Paul's Zenith 601-XL
Work Logs Found: 171
Category Work Time: 527 Hours
 Date
Hours
Work Log Summary

Details

 10-08-2008
5.00
LG - INSTALL GEAR (#104)
Details
     

 10-06-2008
3.80
LG - WHEELS, AXELS, BRAKES (#102)
Details
     

 09-30-2008
4.00
Systems - Flight Controls (#21)
Details
       

 09-29-2008
3.57
601 Fuselage construction (#115)
Details
       

 09-26-2008
4.27
601 Fuselage construction (#115)
Details
       

 09-26-2008
3.97
601 Fuselage construction (#115)
Details
     

 09-25-2008
4.03
601 Fuselage construction (#115)
Details
     

 09-25-2008
5.22
601 Fuselage construction (#115)
Details
       

 09-23-2008
4.02
601 Fuselage construction (#115)
Details
       

 09-15-2008
3.77
601 Fuselage construction (#115)
Details
     

 09-13-2008
4.65
601 Fuselage construction (#115)
Details
       

 09-09-2008
5.43
Assembly - Canopy/Window (#14)
Details
       

 09-09-2008
2.05
601 Fuselage construction (#115)
Details
     

 09-08-2008
3.92
Systems - Flight Controls (#21)
Details
       

 09-08-2008
2.20
601 Fuselage construction (#115)
Details
       

 09-05-2008
6.22
601 Fuselage construction (#115)
Details
       

 09-03-2008
2.50
Systems - Fuel (#22)
Details
       

 08-28-2008
3.88
601 Fuselage construction (#115)
Details

 08-27-2008
3.52
601 Fuselage construction (#115)
Details

 08-27-2008
4.73
601 Fuselage construction (#115)
Details

 08-26-2008
3.80
601 Fuselage construction (#115)
Details

 08-26-2008
4.85
601 Fuselage construction (#115)
Details
     

 08-25-2008
2.58
601 Fuselage construction (#115)
Details

 08-25-2008
4.95
601 Fuselage construction (#115)
Details

 08-18-2008
1.43
601 Fuselage construction (#115)
Details

 08-15-2008
0.82
601 Fuselage construction (#115)
Details

 08-15-2008
5.35
601 Fuselage construction (#115)
Details
     

 08-14-2008
3.50
601 Fuselage construction (#115)
Details
     

 08-14-2008
5.82
601 Fuselage construction (#115)
Details

 08-14-2008
3.85
601 Fuselage construction (#115)
Details

 08-13-2008
4.05
601 Fuselage construction (#115)
Details

 08-12-2008
3.80
601 Fuselage construction (#115)
Details

 08-12-2008
3.33
601 Fuselage construction (#115)
Details

 08-12-2008
4.45
601 Fuselage construction (#115)
Details

 08-12-2008
4.27
601 Fuselage construction (#115)
Details

 08-11-2008
1.75
601 Fuselage construction (#115)
Details

 08-11-2008
7.37
601 Fuselage construction (#115)
Details

 06-17-2008
7.00
And put it all back together
Details
       

 06-16-2008
7.00
Disassembly, Deburr, and Prime
Details
       

 06-10-2008
2.00
Continued work on Baggage Floor
Details
       

 06-10-2008
4.00
Baggage Compartment Floor
Details
       

 06-01-2008
3.00
Started work on the seat back supports
Details
       

 05-29-2008
2.50
Finished spar access panels in seats
Details
       

 05-29-2008
3.00
Finished engine mount bolts and started seating
Details
       

 05-22-2008
2.00
More internal gusset work and mounting of the lowe
Details
       

 05-22-2008
5.00
Finished drilling front fuse side to bottom and f
Details
       

 05-19-2008
3.00
Added L angles to front of fuselage and started fo
Details
       

 05-17-2008
1.50
Installed 6B13-1 wing attachment brackets
Details
       

 05-16-2008
4.00
Just don't ask
Details

 05-12-2008
3.00
Finished main gear mounting, drilling fuse sides a
Details
       

 05-12-2008
2.00
Drilled bottom of side skins for and aft of the ge
Details
       

 05-03-2008
2.00
Gear mounts are located and drilled. Gear support
Details
       

 05-02-2008
3.00
Made new front fuse sides and drilled them in plac
Details
       

 04-30-2008
1.50
Rear turtle deck bulkheads and landing gear mounts
Details
       

 04-30-2008
15.00
Argh! Catch-up post on my fuse front side skin is
Details
     

 04-06-2008
2.00
Upper seat back and instrument panel
Details
       

 04-05-2008
2.50
Installed rear spar attachments and started on the
Details
       

 04-04-2008
5.00
Measuring, measuring, measuring! Firewall in plac
Details
       

 04-01-2008
5.00
Built wing alignment jig and moved fuse to paralle
Details
       

 03-26-2008
5.00
Rivted front bottom fuse and installed rudder peda
Details
       

 03-06-2008
4.00
Re-assembled front of fuse and worked on spar box
Details
       

 03-04-2008
4.50
Spar box and debur
Details
     

 02-29-2008
3.00
Clean-up work and joining of the front and rear fu
Details
       

 02-26-2008
3.00
Rudder Pedal Installation
Details
       

 02-22-2008
1.00
Started lower front floor of fuseage
Details
     

 02-21-2008
3.00
Riveted rear fuse
Details
       

 02-20-2008
3.00
Riveted the firewall and primed the fuse sides
Details
       

 02-19-2008
7.00
Firewall work
Details
       

 02-18-2008
3.00
Firewall work
Details
       

 02-15-2008
4.00
Upper rudder hinge point, landing gear channel, an
Details
       

 02-14-2008
4.00
Rear empanage mounting area framed
Details
       

 02-13-2008
4.00
Left rear fuse side
Details
       

 02-12-2008
3.00
Right rear fuse side
Details
       

 02-08-2008
4.00
Finished fuse bottom right side started
Details
       

 02-07-2008
1.00
Priming bottom of the fuselage
Details
       

 02-07-2008
4.00
Fuse bottom access panel fitted, dissassembly, and
Details
       

 02-05-2008
3.00
More work on fuselage bottom
Details
       

 02-03-2008
0.00
Attended Jabiru USA Engine Install seminar
Details
       

 01-25-2008
2.00
More work on the bottom skin
Details
     

 01-24-2008
2.50
More work on the bottom rear skin of the fues
Details
       

 01-24-2008
2.00
Jabiru 3300 Arrival!
Details
       

 01-23-2008
2.00
Cleaned up and started the fuesleage
Details
     

 01-22-2008
2.00
Right wing wiring and tank removal
Details
       

 01-22-2008
3.00
Finished Left wing
Details
       

 01-21-2008
5.00
Tanks completed, wiring almost complete
Details
       

 01-13-2008
3.50
Wing wiring, pitot plumbing, priming and tank work
Details
       

 01-11-2008
3.00
Removed top skin, deburred, access covers, wiring
Details
       

 01-08-2008
4.00
Finished work on the left wing tip
Details
       

 01-07-2008
4.00
Left wing lighting and wing tip
Details
       

 12-18-2007
4.00
Nose skin, nav lights, and taxi light
Details
       

 12-13-2007
5.00
Fuel sender installation and right wing complete
Details
       

 12-12-2007
3.00
Mounted the gas tanks in the right wing
Details
       

 12-11-2007
4.00
Finishing up landing lights and wiring
Details
       

 12-04-2007
3.00
Right landing light continued
Details
       

 12-04-2007
4.00
Little things and started on the landing lights
Details
       

 12-01-2007
3.00
Finished right wingtip and started installing wiri
Details
       

 11-28-2007
4.00
Right wingtip cont...
Details
       

 11-26-2007
2.00
More work on right wingtip
Details
       

 11-25-2007
2.00
Right Wing tip work begins
Details
       

 11-25-2007
2.50
Debur, install aileron bellcrank, rivet tie down r
Details
       

 11-21-2007
0.50
Primed upper skins
Details
     

 11-21-2007
4.00
Installed nose skin on right wing
Details
       

 11-14-2007
0.00
Move Complete.
Details
       

 11-04-2007
0.00
Moving Day
Details

 10-21-2007
14.75
Time to catch up!
Details
       

 09-19-2007
1.00
Right wing started
Details

 09-07-2007
1.50
Rear Bulkhead assembly
Details
       

 09-06-2007
1.00
Pulled nose skin in place
Details
       

 06-11-2007
2.00
Left skins riveted in place
Details
     

 06-10-2007
5.25
Finished pitot mounting, disassembled, deburred an
Details
       

 06-09-2007
2.00
Left wing leveled with solid blocks, nose skin ins
Details
       

 06-03-2007
4.00
Flipped left wing over, re-leveled it and drilled
Details
       

 06-01-2007
2.00
Top left rear wing skin drilled
Details
       

 05-28-2007
0.00
The trailer!
Details
       

 05-27-2007
1.00
Leveled Left wing
Details
       

 05-20-2007
3.00
Finished left wing skeleton
Details
       

 05-17-2007
3.50
Riveted right wing skelton and moved to the left w
Details
       

 05-15-2007
1.75
Disassembled right wing and deburred and primed
Details
       

 05-14-2007
2.50
Laid out, drilled and attached rear spar to right
Details
       

 05-12-2007
0.75
Root Doubler
Details
     

 05-11-2007
2.00
Attached the nose ribs to the right wing spar
Details
       

 05-10-2007
2.00
Rear ribs located and drilled to the right spar
Details
       

 05-09-2007
1.25
Rivetted Stiffeners to ribs
Details
       

 05-07-2007
2.50
Completed wing walk rib stiffeners
Details
     

 05-03-2007
4.00
Spar work and rib sub-assemblies
Details
       

 05-02-2007
4.00
Work table extention for wing construction
Details
       

 05-02-2007
1.50
Aileron bellcrank support
Details
     

 04-29-2007
1.50
Worked on small parts for the wing
Details
       

 04-29-2007
1.50
Assembled and riveted the ailerons
Details
       

 04-25-2007
6.00
Completed aileron trim tab assembly
Details
       

 04-24-2007
1.00
Started the aileron trim tab
Details
       

 04-24-2007
2.50
Completely assembled ailerons (except trim tab)
Details
       

 04-23-2007
1.00
Drilled ribs to aileron skin ends and bottom
Details
       

 04-22-2007
1.25
Prepped parts, made aileron control horns and mach
Details
       

 04-21-2007
2.00
Primed and assembled the flaps. Installed the err
Details
       

 04-20-2007
4.50
Assembled flaps
Details
       

 04-19-2007
1.00
Prep for flap assembly - drilled ribs to front of
Details
     

 04-15-2007
2.50
Closed up the rudder and added the nav light
Details
       

 04-14-2007
1.75
Added rudder nose skin, deburr and primed
Details
       

 04-09-2007
1.00
Rudder skin
Details
       

 04-09-2007
4.33
Disassembled, deburred, primed & riveted the eleva
Details
       

 04-08-2007
1.50
Cut-outs for trim tab control horns, fitted tab se
Details
       

 04-06-2007
1.00
Drilled hinge to the trim tab and elevator
Details
       

 04-05-2007
4.50
Finished control horn installation , started trim
Details
       

 04-01-2007
4.50
More elevator work
Details
       

 03-17-2007
1.00
Drilled top skin
Details
       

 03-07-2007
2.00
Started working on the elevator
Details
       

 03-07-2007
3.75
Finished up the stabilizer
Details
       

 03-06-2007
1.00
Positioned and drilled hinge on Stab
Details
       

 03-05-2007
1.00
Deburred and Primed Upper Skin
Details
     

 03-03-2007
1.50
Pulled the skin in place on the top of the stab an
Details
       

 03-01-2007
2.00
Debur, prime and rivet bottom of stab skin
Details
       

 02-28-2007
1.50
Skinned lower surface of the stab
Details
       

 02-28-2007
2.00
Aligned ard riveted skeleton
Details
       

 02-27-2007
2.00
Final fitting of rear spar and diassemble/deburr/p
Details
       

 02-26-2007
1.00
Fixing the mis-drilled stab ribs
Details
       

 02-25-2007
5.42
Stab skeleton assembly continues
Details
       

 02-22-2007
0.75
Stab spar assembly begins
Details
       

 02-22-2007
3.17
Rudder skeleton assembly begins
Details
       

 02-20-2007
8.00
Unpacking and Inventory
Details
       

 02-19-2007
1.00
Kit Arrives!
Details
       

 02-09-2007
0.00
Kit Shipped!!
Details

 01-17-2007
0.00
Honey-Do's while waiting for the kit
Details
     

 01-06-2007
3.00
Jigging Bars painted
Details
     

 12-27-2006
0.00
Kit delivery date
Details

 12-14-2006
0.00
Kit Ordered!
Details

 12-10-2006
1.00
Completed Worktable
Details
     

 12-09-2006
7.00
Building Work Table
Details
       

 09-13-2006
2.00
Printing Manual
Details

 09-07-2006
0.00
The Garage/Workshop
Details
     

 09-06-2006
1.00
Plans Arrived!