Work Logs Found: 395
Category Work Time: 1658 Hours
 Date
Hours
Work Log Summary

Details

 01-06-2023
3.00
Final Engineer Inspection
Details

 12-10-2022
4.00
Fuel Calibration
Details
       

 11-19-2022
2.00
Connecting both Tanks
Details
       

 11-18-2022
3.00
Weight and Balance
Details
       

 11-13-2022
5.00

       

 11-06-2022
5.00
Flap and Aileron Connection
Details
       

 11-05-2022
7.00
Wing Connection and final install
Details
       

 10-30-2022
6.00
Plane Assembly
Details
       

 10-29-2022
4.00
Airplane Transport
Details
       

 10-23-2022
3.00
Cockpit Foot Mats
Details
       

 10-16-2022
1.00
Engine Test Run
Details
       

 10-01-2022
3.00
Final Cockpit Install
Details
       

 09-18-2022
3.00
Flap Hinge at the Fuse
Details
       

 09-18-2022
20.00
Airplane Cover
Details
       

 08-20-2022
5.00
Pito Tube Install
Details
       

 08-20-2022
2.00
Installed Fuel Filter and rerouted Airlines for Pi
Details
       

 07-23-2022
6.00
Wing Final Prep
Details
       

 05-28-2022
4.00
Wing Final Install
Details
       

 05-21-2022
6.00
Wing Final Aileron Install
Details
       

 05-15-2022
1.00
Getting Wif's QA Approval
Details
     

 05-14-2022
16.00
Tool Bag
Details
       

 04-09-2022
4.00
Safety Harness Install
Details
       

 03-26-2022
6.00
Rudder Cable Adjustments
Details
       

 03-12-2022
6.00
Final installation of the Electronic parts on the
Details
       

 02-27-2022
20.00
Left Side and Back Panel
Details
       

 02-20-2022
10.00
Side Panel
Details
       

 02-13-2022
15.00
Second Seat
Details
       

 01-29-2022
15.00
First seat
Details
       

 01-22-2022
15.00
Quilt Pattern
Details
       

 01-15-2022
25.00
Pattern development
Details
       

 01-13-2022
2.00
Pre Asemble Inspection
Details

 01-05-2022
3.00
Upholstery
Details
     

 12-29-2021
6.00
Call Sign, Lettering and Labels
Details
       

 12-12-2021
8.00
Seat and Side Panel Cutting
Details
       

 11-27-2021
10.00
Pollished Left Wing
Details
       

 11-20-2021
1.00
German Threat Delivered
Details
       

 11-19-2021
0.50
Received the Leather for the Upholstery Job
Details
       

 10-17-2021
6.00
Wheel Spats
Details
       

 10-17-2021
10.00
Interia Design
Details
       

 08-24-2021
10.00
Painting of the Wheel Spats
Details
       

 08-11-2021
10.00
Wheel Spats Install and Alignment
Details
       

 02-06-2021
2.00
MGL Display Panel problem
Details
       

 01-30-2021
5.00
Main Leg Faring
Details
       

 01-23-2021
6.00
Main Spat install
Details
       

 01-16-2021
4.00
Front Spat
Details
       

 01-09-2021
2.00
Engine Clean up
Details
       

 01-02-2021
1.00
Exhaust install
Details
       

 11-18-2020
2.00
Settup of the VPX Box
Details
     

 11-15-2020
3.00
Scat tube install
Details
       

 11-14-2020
2.00
Propeller install
Details
       

 11-14-2020
1.00
Build an panel install aid
Details
     

 11-12-2020
1.00
Final Engine Mount Torque Check
Details
       

 11-08-2020
2.00
Elevator Stick position
Details
       

 11-07-2020
2.00
Welding the Exhaust
Details
       

 10-31-2020
8.00
Wiring the Cockpit panel
Details
     

 10-24-2020
2.00
Finall Install of the Canopy
Details
       

 10-17-2020
8.00
Add Ons
Details
       

 10-11-2020
3.00
Filling up Brake Fluid
Details
       

 10-10-2020
3.00
Installing the Canopy hinges
Details
       

 10-09-2020
3.00
Engine Wiring
Details
       

 10-08-2020
3.00
Air Filter box connection
Details
     

 10-07-2020
3.00
Oil Cooler connection
Details
       

 10-06-2020
4.00
Cockpit Pannel
Details
     

 09-12-2020
8.00
More wiring
Details
     

 09-05-2020
8.00
Engine Wiring
Details
       

 08-29-2020
5.00
More Cockpit Work
Details
       

 08-29-2020
5.00
Electrical Connections
Details
     

 08-22-2020
8.00
Wiring Ground negative and CAN Bus
Details
       

 08-15-2020
4.00
Throttle Quadrant final install
Details
       

 08-09-2020
1.00
Elevator Final install Push Rod
Details
     

 08-08-2020
2.00
Earth Bar
Details
       

 08-06-2020
2.00
Earth Bar
Details
       

 07-19-2020
4.00
Cableing in the Cockpit
Details
       

 07-18-2020
3.00
CAN Bus Communication wiring
Details
       

 07-11-2020
2.00
Mounting Blocks for Avionics Modules
Details
       

 07-04-2020
2.00
Aerial installation
Details
       

 06-28-2020
4.00
First Step Installed
Details
       

 06-27-2020
4.00
Break install
Details
       

 06-20-2020
2.00
Engine Install
Details
     

 06-14-2020
2.00
Firewall install check
Details
       

 06-13-2020
6.00
Final install of the Firewall
Details
       

 06-07-2020
6.00
Throttle Connection
Details
     

 05-31-2020
8.00
Seat Belt Install
Details
       

 05-24-2020
4.00
Painting Small Parts
Details
       

 05-19-2020
6.00
Finishing off the Tail Plane
Details
       

 05-14-2020
6.00
Elevator Final install
Details
       

 03-21-2020
4.00
Troque rod painting
Details
       

 03-14-2020
8.00
Elevator finishing
Details
       

 03-07-2020
4.00
Removal of Window Masking
Details
       

 02-23-2020
30.00
Polishing of the Fuselage
Details
       

 12-29-2019
8.00
Painting the Fuselage
Details
     

 12-28-2019
10.00
Painting the Fuselage
Details
       

 12-26-2019
3.00
Trail Paint
Details
       

 12-25-2019
5.00
Paint Prep
Details
       

 12-23-2019
8.00
Paint Prep
Details
       

 12-21-2019
16.00
Paint Prep
Details
       

 11-30-2019
8.00
Paint Prep
Details
       

 11-23-2019
8.00
Paint Prep
Details
       

 11-16-2019
12.00
Base coat sanding
Details
       

 11-09-2019
8.00
Base coat for the Fuse
Details
       

 11-02-2019
4.00
Painting prep
Details
     

 10-19-2019
8.00
Safety belt Screw covering
Details
       

 10-05-2019
8.00
Paint prep
Details
       

 06-08-2019
1.00
Preperation for painting the Fuse
Details
       

 05-18-2019
4.00
Preperation for Toe Setting
Details
       

 03-23-2019
5.50
3D Printing
Details
     

 03-02-2019
4.00
Air Duct Inlet Modification
Details
       

 02-16-2019
2.00
Ignition Cooling
Details
       

 02-02-2019
2.00
First Modification
Details
       

 12-02-2018
4.00
Air Ducting
Details
       

 12-01-2018
3.00
Air Engine Ducting
Details
       

 11-25-2018
4.00
Engine Control Box
Details
       

 11-24-2018
2.00
Oil Cooler Duct
Details
       

 11-19-2018
2.00
Installing the Oil Cooler
Details
       

 11-18-2018
4.00
Bending Oil Cooler Metal
Details
       

 11-17-2018
4.00
Oil Cooler Manufacturing
Details
       

 11-13-2018
1.00
Installing the braket for the Oil cooler
Details
     

 11-12-2018
1.00
Starter Solenoid Install
Details
     

 11-11-2018
1.00
Cabin Heater Control install
Details
     

 11-10-2018
2.00
Installing Control Box for the EFIS
Details
       

 11-09-2018
0.50
Material used
Details
     

 10-21-2018
2.00
Installing the Air Box
Details
       

 10-20-2018
2.00
NACA Scoop sanding
Details
       

 10-02-2018
2.00
Glueing the NACA scoop to cowl
Details
       

 10-01-2018
3.00
Glueing NACA Scoops to the Fuse
Details
       

 09-30-2018
10.00
Nose Wheel Spats and Faring installation
Details
       

 09-29-2018
2.00
Manufacturing Clamps for Front Leg Faring
Details
       

 07-29-2018
2.00
Oil Stick Cover
Details
       

 07-22-2018
2.00
Oil Stick Cover
Details
       

 07-15-2018
2.00
Cowl Oil Stick
Details
       

 07-05-2018
1.00
Spats fitting
Details
     

 07-03-2018
1.00
Cowl fitting
Details
       

 07-01-2018
4.00
Front Spat
Details
       

 06-02-2018
5.00
Cowl Fitting
Details
       

 05-19-2018
2.00
Cowl fitting
Details
       

 03-17-2018
4.00
Engine Rubber Press
Details
       

 02-12-2018
1.00
Engine Maintenance Course
Details
     

 01-20-2018
5.00
Cowl Install
Details
       

 01-13-2018
3.00
Engine Install
Details
       

 12-09-2017
4.00
Nose Wheel Alignment
Details
       

 12-02-2017
16.00
Main Gear Install
Details
       

 11-25-2017
7.00
Carpet Cutting
Details
       

 11-19-2017
3.00
Middle Console
Details
       

 11-18-2017
7.00
Canopy
Details
       

 11-11-2017
4.00
Throttle Quadrant
Details
     

 10-21-2017
8.00
Left Wing Polish
Details
       

 10-20-2017
2.00
Final Delivery of Engine JJ3300 V4
Details
     

 09-10-2017
2.00
Canopy Top
Details
       

 09-04-2017
20.00
Painting the Wings
Details
       

 09-03-2017
8.00
Painting the Wings
Details
       

 08-19-2017
7.00
Inside Frame Painted
Details
       

 08-12-2017
1.00
Painted Inside Canopy Handle
Details
     

 07-23-2017
1.00
Fuel System Install
Details
     

 07-01-2017
4.00
Aileron Servo Install
Details
       

 06-17-2017
2.00
Modified Servo Push Rod
Details
     

 06-11-2017
2.00
Fuel system and Firewall Hole drilling
Details
       

 06-10-2017
3.00
Aileron Servo Install
Details
     

 05-27-2017
3.00
Air Box Prep Work
Details
       

 05-20-2017
3.00
Pattern Details
Details
       

 05-13-2017
3.00
More Patterns for the Upholstery
Details
       

 05-06-2017
6.00
Upholstering Preparation
Details
       

 03-04-2017
3.00
Electronic Installation
Details
     

 11-19-2016
2.00
Tail Fin Camera Installed
Details
       

 11-05-2016
10.00
Camera Holder
Details
       

 05-01-2016
5.00
Assembling the Cockpit Panel
Details
       

 04-17-2016
4.00
Pollishing
Details
       

 04-10-2016
8.00
Instrument Panel
Details
       

 04-03-2016
4.00
Painting Cockpit Panel
Details
       

 04-02-2016
5.00
Carbone fibre Painting
Details
       

 03-27-2016
5.00
Break Valve Location
Details
       

 03-26-2016
4.00
Final Wing Assembly
Details
       

 03-23-2016
1.00
First parts getting final paint
Details
       

 03-20-2016
4.00
Luggage Aera Completed
Details
       

 03-19-2016
4.00
New Canopy Lock
Details
       

 03-13-2016
2.00
Testing the remote Door Lock
Details
       

 03-12-2016
5.00
Mounting the remote Door Lock
Details
       

 03-05-2016
4.00
Finishing the carpet
Details
       

 02-28-2016
8.00
Carpet in Luggage Area
Details
       

 01-03-2016
3.00
Paint Sample
Details
       

 12-19-2015
2.00
Covered Seat with Carpet
Details
       

 12-12-2015
8.00
Canopy remote Lock Actuator
Details
       

 12-05-2015
3.00
Back rest support
Details
       

 11-29-2015
3.00
Canopy Locking Mechanism
Details
       

 11-15-2015
3.00
Cockpit Panel Work
Details
       

 11-04-2015
1.00
Middle Console
Details
       

 10-29-2015
1.00
Middle Console
Details
     

 10-28-2015
2.00
Middle Console
Details
       

 10-25-2015
6.00
New Cockpit Panel
Details
       

 10-24-2015
10.00
Middle Console
Details
     

 10-17-2015
10.00
Middle Console
Details
       

 10-10-2015
3.00
Middle Console
Details
     

 10-09-2015
1.00
Transponder Mounting
Details
       

 10-08-2015
1.00
Throttle Lever Mounting
Details
       

 10-07-2015
3.00
Carbone Cockpit
Details
       

 10-05-2015
2.00
Carbon Cockpit
Details
       

 10-04-2015
1.00
Flap Indicator Installed
Details
       

 10-03-2015
2.50
Flap Indicator Mounting
Details
       

 09-27-2015
2.00
Mounting for Servos
Details
       

 09-20-2015
4.00
Servos for Auto Pilot
Details
       

 05-03-2015
5.00
Final Wing Preparation
Details
       

 02-17-2015
3.00
Install Instruments
Details
       

 01-10-2015
8.00
Cockpit Panel
Details
     

 12-13-2014
2.00
Final Sanding of the left wing
Details
       

 12-06-2014
3.00
Right Wing Under Coating
Details
       

 11-29-2014
4.00
Color Sample
Details
       

 11-15-2014
3.00
Airplane Sample Painting
Details
     

 11-09-2014
3.00
Instrument Panel
Details

 11-08-2014
6.00
Right Wing
Details
       

 11-01-2014
5.00
Left Wing Details
Details
       

 09-13-2014
3.00
Under Coat on First Wing Underside
Details
       

 09-04-2014
3.00
Under Coat
Details
       

 09-03-2014
4.00
Under coat
Details
       

 07-20-2014
2.00
Gascolator Bracket
Details
     

 05-18-2014
4.00
Paint Prep Work
Details
       

 04-12-2014
2.50
Flap Preperation
Details
       

 04-10-2014
3.00
General Check
Details
       

 04-07-2014
3.00
Opera Window Finishing
Details
       

 04-06-2014
3.50
Opera Window Install
Details
       

 04-05-2014
3.00
Final Rudder work
Details
       

 04-03-2014
4.00
Epoxy Primer and Filler
Details
     

 04-02-2014
4.00
Control Mixer trail and Sanding
Details
     

 04-01-2014
5.00
Workshop Move
Details
       

 03-31-2014
5.00
Rudder testing and Spar Box Troque
Details
       

 03-30-2014
3.00
Luggage Support and Rudder Control
Details
       

 03-29-2014
5.00
Luggage Compartment
Details
       

 03-28-2014
5.00
Lot of tidy up work
Details
       

 03-27-2014
5.00
Final Sanding of the right Wing top
Details
       

 03-26-2014
5.00
Foot Step Install
Details
       

 01-30-2014
2.50
Seat rail install
Details
       

 01-29-2014
4.50
Fitting the Centre Console Mounts
Details
       

 01-27-2014
4.00
Seat Side Rail Install
Details
       

 01-26-2014
4.00
Seat Installation
Details
       

 01-12-2014
2.00
Oil Cooler NACA
Details
       

 01-05-2014
2.00
Finising the Top Side of the Wing
Details
       

 12-29-2013
2.50
Engine Mount Washers Install
Details
       

 12-22-2013
5.50
Drilling Firewall Holes
Details
       

 12-15-2013
18.00
Firewall Polish
Details
       

 12-01-2013
10.00
Polishing Rig
Details
     

 11-17-2013
0.00
Work Shop Companion
Details
       

 11-17-2013
4.00
Firewall cutout
Details
     

 10-23-2013
5.00
Finishing Wing Underside
Details
       

 10-20-2013
1.00
Firewall Cut-out
Details
       

 10-15-2013
5.00
Filling Sanding Filling...
Details
       

 10-11-2013
2.00
Closing the Aileron Gap
Details
       

 10-09-2013
1.50
Landing Light Frame Install
Details
       

 10-07-2013
2.00
Aileron Gap
Details
       

 10-06-2013
2.00
Finished the Flap Gap
Details
       

 10-05-2013
2.00
A few Little Jobs
Details
       

 10-04-2013
3.00
Wing Tip Attached
Details
       

 10-03-2013
3.00
Wing Tip Prep
Details
       

 10-02-2013
5.00
Flap Gap Close Up
Details
       

 10-01-2013
3.00
Wing Tip Rib
Details
     

 09-30-2013
5.00
Wing Tip Line up
Details
       

 09-28-2013
2.00
Wing Tip Alignment
Details
       

 09-28-2013
2.00
New Cockpit Panel
Details
     

 09-27-2013
1.00
Outer Aileron Bracket
Details
       

 09-27-2013
4.00
Aileron Brackets
Details
       

 09-25-2013
3.00
Installed the Flap and Wing Tip Vent
Details
       

 09-24-2013
1.00
Fuse with Right Wing
Details
     

 09-23-2013
3.00
Rudder Pedal Support Beam
Details
       

 09-22-2013
2.00
Right Wing AOI Nutplate
Details
       

 09-21-2013
6.00
Top Wing Fairing
Details
       

 08-31-2013
3.00
Main Landing Leg Install
Details
       

 08-17-2013
2.00
Finishing work allaround
Details
       

 08-10-2013
1.50
Installing the Flap Bracket
Details
       

 08-03-2013
4.00
Modifying the Cockpit Frame
Details
       

 07-28-2013
10.00
Sourcing the Avionics
Details

 07-06-2013
4.00
More Finishing Work
Details

 06-30-2013
2.00
Aileron Linkage and more Filling
Details
       

 06-23-2013
2.00
Test Fit of Flap and Aileron and Cutting Trailing
Details
       

 06-16-2013
2.00
More Filling and Sanding
Details
       

 06-15-2013
3.00
Flap Bracket and Landing light install
Details
       

 06-08-2013
2.00
Finishing the Aileron
Details
       

 06-02-2013
2.00
More Filling Work
Details
       

 06-01-2013
5.00
Wing Tip Fibre glassing
Details
       

 05-26-2013
3.00
Preperation for Glassing the Tip
       

 05-11-2013
5.00
Wing Tip Gluing
Details
       

 04-21-2013
4.00
Closing the Wing Tip Aileron Gap
Details
       

 04-13-2013
10.00
Wing Tip Profile
Details
       

 03-29-2013
2.00
Wingtip Trailing Edge
Details
       

 03-29-2013
2.00
Wingtip prep Work
Details
       

 03-27-2013
5.00
Wingtip work
Details
       

 03-26-2013
2.00
Installing the Aileron Hinges
Details
       

 03-25-2013
1.00
Position of Out-board Bracket
Details
       

 03-25-2013
2.00
Bending the Inboard Aileron Hinge
Details
       

 03-24-2013
2.00
Installing the Flaps
Details
       

 03-24-2013
1.50
Flap Cut-out
Details
       

 01-28-2013
1.50
More Sanding and Filling
       

 01-27-2013
2.00
Sanding the Glare Shield
Details
       

 01-26-2013
2.50
Glare Shield
Details
       

 01-19-2013
1.50
Glare Shield prepwork
Details
       

 01-13-2013
2.00
Glare Shield prep
Details
       

 01-13-2013
1.50
Access Cover
Details
       

 01-12-2013
3.50
Fuel Sender Probe
Details
       

 01-06-2013
3.00
More prep work
Details
       

 12-30-2012
4.00
Wing Prep Work Number Two
Details
       

 12-30-2012
6.00
Deja-vu Strikes me, same Work for the Second Wing
Details
     

 12-29-2012
2.00
Landing Light Prep Work
Details
       

 12-29-2012
2.00
Fuel Filler Sanding and FIlling
Details
       

 12-26-2012
3.00
Fuel Filler Cap
Details
       

 12-23-2012
3.00
Frame Cut-out and Preparation
Details
       

 12-23-2012
2.00
Finishing little things
Details
       

 12-22-2012
3.00
Flap Filling and Rework
Details
       

 12-22-2012
2.00
Cutting Templet for Landing Light
Details
       

 12-16-2012
4.00
Wing Preperation
Details
       

 12-16-2012
2.00
Installed the Check Valve for theTank Vent
Details
       

 12-15-2012
1.50
Wing Preperation
Details
       

 12-13-2012
2.00
Rudder Paddle Retainer Rings
Details
     

 12-09-2012
2.00
Torsional Support Bar
Details
       

 12-01-2012
2.00
Attache Weldment to Leg
Details
       

 11-25-2012
2.00
Nutplate Mounting
Details
       

 11-24-2012
2.00
Left Wing AOT Nutplate Install
Details
       

 11-18-2012
2.00
Wing AOT checked and drilled
Details
       

 11-11-2012
4.00
Pulley Assembly
Details
       

 11-10-2012
6.00
Gear Leg and Axle Assembly
Details
       

 11-03-2012
4.50
Front wheel
Details
       

 11-01-2012
1.00
Drill Axle Bolt Hole on Nose Fork
Details
     

 10-27-2012
5.00
Rudder Pedal Support
Details
       

 10-20-2012
2.00
Landing Gear Support
Details
     

 10-18-2012
3.00
Air Intake
Details
       

 10-10-2012
1.50
Elevator Trim Tab
Details
       

 10-07-2012
3.00
Air Intake for Cockpit
Details
       

 10-06-2012
4.00
Trim Tab
Details
       

 10-02-2012
1.00
Spar Box Final Install
Details
       

 10-01-2012
5.00
Wing Alignment and Incident
Details
       

 09-30-2012
4.00
Trim Tab Control Horn
Details
       

 09-29-2012
2.00
Preparation for Wing Assembly
Details
     

 09-29-2012
4.00
Install of the Spar box
Details
       

 09-23-2012
4.00
Pedal Push Rod Assembly
Details
       

 09-22-2012
6.00
Fitting the Break Cylinders
Details
       

 09-21-2012
1.00
Filling Glass Frame on Canopy
Details
       

 09-16-2012
4.00
Cleaning the Frame Edge
Details
       

 09-15-2012
4.00
Glassing the Canopy Frame
Details
       

 09-13-2012
1.00
Canopy Preparation
Details
     

 09-10-2012
1.00
Cutting Expender Foam
Details
       

 09-09-2012
4.00
Further Preparation of the Canopy Frame
Details
       

 09-08-2012
4.00
Gluing the Canopy
Details
       

 09-06-2012
1.00
Trim Servo Connection
Details
       

 09-02-2012
5.00
Canopy Gluing Preparation
Details
       

 08-26-2012
2.00
Hinge Final Test and Completion
Details
       

 08-25-2012
4.00
Canopy Frame Preparation
Details
       

 08-19-2012
4.00
Finishing the Flute Tube and Support
Details
       

 08-18-2012
4.00
Canopy Lock Install
Details
       

 08-17-2012
4.00
Installed the Strut Mount and the Canopy Guide
Details
       

 08-15-2012
4.00
Further Modifications on Brackets
Details
       

 08-14-2012
5.00
Canopy Hinge Bracket
Details
       

 08-13-2012
5.00
Canopy Hinge Bracket
Details
       

 08-11-2012
4.00
New Canopy Hinges
Details
       

 08-08-2012
2.00
Fuselage Joint Preparation
Details
       

 08-05-2012
5.00
Canopy Hinge Install
Details
       

 08-04-2012
3.00
Finished the Dashboard Mount
Details
     

 07-29-2012
4.00
Dashboard Mount Install
Details
       

 07-27-2012
2.00
More Sanding and Filling
Details
     

 07-22-2012
5.00
A lot of Sanding and little Jobs
Details
       

 07-21-2012
3.00
Sanding Glueing etc
Details
       

 07-18-2012
2.00
Canopy Strut Mount and Cockpit Vent
Details
       

 07-15-2012
5.00
Cockpit Panel Work
Details
       

 07-14-2012
4.00
Glassed the Bottom Fuse Joint
Details
       

 07-13-2012
1.00
Fuselage Preparation
Details
     

 07-08-2012
3.00
Filling the HS Fairing Underside
Details
     

 07-07-2012
4.50
Turned the Fuselage
Details
       

 07-05-2012
1.50
Install Trim Tab Hinge
Details
       

 07-03-2012
1.50
Trim Tab Installation
Details
       

 07-01-2012
6.00
Install of Instrument Panel
Details
       

 06-30-2012
2.00
Instrument Panel Preperation
Details
     

 06-29-2012
2.00
Glassing the Gap on Tail
Details
       

 06-26-2012
2.00
More Sanding
Details
       

 06-25-2012
1.50
Elevator Bell Crank
Details
     

 06-22-2012
3.00
Drilling the AOI Bolts
Details
       

 06-17-2012
10.00
Rework of the HS Spar
Details
       

 06-11-2012
5.00
Canopy Preparation
Details
       

 06-09-2012
6.00
Canopy Preparation
Details
       

 06-08-2012
3.00
HS Sanding
Details
     

 06-03-2012
5.00
Elevator Balance Modification
Details
       

 06-02-2012
5.00
Elevator Balance Modification
Details
       

 05-29-2012
2.00
HS Hinge Install Left Site
Details
     

 05-28-2012
5.00
Making Incidence Meter
Details
       

 05-24-2012
2.00
Fabricating Mounting Pan for Trim Servo
Details
       

 05-23-2012
2.00
Rudder Filling and Preparation
Details
       

 05-21-2012
2.00
Elevator Preparation
Details
       

 05-19-2012
5.00
Elevator Bell Crank
Details
       

 05-17-2012
5.00
Work on HS and elevator
Details
       

 05-13-2012
6.00
Install the hinges and prep the elevator
Details
     

 05-11-2012
1.00
Hinge Drilling
Details
     

 05-10-2012
1.50
Cutting the HS hinges
Details
     

 05-09-2012
1.50
Cover plate on HS
Details
       

 05-08-2012
1.00
Hinge line cutting
Details
       

 05-07-2012
8.00
Horizontal stab install preperation
Details

 05-04-2012
6.00
Horizontal stab install preperation
Details
       

 05-03-2012
4.00
Rudder hinge mounting
Details
       

 05-02-2012
8.00
Fuselage Preparation
Details
       

 05-01-2012
4.00
Wing spar-box cut-out
Details
       

 04-30-2012
4.00
Opera window cut out
Details
       

 04-29-2012
5.00
Building wing rack and fuselage stand
Details
       

 04-26-2012
3.00
Arrival of the Crate
Details
       