0.75
search prints for a certain washer reference
Details

 09-21-2019
1.75
clean and organize garage shop
Details

 08-28-2019
1.25
remove and trim canopy
Details

 08-09-2019
1.25
canopy trimming and sanding
Details

 08-02-2019
1.75
work on canopy fit
Details

 08-01-2019
1.25
work on canopy
Details

 12-15-2018
1.85
trim and sand fiberglass with multi-tool
Details
       

 12-05-2018
1.50
redrill holes for canopy scews, trim & sand fiberg
Details
       

 11-09-2018
2.25
34-16
Details
     

 11-08-2018
1.50
Sand canopy fairing w/100 & 150 grit
Details

 11-05-2018
1.25
Sand and apply epoxy only
Details

 11-02-2018
1.00
sand with 100 and 150 grit, apply epoxy w/balloons
Details

 11-01-2018
2.50
sand fairing, apply epoxy
Details
       

 10-31-2018
1.00
sanding canopy fiberglass fairing
Details

 10-29-2018
0.75
sand and add more expoxy/microbead layer
Details

 10-26-2018
1.50
remove middle pealply, sand and fill gaps
Details
       

 10-23-2018
2.50
epoxy middle 10 plies and pealply
Details
       

 10-22-2018
1.50
remove pealply from right, cut middle plies
Details

 10-19-2018
2.25
fiberglass right side of canopy
Details
       

 10-18-2018
3.00
wax left side and apply fiberglass to left side
Details
       

 10-17-2018
1.50
sanded canopy and metal parts for glass bonding
Details

 10-16-2018
3.50
cut left and right fiberglass plies 1 - 5
Details

 10-10-2018
4.00
finish sanding foam, apply electrical tape to cano
Details
       

 10-06-2018
0.75
More sanding shaping of the foam
Details

 10-05-2018
1.00
epoxy left side foam, start shaping foam
Details

 10-04-2018
1.50
Scuff and epoxy right side only canopy foam
Details

 09-24-2018
1.75
Cut canopy foam and final paint steps
Details
     

 09-22-2018
0.25
Final coat of paint on steps
Details

 09-21-2018
2.50
Sand, prime paint steps; finish masking
Details
       

 09-17-2018
1.25
Mask instrument panel
Details

 05-21-2018
3.00
Finish wing stands
Details
       

 03-14-2018
3.25
install cockpit light, install POH tray
Details
       

 03-13-2018
1.50
Install noise cancelling capacitor
Details

 03-09-2018
1.50
rivet left side F-1237-L
Details
     

 03-08-2018
3.75
deburr parts and rivet cover plates
Details
     

 03-07-2018
0.75
secure poly brake lines with tie wraps
Details

 03-04-2018
1.25
Install left main alum brake line, add tie wrap
Details
       

 03-02-2018
2.00
connect brake lines
Details
     

 02-28-2018
0.25
install nose wheel turn stop screw
Details

 02-22-2018
1.25
Install nose wheel
Details
       

 02-21-2018
3.50
nose gear mount, install rivnuts, nose fork
Details

 02-16-2018
2.00
modify nose wheel fork
Details

 02-07-2018
2.50
Bolt on mains axles, attached wheels
Details
       

 01-31-2018
1.33
mount main axles, check allignment
Details
     

 01-30-2018
3.50
Torque all gear leg attach bolts
Details

 01-22-2018
2.00
install left and right gear legs, install inbd. pl
Details

 01-19-2018
2.25
install outboard gear leg doubler and wear plates
Details

 01-13-2018
0.75
grease main wheel bearings, grease steel parts
Details

 01-12-2018
1.25
Debur and prime gear plates
Details
     

 01-11-2018
2.00
Finish second main tire and assemble brake conn.
Details
       

 01-10-2018
2.80
Install engine mount, start on wheels and tires
Details
       

 01-09-2018
1.67
Start install of upper engine mount
Details

 12-12-2017
2.00
Finish build of saw horses
Details
     

 12-09-2017
2.00
Continue build of saw horses
Details

 12-06-2017
2.00
Start build on saw horses to hold fuselage
Details

 11-29-2017
1.75
Install canopy catch option
Details
     

 11-28-2017
2.67
Fabricate and install canopy guide blocks
Details
       

 11-25-2017
4.25
add canopy latch safety switch
Details
     

 11-20-2017
1.25
Install canopy latch and latch block
Details
     

 11-17-2017
2.50
rivet canopy skitrts to frame and bolt and rivet
Details
       

 11-16-2017
1.20
Screw canopy to rear bow of frame
Details

 11-15-2017
1.00
put canopy on frame, clecoed front bow
Details

 11-04-2017
1.00
2nd coat paint and paint canopy skirts
Details

 11-03-2017
1.00
paint the canopy frame
Details
     

 11-02-2017
1.75
Prep and prime canopy frame
Details

 10-26-2017
1.50
fabricate two canopy lift handles
Details

 10-19-2017
1.40
Canopy guide plates and guide blocks
Details
       

 10-18-2017
0.50
Round edges on canopy latch handle
Details
       

 10-17-2017
3.17
Final drill canopy, countersink, start latch handl
Details

 10-14-2017
1.25
match drill skirt holes to canopy and frame angles
Details
       

 10-12-2017
4.85
match drill canopy skirts, dimple and bend skirts
Details

 10-10-2017
1.00
remove canopy and prep for fit
Details

 09-29-2017
1.50
finish drill and cleco canopy front and aft
Details
       

 09-28-2017
3.25
file weld fillet on frame for fit, sand canopy for
Details
       

 09-25-2017
2.00
prep canopy, place on frame
Details
     

 09-23-2017
1.00
prep plastic caps for clecos
Details
     

 09-15-2017
1.00
put cover back on instrument panel, got out canopy
Details
       

 09-11-2017
0.50
apply Boelube and install instrument cover
Details

 09-07-2017
0.50
apply Permatex bead on instrument panel doubler
Details

 09-06-2017
0.75
remove instrument panel cover
Details

 09-02-2017
1.50
Complete right side canopy attach angles
Details
       

 08-29-2017
1.00
Flute and match drill left side canopy attach angl
Details
       

 08-29-2017
2.25
Attach canopy frame
Details
       

 08-26-2017
0.25
Finish right side canopy attach angles
Details

 08-25-2017
1.75
finish deburr of canopy frame, drill C-1203A and B
Details

 08-24-2017
1.25
attach canopy latch handle stop to canopy frame
Details

 08-23-2017
2.00
canopy frame prep
Details

 08-22-2017
2.00
prep canopy gas strut
Details

 08-17-2017
1.25
deburr and attach rear baggage floor piece
Details
     

 08-16-2017
1.50
assemble rear bulkhead covers and install
Details
     

 08-15-2017
2.00
work on rear bulkhead cover for behind fuel tank
Details

 08-11-2017
3.25
attach flap handle cover and front tunnel cover
Details
       

 07-07-2017
3.00
Install/route stabilator cables & pulleys
Details
     

 07-04-2017
3.00
Straighten control sticks
Details

 06-29-2017
3.67
finish install of stabilator/rudder cables and sle
Details
     

 06-28-2017
1.50
Install rudder cables and sleeves
Details
       

 06-27-2017
0.50
Epoxy flaperon torque tube spacers
Details
       

 06-22-2017
1.00
Drill flaperon torque tube spacers, grease detent
Details

 06-20-2017
1.50
attach flap detent bracket,rivet flap handle knob
Details
       

 06-15-2017
0.50
attach flap handle knob, shorten flap handle sprin
Details

 06-13-2017
2.75
Fabricate flap handle parts and detent bracket
Details
       

 05-31-2017
5.00
fabricate and attach flaperon pushrods
Details
       

 05-26-2017
1.75
Attach control stick push rods, wire connector
Details
       

 05-24-2017
0.50
Tried to attach push rods
Details

 05-19-2017
3.00
Polish and attach control stick bushings
Details
       

 05-18-2017
1.50
Construct 2 Control Stick Push Rod assemblies
Details

 05-17-2017
1.50
Assemble flaperon mixer arms
Details
       

 05-16-2017
1.67
mount flap handle and blocks
Details
       

 05-16-2017
1.25
finish wiring system mount blocks
Details
       

 05-12-2017
1.50
fabricate flap handle blocks
Details
     

 05-11-2017
1.75
deburr parts, mount bearings, assemble flap pushro
Details
       

 05-06-2017
1.25
install brake reservoir
Details
       

 05-05-2017
2.25
Complete SB 16-08-24 replace engine mount rivets
Details
       

 04-28-2017
1.50
install roll bar wiring for cockpit light and latc
Details
       

 04-22-2017
1.00
wire-tie wires to rudder mount wire bracket
Details

 04-19-2017
0.75
install over rudder wireway bracket
Details

 02-17-2017
2.00
Redo wiring at rudder pedal assembly
Details

 01-26-2017
4.00
redo table legs for sturdiness
Details

 01-25-2017
2.75
Assemble parts for 31B-25 and move wires
Details

 01-21-2017
3.50
install fuel pump elec. filter and wing fuse conne
Details
       

 01-16-2017
2.00
continued wiring
Details

 01-07-2017
1.25
deburr and prep parts related to wiring
Details

 12-29-2016
2.00
wire wing connectors and pitch servo connector
Details
       

 12-29-2016
0.50
fabricate wing connector extract tool
Details
       

 11-30-2016
2.00
complete wiring and install of comm. connectors
Details
       

 11-19-2016
1.25
Install power port and start on comm. ports
Details

 10-09-2016
0.25
route wires along phone cable for ELT
Details

 10-05-2016
0.50
finish difficult grommet routing
Details

 09-28-2016
2.67
more routing details of WH-00045
Details
       

 09-26-2016
2.50
Install OAT, start routing of optional cable harne
Details
       

 09-20-2016
1.75
push to talk wiring routing
Details

 09-17-2016
1.75
modify for proper mount & temp install of control
Details
       

 09-16-2016
2.00
install control stick grips and wiring
Details
     

 09-15-2016
3.00
complete more wiring for fuel pump, GPS, latch sw.
Details
       

 09-14-2016
1.25
finish spar pin switch wiring and switch install
Details
       

 09-11-2016
1.00
continue spar pin switch wiring
Details

 09-09-2016
1.17
start spar pin switch wiring
Details

 09-07-2016
1.75
install audio jack, wing conn., autopilot conn.
Details
       

 09-07-2016
0.50
finish painting around power and audio connectors
Details
       

 09-06-2016
2.00
route cable harness wires
Details
       

 09-04-2016
0.25
Install left instrument cooling fan
Details

 09-02-2016
1.50
Instrument cooling fans insall
Details

 09-01-2016
1.50
finish cables install
Details
       

 08-31-2016
1.00
install conduit, start cabling
Details

 08-24-2016
1.33
prep plastic conduit
Details

 08-22-2016
1.50
install grommet and clamp
Details
       

 08-01-2016
1.20
RV-12 transition training
Details

 07-06-2016
1.75
Assemble wing fuselage pins
Details
       

 06-30-2016
0.75
Install screwws in back of map box
Details
       

 06-29-2016
2.00
assemble map box and rivet to right side panel
Details
     

 06-28-2016
0.75
prime and paint map box halves, prime nut plates
Details
     

 06-25-2016
0.25
rivet nutplates to ctr panel, install center panel
Details
       

 06-23-2016
1.50
work on map box door, deburr center panel
Details
     

 06-22-2016
3.25
work on map box and door, left generic panel
Details
     

 06-21-2016
2.75
finish forward fuselage skin, start map box
Details
       

 06-20-2016
0.50
Attach fwd fuse skin dimple nut plates and bracket
Details

 06-16-2016
2.42
prep, drill dimple, and deburr Upper Fwd Fuse skin
Details
       

 06-01-2016
0.50
Assemble cover plate and clip
Details
       

 05-25-2016
3.92
Deburr parts and assembly
Details
       

 05-24-2016
4.92
panel base and canopy ribs attachment
Details
       

 05-20-2016
1.25
cleco and match drill Panel Base to longerons
Details

 05-19-2016
2.00
deburr F-1202B Panel Base, install nut plates
Details

 05-16-2016
0.45
Finish right canopy rib assembly
Details

 04-20-2016
2.75
Finish deburr, finish canopy rib L
Details
     

 04-19-2016
0.33
more deburr
Details

 04-14-2016
1.25
Prep F-1202H-L&R, deburr edges F-1202A-L&R
Details

 04-06-2016
2.50
attach mid-cowl hinges & attach stiffeners
Details
       

 04-04-2016
4.25
finish cowl hinges, complete antenna shelf
Details
       

 04-01-2016
1.83
start to attach cowl hinges
Details

 03-31-2016
3.00
install firewall spacers, install upper fuse Doubl
Details
       

 03-30-2016
2.33
fabricate cowl hinges, and stiffeners
Details

 03-29-2016
0.25
Fabricate hinges
Details

 03-28-2016
2.25
Fabricate and install forward fuel return line
Details
       

 03-26-2016
2.00
construct and install rear return fuel line
Details

 03-25-2016
3.00
Redo 3/8" fuel feed lines
Details
       

 03-11-2016
3.00
Testing flares on 3/8 fuel lines, get new tools
Details

 03-04-2016
1.75
safety wire and install gascolator
Details
       

 02-25-2016
0.83
install fuel sensor
Details
     

 02-08-2016
3.00
Complete the Finish Kit inventory
       

 02-05-2016
2.50
Finish small hardware inventory
Details

 02-03-2016
2.00
continue inventory of small hardware
Details

 02-02-2016
2.00
inventory small hardware
Details

 01-27-2016
1.00
Inspect finish kit received 1/22/16
Details
       

 01-22-2016
0.75
Receive Finish Kit
Details
       

 01-20-2016
2.50
fabricate and install pump to valve fuel line
Details
       

 01-16-2016
1.75
fabricate and install first fuel line
Details
       

 01-15-2016
2.33
mount fuel pump and fuel shut off valve
Details
       

 01-13-2016
1.55
put fuse on side, run remaining brake lines
Details
       

 01-09-2016
0.50
cut brake lines
Details

 01-07-2016
2.50
install brake line fittings and crossover lines
Details
       

 12-29-2015
2.00
mount rudder/brake pedal assembly to fuselage
Details
       

 12-28-2015
4.40
assemble brake pedals and brake cylinders
Details
       

 12-22-2015
1.75
start on rudder pedal assembly
Details
       

 12-04-2015
4.40
finish seat backs and install in fuselage
Details
       

 12-02-2015
1.75
fabricate seat back hinges
Details

 11-30-2015
2.00
prep seat back parts
Details

 11-13-2015
0.75
install attach angle in baggage area rear bulkhead
Details
     

 11-12-2015
3.50
install rear bulkhead, brace
Details
       

 11-11-2015
1.00
Install rollover assembly
Details
       

 11-10-2015
0.50
move fuselage from basement to garage
Details
       

 11-09-2015
1.50
prep garage for fuse, match drill tailcone Shear C
Details

 11-06-2015
3.00
deburr parts
Details

 09-17-2015
1.50
match drill and prime rollover arch bases
Details
     

 09-16-2015
1.70
rivet the rollover arch assembly
Details
       

 09-15-2015
1.75
prime rollover arches, deburr other parts
Details
     

 09-14-2015
0.75
finish rollover arch latch parts
Details

 09-12-2015
1.75
finish match drilling, deburr all holes
Details

 09-11-2015
2.00
cleco parts for rollover arch, start final drillin
Details
     

 09-10-2015
1.00
deburr edges of rollover assembly parts
Details

 09-09-2015
0.75
sort out rollover assembly parts, breakdown crate
Details

 09-09-2015
0.75
redo left cowl hinge
Details

 09-08-2015
1.50
fabricate and install cowl hinges
Details
       

 09-07-2015
2.75
assemble and install vent door assemblies
Details
       

 09-06-2015
0.83
start side vent assemblies
Details

 09-06-2015
1.67
left side skin riveted, two stiffeners riveted
Details
       

 09-05-2015
3.75
rivet right side skin
Details
       

 09-04-2015
1.75
deburr left side skin, dimple and nut plates
Details
       

 09-03-2015
1.75
countersink canopy decks, deburr right side skin
Details

 09-02-2015
1.75
finish prep of left skin, prime longerons
Details
       

 09-01-2015
1.83
deburr left longeron and other left skins
Details

 08-31-2015
1.67
deburr right longeron and other right side skins
Details

 08-26-2015
2.20
transition flight training
Details

 08-25-2015
0.90
transition flight training
Details

 08-21-2015
2.67
finish cleco side skins, match drill longerons
Details
       

 08-20-2015
2.10
finish wing spar cut outs on side skins, & gusset
Details
       

 08-17-2015
0.75
cleco longeron assembly and start side skins
Details
       

 08-16-2015
2.75
complete arm rest and side channel pieces
Details
       

 08-15-2015
2.00
finish roll bar attach plate, start arm rest side
Details
       

 08-14-2015
2.50
deburr longerons, complete roll bar attach plates
Details

 08-11-2015
3.25
Bend and drill longerons
Details
       

 08-10-2015
0.75
finish flatten area and bend left longeron
Details

 08-06-2015
1.50
Flattened forward end of longerons
Details
       

 08-05-2015
0.75
worked to flat forward end of longerons
Details

 08-04-2015
1.67
Cut and marked longerons, deburr templates
Details

 07-27-2015
1.00
sort out section 23 parts
Details

 07-08-2015
2.25
cleco and rivet fwd lower fuselage to mid fuselage
Details
       

 07-07-2015
1.00
prime and rivet gascolator and rivet fuel flow bra
Details
       

 07-06-2015
1.00
install FF-1204D firewall stiffener and fab F-1201
Details

 07-05-2015
2.20
Install firewall shelf
Details
       

 07-02-2015
1.60
rivet cowl attach plates, drill gascolator hole
Details
       

 07-01-2015
1.10
fab firewall spacers and drill in cowl attach plat
Details

 06-30-2015
4.60
rivet nut plates and forward fuselage pieces
Details
       

 06-29-2015
1.20
deburr F-1272, F-1217A-L&R, F-1271-L&R
Details

 06-26-2015
2.00
deburr F-1288 and prep many others
Details

 06-25-2015
3.33
install baggage bulkhead and autopilot brackets
Details
       

 06-25-2015
1.00
install autopilot brackets
Details
     

 06-23-2015
1.42
install step floors
Details
       

 06-22-2015
1.00
install steps, add nut plates and install snap bus
Details
       

 06-21-2015
0.67
rivet nut plate and step attach brackets to fusela
Details

 06-20-2015
3.00
match drill steps and brackets and begin riveting
Details
       

 06-19-2015
1.75
fabricate step attach brackets & nut plate bracket
Details

 06-18-2015
2.00
rivet the fuselage bottom skin
Details
       

 06-17-2015
4.10
finish prep and deburr F-1276, rivet nut plates, c
Details
     

 06-16-2015
1.00
use soldering pencil to prep bottom skin coating
Details

 06-15-2015
1.50
prep and deburr F-1204Z & F-1268A to E
Details

 06-12-2015
3.91
prep, deburr and rivet L & R corner skins
Details
       

 06-11-2015
2.50
secure control column, install floor ribs
Details
       

 06-08-2015
158.00
nut plates to seat floors, control column partial
Details

 06-05-2015
2.00
bulkhead to seat floor assy, rivet seat floor ramp
Details
       

 06-04-2015
3.67
bulkhead assembly completion
Details
       

 06-03-2015
1.92
prep and rivet stub spar receptacle, doublers
Details
       

 06-02-2015
3.75
prep bulkhead, prep other parts
Details
       

 06-01-2015
1.75
rivet control column mount assembly
Details
     

 05-30-2015
1.83
Install left and right forward bulkhead side assys
Details
       

 05-30-2015
1.25
deburr brackets and parts
Details

 05-29-2015
2.25
finalize seat floor assemblies
Details
       

 05-27-2015
3.93
finish left seat floor assembly
Details
     

 05-26-2015
2.25
assemble seat ribs, prep seat hinges
Details
       

 05-24-2015
2.25
find more parts in crate, prep parts
Details

 05-22-2015
2.00
autopilot servo brackets install, seat ribs assy
Details
       

 05-20-2015
2.17
install pulley bracket assy and mixer to seat ribs
Details
       

 05-19-2015
0.75
rivet nut plates, final drill #19 and dimple seat
Details

 05-18-2015
2.17
finish deburr, continue seat rib assemblies
Details

 05-15-2015
2.00
start prep and deburr of seat ribs
Details

 05-13-2015
1.75
cotter pin install, prep seat belt attach pieces
Details
       

 05-12-2015
0.75
assemble flaperon mixer assembly
Details

 05-11-2015
0.25
install LP4-5 rivets per Vans
Details
       

 05-11-2015
1.75
assemble pulley brackets onto intercostal
Details
       

 05-09-2015
3.25
rivet ribs, nutplates and SB 12-14-06
Details
       

 05-06-2015
1.75
rivet bulkhead to baggage ribs
Details

 05-05-2015
2.00
dimple and rivet nut plates plus bearing bracket
Details
     

 05-01-2015
2.25
prepare and install rear spar wing supports
Details
       

 04-29-2015
1.00
dimple and install nut plates
Details
     

 04-28-2015
2.50
dimple and rivet baggage ribs
Details
       

 04-22-2015
1.20
install fuselage baggage floor
Details
     

 04-21-2015
3.00
redo rivet, prep fuselage baggage floor
Details

 04-20-2015
1.25
prep rear fuselage ribs
Details

 04-16-2015
0.75
redo 2 Cherry rivets
Details

 04-14-2015
2.08
finish fuselage center section
Details
       

 04-11-2015
4.50
finish match drill, countersink center fuse assy.
Details
     

 04-04-2015
1.50
match drill half of holes in center section assemb
Details
     

 04-03-2015
4.00
work on fuselage center section assembly
Details
     

 04-01-2015
1.25
prime nut plates
Details
     

 03-31-2015
1.50
organize fuselage hardware

 03-25-2015
3.00
organize fuselage hardware

 03-21-2015
1.00
organize fuselage hardware

 03-16-2015
0.50
hang flaperons for storage
Details
     

 03-14-2015
2.00
complete right flaperon
Details
     

 03-13-2015
4.25
finish left flaperon, work on right
Details
       

 03-12-2015
2.33
finish left flaperon skeleton, start skin riveting
Details
       

 03-11-2015
2.25
deburr all edges on flaperon skins, mount brackets
Details

 03-10-2015
1.33
deburr all holes on flaperon skins
Details

 03-05-2015
2.00
remove plastic from flaperon skins
Details

 03-03-2015
2.50
deburr all ribs
Details

 02-26-2015
1.50
flaperon rib and hinge bracket prep
Details

 02-25-2015
2.50
manual 18-03 steps 4 - 6
Details

 02-21-2015
4.83
manual 18-03 steps 1 - 4, 18-04 step 1
Details
       

 02-20-2015
1.75
manual 18-02 steps 1 - 3
Details

 02-18-2015
0.33
work on right wing tip light mount
Details

 02-18-2015
1.25
put up straps to hang right wing
Details
       

 01-25-2015
2.00
inventory fuselage hardware
Details

 01-22-2015
2.00
inventory fuselage
Details
       

 01-21-2015
2.00
finish right wing tip light, test, right wing fini
Details
       

 01-20-2015
2.25
Further work on right wing tip light
Details

 01-15-2015
2.00
prepare right wing tip light fiberglass mount
Details
       

 01-14-2015
2.30
finish right wing, start wing tip light
Details
     

 01-13-2015
2.00
deburr W-1204D-R and begin fit
Details

 01-09-2015
1.75
rivet skins and deburr right wing tip pieces
Details
       

 01-07-2015
1.00
deburr W-1204B and W-1204A-R
Details

 12-29-2014
0.10
received fuselage kit
Details

 12-16-2014
3.00
rivet right wing top skins, add wing hold & rib
Details
       

 12-15-2014
1.67
deburr W-1201C-R, cleco
Details

 12-12-2014
2.00
Complete right wing top skins, ready for doubler
Details
     

 12-11-2014
2.33
finish right wing top inboard and outboard skins
Details

 12-10-2014
1.50
deburr upper right wing inboard skin, cleco
Details

 12-06-2014
2.00
prep right wing top skins
Details

 12-05-2014
1.00
install two flaperon hinges on right wing
Details

 12-04-2014
3.75
finish landing light lens and mounting light assem
Details
       

 11-30-2014
3.50
mark ldg. light lens,wiring connectors
Details

 11-21-2014
4.33
deburr W-1202-L, cleco, rivet, flip wing, rivet
Details
       

 11-19-2014
2.00
finish landing light mounts
Details
     

 11-17-2014
2.00
rivet right bottom out board wing skin
Details
     

 11-15-2014
4.25
Finish wing tip light and landing light holes
Details
       

 11-14-2014
1.00
pneumatic riveter, cut wing tip light hole
Details

 11-10-2014
1.67
deburr W-1203-R and prep W-1204D
Details
       

 11-08-2014
1.95
prep the bottom rt wing skins W-1202, W-1203
Details

 11-07-2014
1.75
rivet W-1201-R bottom inboard wing skin
Details

 11-05-2014
2.75
deburr and cleco right wing skin W-1201-R
Details

 10-31-2014
1.75
right wing skin prep
Details

 10-29-2014
1.00
Prep right wing skins
Details

 10-28-2014
1.00
moved right wing skeleton to basement
Details

 10-25-2014
1.00
right wing lighting connector
Details
       

 10-24-2014
1.25
right wing lighting wiring
Details
       

 10-23-2014
3.25
redo rear spar rivets, install front rivets rt win
Details
       

 10-21-2014
0.50
prep and clean partial right wing assy.
Details

 10-20-2014
1.50
prep and move left wing to basement storage
Details
       

 10-09-2014
3.00
Finish left wing tip lighting and test
Details
       

 10-08-2014
2.25
Finish epoxy/flox work and wire connector
Details
       

 10-07-2014
2.00
add epoxy/flox to left wingtip light mount
Details
       

 10-04-2014
1.00
Added rivet and install stall switch access door
Details
     

 10-03-2014
3.00
Prepare left wing tip light fiberglass extension
Details
       

 09-25-2014
1.50
Rivet left wing tip close-out
Details
       

 09-24-2014
3.42
flip wing, fit W12-04D-L, cut light hole
Details
       

 09-23-2014
1.67
deburr parts and investigate wing tip light
Details

 09-22-2014
0.40
Fabricate bending tool
Details

 09-21-2014
2.00
Prep and install top skins left wing tip
Details
       

 09-20-2014
3.20
work on left wing tip
Details

 09-17-2014
3.60
close up left wing top skins including wing walk
Details
       

 08-12-2014
0.50
check left wing before closure
Details

 08-10-2014
2.00
prepare various parts
Details

 08-06-2014
2.50
prepare W-1201C-L, mod rear spar rivets
Details
     

 07-24-2014
1.58
cleco and rivet W-1202B
Details
       

 07-23-2014
3.08
prep, deburr, rivet W-1203B-L, prep W-1202B-L
Details

 07-22-2014
1.25
Finish riveting W-1201B-L
Details

 07-21-2014
0.50
cleco W-1201B-L
Details

 07-15-2014
1.50
prepare W-1201B-L
Details

 07-11-2014
3.00
rivet left wing leading edge, flaperon hinges
Details
       

 07-11-2014
1.92
finish rivet and flip left wing
Details
       

 07-10-2014
2.67
Prep and cleco W-1202-L
Details

 07-09-2014
2.00
Rivet W-1201-L
Details
       

 07-08-2014
4.00
Finish prep of W-1201-L, deburr, cleco
Details

 07-07-2014
0.50
dimple holes, prepare W-1201-L
Details

 07-06-2014
0.25
Install stand-off with Loctite 243
Details

 07-03-2014
3.00
Finish deburring and cleco W-1203-L
Details
       

 07-02-2014
2.25
Prepare W-1203-L
Details

 07-02-2014
2.00
Left wing wiring connector and string light wires
Details
     

 07-01-2014
2.00
Left wing wiring connector
Details

 06-24-2014
3.50
Finish stall warning switch install & adjust
Details
       

 06-23-2014
1.00
stall warning switch GND wire
Details

 06-21-2014
1.00
transition flight training
Details

 06-20-2014
1.00
transition flight training
Details

 06-17-2014
38.00
Attend 2014 RV-12 Expo, transition flight training
Details
       

 06-14-2014
2.00
Construct stall warning switch assembly
Details
     

 06-13-2014
2.00
Finish left front wing ribs riveting.
Details
       

 06-12-2014
1.00
Continue prep for left front wing ribs & call Vans
Details

 06-10-2014
0.75
Prepare to begin front wing ribs on table
Details

 05-21-2014
2.00
Complete right wing rear main ribs
Details
       

 05-20-2014
1.67
Manual 15-04 step 9,15-06 cleco steps 1-7
Details

 05-17-2014
1.75
Complete most of left wing rear ribs attachment
Details
     

 05-16-2014
1.17
Finish rear main ribs
Details

 05-16-2014
1.16
finish deburring rear wing ribs and flute
Details
     

 05-15-2014
1.58
deburring right rear main wing ribs
Details

 05-14-2014
2.00
finished deburring left rear main wing ribs
Details

 05-13-2014
1.58
deburring rear main wing ribs
Details
     

 05-09-2014
2.33
Trim rear main ribs and deburr
Details

 05-08-2014
0.50
Remove plastic from rear main ribs
Details

 05-08-2014
1.50
deconstruct wing spar packaging
Details

 05-07-2014
6.55
Finish fwd ribs
Details
       

 05-06-2014
0.67
Deburr fwd ribs large holes
Details

 05-01-2014
1.33
Deburr forward wing ribs
Details

 04-30-2014
1.25
Deburr forward wing ribs
Details

 04-24-2014
1.20
Deburr fwd wing ribs
Details

 04-23-2014
2.00
trim forward wing ribs
Details

 04-16-2014
2.58
Left and right rear spar assemblies
Details
       

 04-14-2014
1.00
Prep tip attach angles.
Details

 04-10-2014
2.90
Rivet stub spars, hinge pieces
Details
       

 04-09-2014
5.50
Prep and countersink stub spars
Details

 04-02-2014
3.50
Complete wing main spars
Details
       

 04-01-2014
1.00
Start wing main spars
Details

 03-31-2014
1.50
Prep parts and steps 1 & 2
Details

 03-29-2014
1.00
Hang tailcone in garage
Details
     

 03-18-2014
0.83
Finish riveting tailcone assembly
Details
       

 03-15-2014
3.00
tailcone fwd skin rib, stiffeners, rivet right
Details

 03-14-2014
2.85
Finish rivet tailcone sides, cleco top skin
Details
       

 03-13-2014
2.00
Rivet left half of tailcone sides
Details

 03-11-2014
1.75
Install snap bushing brackets and guide strings
Details

 03-08-2014
1.25
deburr all holes and edges F-1279-L & R
Details

 03-07-2014
3.50
Route elev. trim wiring and static plumbing
Details
       

 02-25-2014
1.25
remove plastic from F-1279-L & R
Details

 02-24-2014
1.00
Flip tailcone and install skins
Details

 02-19-2014
5.09
Complete manual 10-06 and 10-07
Details
       

 02-05-2014
2.50
Add stiffeners to bottom tailcone skins
Details

 02-04-2014
0.42
Start prep of F-1282-L
Details

 02-04-2014
1.00
Deburr and break F-1278
Details

 01-29-2014
1.67
Deburr and break F-1280-L & R
Details

 01-22-2014
2.25
Deburr and break F-1281-L & R
Details

 01-21-2014
1.00
Deburr and break F-1282-R
Details

 01-16-2014
2.50
remove blue plastic from tail cone skins
Details

 12-17-2013
1.00
Finish wing kit inventory
Details

 12-10-2013
2.00
Unpack and inventory wing kit
Details
       

 12-03-2013
0.25
Wing kit delivered

 11-06-2013
1.75
Figure out and add washers to horz. stab.
Details

 10-28-2013
1.20
Finish F-1211 assembly
Details
     

 10-25-2013
3.20
Rivet F-1211 assembly
Details

 10-18-2013
0.00
Pictures of basement shop
Details
       

 10-18-2013
0.70
Match drill, final drill, Prime remaining nut plat
Details

 10-17-2013
1.55
work on fuselage rear bulkhead
Details

 10-16-2013
2.20
Complete manual page 10-03
Details

 09-25-2013
1.75
Fabricate Tail Skid bracket
Details
     

 09-19-2013
2.65
Finish F-1210 frame
Details
     

 09-13-2013
0.50
Rivet wear plate and tail cone ribs
Details
     

 09-11-2013
2.15
Deburred ribs F-1208 and F-1209
Details

 09-09-2013
0.60
Remove plastic and flute tailcone ribs
Details

 09-06-2013
0.40
Ordered wing kit
Details

 09-05-2013
0.70
sort parts and 10-02 step 3
Details

 09-03-2013
0.50
Hang the finished horizontal stab
Details
       

 08-30-2013
0.50
Add counterbalance weights
Details
       

 08-29-2013
2.90
Installed aft outside skins on stab
Details

 08-27-2013
2.00
Rivet hinges and aft ribs on stab.
Details
       

 08-27-2013
0.55
Finish riveting on horz. stabilator skeleton
Details
       

 08-26-2013
1.55
Rivet right main stab skin onto skeleton
Details

 08-22-2013
2.25
Rivet left main stab skin top and bottom
Details

 08-21-2013
3.80
Deburr main stab skins and cleco on skeleton
Details

 08-20-2013
1.00
Deburr inside of stab main skins
Details

 08-16-2013
1.75
Drill stab hinges
Details

 08-07-2013
1.00
Visited Vans Aircraft at Aurora, OR
Details
     

 07-18-2013
2.00
Install horz stab stops and torque, mark hinges
Details

 07-16-2013
0.75
Install horz stab hinges
Details

 07-11-2013
4.50
Finish Stabilator Skeleton Assembly
Details
       

 07-03-2013
1.00
Rivet horz spar rib clips, radius ribs
Details

 06-28-2013
2.50
Fab hinge stops,rivet spar caps
Details
       

 06-27-2013
2.50
Rivet all nut plates and counterbalance brackets
Details
       

 06-26-2013
3.25
horz stab spar work
Details

 06-25-2013
2.80
Cleco attach and drill counterbalance pieces
Details

 06-21-2013
4.00
Deburr and rivet stab spar caps
Details
       

 06-19-2013
1.50
Match drill #12, cut and deburr pieces
Details

 06-15-2013
1.50
Reread manual section 5, countersink holes
Details

 06-12-2013
2.10
Countersink horz stab spar pieces
Details

 06-06-2013
2.50
Drilled 2 hinges pieces, finished AST assemblies
Details
     

 06-05-2013
1.50
installed AST spars, cut AST hinges
Details
     

 06-03-2013
1.00
Countersink and rivet AST control horns
Details
     

 05-22-2013
1.10
Debur edges and rivet AST skins
Details

 05-21-2013
1.25
Debur HS-1222 ribs and HS-1221-L & R skins
Details

 05-16-2013
1.25
Prepare/drill left and right anti-servo tabs
Details

 05-15-2013
3.25
Finish rudder
Details
     

 05-14-2013
3.50
Finished Rudder skeleton assembly
Details
       

 05-08-2013
0.50
Screw on vert stab fwd skin & hinges
Details
     

 05-08-2013
2.00
Finish rudder spar assembly
Details
     

 04-26-2013
1.25
Finish riveting vert stab skin
Details
     

 04-25-2013
2.50
Rivet vert stab skin on skeleton
Details
     

 04-24-2013
3.00
Vert Stab main skin
Details
     

 04-12-2013
1.00
Finish riveting nut plates on VS-1201
Details
     

 04-11-2013
2.25
Final drill, dimple & rivet vert stab skins
Details
     

 04-10-2013
1.00
Trim fwd and main vert stab skins
Details

 04-06-2013
2.40
Complete V-Stab Skeleton Assembly
Details
     

 04-05-2013
0.60
Rivet two ribs to vert stab front spar
Details

 04-03-2013
1.75
Radius vert stab ribs, debur, flute
Details

 04-02-2013
1.30
Rivet the nut plates page 06-04
Details
       

 03-29-2013
0.50
Prime nut plates, deburr
Details

 03-29-2013
0.50
Finish mini paint booth
Details

 03-22-2013
1.00
Rivet spar caps to vert stab rear spar
Details
     

 03-20-2013
1.50
Countersink #40 holes
Details

 03-16-2013
1.25
Match drill #40 and #12 holes
Details
     

 03-14-2013
1.50
Finish match drilling #30
Details

 03-01-2013
1.00
Finish rudder hinges
Details
     

 02-25-2013
3.00
Match drill #30 holes
Details
     

 02-22-2013
2.00
Prime and work on more rudder pieces
Details
     

 02-21-2013
2.50
Rudder hinges
Details
     

 02-16-2013
2.00
Sort and store misc hardware
Details

 02-15-2013
0.50
Setup and test band saw
Details

 02-09-2013
3.00
Inventory Empenage
Details
     

 02-08-2013
1.75
Unpack kit from crate
Details
     

 02-04-2013
1.00
Pick-up various tools locally
Details

 02-01-2013
2.50
Pick up tools and visit W & C hangar
Details

 01-29-2013
0.50
Empennage crate delivered
Details

 01-26-2013
1.00
Modify Cleaveland Tool RV-12 spreadsheet
Details

 01-21-2013
0.50
Order RV-12 empennage and fastener kit
Details

 07-26-2012
0.50
RV-12 demo flight at Oshkosh
Details
       

 08-12-2006
0.50
Flew Gene Larsens RV 9A
Details

 07-30-2005
0.50
First ride in a Vans airplane, RV-7A at Oshkosh
     










Copyright © 2001-2024 Matronics. All Rights Reserved.