Aviation Partners, LLC Project
Work Logs Found: 303
Category Work Time: 4002 Hours
 Date
Hours
Work Log Summary

Details

 11-10-2012
60.00
Completed Flight Test and Sign Off
Details

 10-11-2012
7.00
Addressed test flight 1 squawks
Details

 10-10-2012
1.00
First Flight
Details
       

 10-09-2012
2.00
DAR Inspection
Details
       

 10-06-2012
4.00
Installed Data Plate and various items
Details

 10-05-2012
3.00
Met with DAR
Details

 10-04-2012
10.00
Inspected all controls and taxied aircraft
Details

 10-02-2012
10.00
Engine Runup and Taxi with cowling on
Details
       

 10-01-2012
3.00
First Engine Run up Successful
Details
       

 09-29-2012
4.00
Weighed Aircraft
Details

 09-23-2012
15.00
Finished up with assembly
Details
       

 09-22-2012
6.00
Calibrated Fuel Sender
Details

 09-21-2012
22.00
Finished wing installation
Details
       

 09-19-2012
10.00
Finished installation of wings
Details
       

 09-18-2012
2.00
Re-installed flaps
Details

 09-18-2012
6.00
Installed Wings
Details
       

 09-17-2012
2.00
Installed Pitot tube and aileron trim servo
Details
     

 09-17-2012
6.00
Finished empennage installation
Details
       

 09-16-2012
9.00
Continued empannage install
Details

 09-15-2012
10.00
Moved to airport
Details
       

 09-11-2012
15.00
Fixed a couple of minor paint issues
Details

 09-10-2012
2.00
Installed compass
Details
       

 09-10-2012
2.00
Fabricated gust lock
Details
     

 09-03-2012
2.00
Installed Seats
Details
       

 09-01-2012
9.00
Installed Sticks and misc
Details
       

 08-31-2012
6.00
Modified Exhaust system bracket
Details
       

 08-29-2012
2.00
Installed nose wheel pant
Details

 08-29-2012
2.00
Installed heat shield
Details
     

 08-28-2012
4.00
Installed the Aerosport Rudder Trim
Details

 08-28-2012
55.00
Completed Painting of Wheel Pants
Details
       

 08-26-2012
14.00
Started on wheel pants
Details
       

 08-24-2012
18.00
Painted Wing Tips
Details
       

 08-22-2012
6.00
Finished up installing the insrument panel
Details
       

 08-22-2012
46.00
Finished Painting Wings
Details
       

 08-16-2012
20.00
Continued with Painting Prep
Details

 08-08-2012
3.00
Engine inspected by A/P, installed prop
Details
       

 08-07-2012
30.00
Installing interior
Details
       

 08-02-2012
1.00
Installed new linkage for prop govenor
Details
       

 08-01-2012
12.00
Installed stick grips and adjusted torque tubes
Details
       

 07-27-2012
140.00
Continued with painting
Details

 07-06-2012
2.00
Bleed Brakes
Details
       

 07-04-2012
38.00
Finished up engine installation
Details
       

 06-30-2012
20.00
Continued with Engine Installation
Details
       

 06-28-2012
12.00
Finished Vert Stab Paint
Details
       

 06-26-2012
52.00
Installing Engine Accessories
Details
       

 06-14-2012
48.00
Finished painting the fuse
Details
       

 06-09-2012
28.00
Painted bottom of Fuse
Details
       

 06-02-2012
10.00
Painted base color on fuselage
Details
       

 06-01-2012
9.00
Final Primed Fuselage
Details
       

 05-30-2012
60.00
Finally Color
Details
       

 05-29-2012
2.00
Paint Scheme completed in Photshop
     

 04-30-2012
6.00
Fuselage off to painter
Details
       

 04-26-2012
33.00
Finish cowl baffle
Details

 04-18-2012
30.00
Finished trimming baffle aluminum
Details
       

 04-15-2012
30.00
Worked on baffle seals
Details
       

 04-12-2012
10.00
Primed Cowls
Details
       

 04-11-2012
15.00
Skim coated cowl
Details
       

 04-09-2012
7.00
Installed louvers in cowl
Details
       

 04-08-2012
9.00
Worked on air inlet
Details
       

 04-07-2012
30.00
Completed Filtered Air Box and started cowl air in
Details
       

 04-03-2012
30.00
Continued with the cowling installation
Details
       

 03-30-2012
48.00
Installed attachment hinges on cowl
Details
       

 03-24-2012
26.00
Trimmed Cowling
Details
       

 03-21-2012
30.00
Primed Wheel Pants and Fairings
Details
       

 03-19-2012
5.00
Installed Tail
Details
       

 03-16-2012
4.00
Installed engine on aircraft
Details
       

 03-15-2012
38.00
Worked on Cowling
Details
       

 03-09-2012
7.00
Completed Fab of the spinner
Details
       

 03-08-2012
9.00
Began spinner fabrication
Details
       

 03-07-2012
10.00
Installed Upper Click Loc Tabs
Details
       

 03-06-2012
42.00
Completed Farings and Wheel Pants
Details

 02-29-2012
9.00
Began install of lower right intersection fairing
Details
       

 02-28-2012
30.00
Began installation of the gear leg fairings
Details
       

 02-18-2012
20.00
Installed Nose Strut Fairing
Details
       

 02-14-2012
55.00
Finished Left and Front Wheel Pants
Details
       

 02-07-2012
25.00
Installed right wheel pant
Details
       

 02-03-2012
4.00
Assembled Right Wheel Pant
Details
       

 02-02-2012
4.00
Reconfigured Fuse Stand
Details

 01-31-2012
10.00
Attached Axle and Nose Gear
Details
       

 01-29-2012
6.00
Attached Landing Gear
Details
       

 01-27-2012
9.00
Attached Engine Mount
Details
       

 01-26-2012
10.00
Finished empenage farining
Details

 01-25-2012
6.00
Worked on Empennage Fairing
Details
       

 01-15-2012
2.00
Fabricated hinge cover plate
Details
     

 01-13-2012
25.00
Attached Right Door
Details
       

 01-09-2012
30.00
Finished up with the windows and priming
Details
       

 01-04-2012
23.00
First Prime on Doors And fuse
Details
       

 01-02-2012
52.00
Continued with final installation of windows
Details
       

 12-26-2011
34.00
Continued with installation of front and side wind
Details
       

 12-20-2011
6.00
Began installation of wind screen
Details
       

 12-19-2011
9.00
Installed last interior panels
Details
     

 12-16-2011
45.00
Installed right and left window
Details
       

 12-13-2011
9.00
Installed instrument panel
Details
       

 12-12-2011
45.00
Installed Cabin Cover
Details
       

 12-09-2011
10.00
Installed Aerosport interior panels
Details
     

 12-08-2011
9.00
Finished installing Glareshield
Details
       

 12-07-2011
5.00
Fitted Windshield
Details

 12-06-2011
4.00
Epoxied Cabin Cover
Details
       

 12-04-2011
3.00
Cut out interior Kydex
Details
     

 12-03-2011
36.00
Began re-assembly of cabin cover
Details
       

 11-29-2011
20.00
Started assembling panel and interior
Details
       

 11-27-2011
6.00
Painted interior pieces
Details
       

 11-26-2011
7.00
Fabricated glare shield overlays
Details
       

 11-25-2011
9.00
Finished Priming panel overlay
Details
       

 11-23-2011
6.00
Attached upper fwd fuselage
Details
     

 11-22-2011
6.00
Primed center arm rest and various pieces
Details
     

 11-20-2011
30.00
Wired control stick and audio jacks
Details
       

 11-15-2011
6.00
Wired Flap motor and position sensor
Details
       

 11-14-2011
10.00
Continued with wiring
Details
       

 11-11-2011
10.00
Dynon magnetometer
Details
       

 11-10-2011
12.00
Installed Instrument Panel
Details
       

 11-09-2011
30.00
Continued with firewall
Details
     

 11-01-2011
12.00
Installed Firewall Insulation
Details
       

 10-30-2011
4.00
Installed remaining insulation
     

 10-29-2011
22.00
Panel Checkout
Details
     

 10-27-2011
64.00
Continued work on the wiring
Details
       

 10-22-2011
70.00
Fired up Panel
Details
       

 10-16-2011
110.00
Continue Panel Wiring
Details
       

 10-12-2011
60.00
Last 12 days
Details
       

 10-05-2011
9.00
Continued wiring of panel
Details
     

 10-04-2011
24.00
Continued with wiring
Details
       

 09-28-2011
10.00
Started wiring the avionics harnesses
Details
       

 09-27-2011
7.00
Completed wiring if Batteries
Details
       

 09-26-2011
10.00
Cleaned up cables to rear of aircraft
Details
     

 09-23-2011
4.00
Installed Whelen Power Supply Bracket
Details
     

 09-22-2011
6.00
Fabricated Annunciator Panel
Details
       

 09-20-2011
6.00
Mounted various avionics on panel
Details
       

 09-19-2011
9.00
Painted instrument sub-panel
Details

 09-16-2011
10.00
Pulled wire
Details
       

 09-15-2011
8.00
Completed Aux Batt Mount
Details
       

 09-14-2011
10.00
Located various avionics and fabricated shelf
Details
       

 09-13-2011
5.00
Cut out sub panel to accomodate radio stack
Details

 09-12-2011
2.00
Installed avionics fan
Details
     

 09-07-2011
10.00
Installed side panels and throttle quadrant
Details
       

 09-06-2011
5.00
Completed installation of flap bracket
Details
       

 09-05-2011
6.00
Began fabrication of Flap Position Assy
Details
       

 09-03-2011
10.00
Continued installation of the inst. panel
Details
       

 09-02-2011
9.00
Began installation of Instrument Panel
Details
       

 08-28-2011
4.00
Attached right wing fairings
Details
       

 08-27-2011
3.00
Attached Right Wing
Details
       

 08-26-2011
6.00
Completed disassembly of wing attachment
Details
       

 08-25-2011
10.00
Installed wing root fairings
Details
       

 08-24-2011
24.00
Attached control surfaces and pushrods
Details
       

 08-23-2011
12.00
Attached Left Wing
Details
       

 07-24-2011
6.00
Completed Wing Root Fairings
Details
       

 07-22-2011
9.00
continued with section 44
Details
       

 07-21-2011
5.00
Began Wing attachment tasks
Details
       

 07-20-2011
2.00
Built Flap Pushrod
Details

 07-19-2011
4.00
Installed connector on A/P and Pitot Heat
Details
       

 07-18-2011
6.00
Installed connectors for aileron trim
Details
       

 07-06-2011
7.00
Finished right and left wing tip
Details
       

 07-05-2011
2.00
Attached Bellcrank to aileron pushrod
Details
     

 07-04-2011
6.00
Began attachment of right wing tip
Details
       

 07-04-2011
2.00
Attached brackets to aileron and flap (R)
Details

 07-01-2011
17.00
Began with attachment of right wing tip
Details
       

 06-30-2011
8.00
Completed riveting W-1005 (r)
Details
       

 06-29-2011
5.00
Continued riveting W-1005 (R)
Details
     

 06-28-2011
6.00
Continued working on riveting W-1005 skin (R)
Details
     

 06-27-2011
6.00
Started attachment of lower wing skin (R)
Details
     

 06-25-2011
4.00
Attached right torque tube
Details
     

 06-24-2011
9.00
Completed match drilling and dimpling of w-1005
Details
     

 06-23-2011
2.00
Installed right fuel sender
Details

 06-22-2011
10.00
Match drilled J channel and W-1005 skin right side
Details

 06-21-2011
6.00
Installed left Torque Tube Assembly
Details
       

 06-21-2011
2.00
Competed installation of Aileron Trim
Details

 06-20-2011
2.00
Attached Flap to wing (left)
     

 06-20-2011
10.00
Attached aileron brackets
Details

 06-19-2011
4.00
Completed wing access plates for w-1005L
Details

 06-17-2011
6.00
Completed attachment of lower outboard bottom skin
Details
       

 06-16-2011
4.00
Completed right wingtip lighting
Details

 06-15-2011
4.00
Continued riveting of left bottom skin
Details
     

 06-14-2011
6.00
Competed installaion of wingtip lights
Details

 06-13-2011
8.00
Installed lens and left wing tip lighting
Details
       

 06-13-2011
4.00
Began riveting lower wing skin
Details
     

 06-10-2011
5.00
Dimpled lower left wing skin
Details

 06-10-2011
4.00
Completed wire harness for left
Details
       

 06-09-2011
10.00
Fit lower outboard left wing skin
       

 06-08-2011
4.00
Installed Dynon Pitot
Details
       

 06-06-2011
10.00
Installed left wing gap fairings
Details
       

 06-04-2011
6.00
Fabricated left forward torque tube
Details
     

 06-03-2011
6.00
Assembled Aileron Trim
Details
       

 06-02-2011
7.00
Fabricated aileron torque tubes
Details
       

 06-01-2011
9.00
Installed stall warning switch and acces plate
Details
       

 05-31-2011
3.00
Tested Left Fuel Tank for Leaks
Details
     

 05-31-2011
3.00
Installed Fuel Sender in Left Tank
Details
       

 05-29-2011
4.00
Installed Right Door Window
Details

 05-26-2011
8.00
Finished trim on glass in Left Door
Details
       

 05-24-2011
6.00
Fabricated Rudder Pulley Assembly
Details
       

 05-23-2011
12.00
Installed glass in left door
Details
       

 05-18-2011
6.00
Began final fitting and prep of door windows
Details
       

 05-17-2011
2.00
Installed Heat selector boxes
Details
     

 05-16-2011
6.00
Assembled Oil Cooler Bracket
Details
     

 05-12-2011
4.00
Installed Fibrefrax ceramic insulation
Details
       

 05-11-2011
6.00
Installed overhead vents and pnuematic strut brack
Details
       

 05-10-2011
6.00
Re-installed latch system on doors
Details
     

 05-09-2011
10.00
Completed Paint on Overhead
Details
       

 05-05-2011
60.00
Finished Painting the Inside of Doors
Details
       

 05-03-2011
28.00
Finished Primer on outside of doors
Details
       

 05-02-2011
6.00
Skim coated and filled outside left and right door
Details
       

 04-25-2011
60.00
Completed primer of door inside panels
Details
       

 04-23-2011
4.00
Applied primer to inside of Cabin Cover
Details
       

 04-20-2011
32.00
Continued with Overhead Console Paint Prep
Details
       

 04-19-2011
9.00
Began installation of Overhead console
Details
       

 04-15-2011
30.00
Finished fitting the Door Seal
Details
       

 04-08-2011
45.00
Continued finishing the cabin cover
Details
       

 04-03-2011
10.00
Completed left door latch and installed
Details
       

 04-02-2011
2.00
Added locking clip to right door latch
Details
     

 03-28-2011
9.00
Trimmed left and right door windows
Details
       

 03-25-2011
8.00
Fabricated hinge cover for both doors
Details
       

 03-24-2011
7.00
Began Trimming doors
Details
     

 03-22-2011
8.00
Bonded Left Door Skins
Details
       

 03-21-2011
8.00
Prep'd left door for installation of Center Latch
Details
     

 03-18-2011
4.00
Completed Right Door installation of latch
Details
     

 03-17-2011
4.00
Continued installation of center latch
Details

 03-16-2011
12.00
Began installation of center latch
Details
       

 03-15-2011
4.00
Installed door latch in right door
Details
       

 03-11-2011
4.00
Installed right door hinge half
Details
       

 03-11-2011
10.00
Finished Right door trimming
Details
       

 03-10-2011
4.00
Assembled Door Latches
Details
       

 03-09-2011
12.00
Trimmed doors and match drilled
Details
       

 03-08-2011
10.00
Installed Cabin top
Details
       

 03-07-2011
10.00
Installed center brace and support bracket
Details
       

 03-05-2011
6.00
Completed final drilling of all attaching holes
Details
       

 03-04-2011
9.00
Installed Cabin Cover and Match Drilled
Details
       

 03-03-2011
11.00
Reinstalled Upper Fuse Comm Antenna
Details
       

 03-01-2011
6.00
Sanding and Fitting door openings
Details
       

 02-28-2011
12.00
Continued Sanding Cabin Cover
Details

 02-25-2011
6.00
Installed Transponder and Comm antenna
Details
       

 02-25-2011
3.00
Assembled Mid-seat Rail Support
Details
       

 02-17-2011
10.00
Finalized fitting of Cabin cover to Fuselage
Details
       

 02-16-2011
14.00
Continued Trimming Cabin Cover
Details

 02-15-2011
10.00
Continued work on Cabin Cover installation
Details
       

 02-14-2011
10.00
Began fitting of Cabin Cover
Details

 02-13-2011
4.00
Fuel Line Re-Do
Details
       

 02-10-2011
5.00
Installed Rear NACA Ducts
Details
       

 02-09-2011
12.00
Completed Rear Seat Backs
Details
       

 02-08-2011
12.00
Completed Section 40 Flaps Installation
Details
       

 02-08-2011
3.00
Began construction of rear seat backs
Details
       

 02-07-2011
4.00
Partlially completed Flap torque tube installation
Details
     

 02-06-2011
7.00
Began flap system assembly
Details
       

 02-05-2011
6.00
Finished Installation of controls
Details
       

 02-04-2011
4.00
Completed installation of pedals and brake lines
Details
       

 02-04-2011
5.00
Completed Brake Line and Brake Reservoir Installat
Details
     

 02-04-2011
5.00
Assembled and installed control stick base
Details
       

 02-03-2011
14.00
Fabricated remaining pushrods for Aileron
Details
       

 02-02-2011
6.00
Installed Rudder Cable Fairings
Details
       

 02-02-2011
2.00
Fabricated Elevator Pushrod
Details

 02-01-2011
7.00
Routed left and right rudder cables through fuse
Details
       

 01-31-2011
7.00
Installed Matco Parking Brake
Details
       

 01-30-2011
2.00
Installed Safair1 Static Ports
Details
       

 01-29-2011
6.00
Attached Brake Assemblies to WD1006
Details
     

 01-28-2011
14.00
Primed remaining panels and covers, painted rudder
Details

 01-28-2011
4.00
Assembled Brake Pedals
Details

 01-27-2011
18.00
Fabricated inspection panel
Details
       

 01-26-2011
1.00
My old flight instructors visit
Details
       

 01-24-2011
18.00
Fabricated Lines and Installed Fuel System
Details
       

 01-23-2011
10.00
Fabricated and installed brake lines
Details
       

 01-12-2011
3.00
Cut out Rear NACA vent slots

 01-11-2011
7.00
Completed Tunnel Covers
Details
       

 01-10-2011
6.00
Installed Px seat floors
Details
       

 01-10-2011
4.00
Final Riveted the PAX seat bottom
Details
     

 01-08-2011
2.00
Installed Left Baggage cover to Fuse
Details
     

 01-07-2011
7.00
Installed completed baggage door to fuselage
Details
       

 01-07-2011
5.00
Completed baggage door
Details
       

 01-06-2011
6.00
Ran additional conduit through baggage floor
Details
       

 01-05-2011
6.00
Painted baggage door hardware
     

 01-04-2011
6.00
Completed initial assy of baggage door
Details
       

 01-04-2011
1.00
Completed Baggage Bulkead Assy

 01-03-2011
12.00
Completed Baggage Close-Out
Details
       

 01-02-2011
6.00
Installed right baggage cover to fuse
Details
       

 12-31-2010
17.00
Riveted Baggage floor to fuse
Details
       

 12-30-2010
8.00
Modified right baggage floor for inspection cover
Details
     

 12-29-2010
10.00
Fabricated comm antenna doubler and installed
Details
     

 12-28-2010
16.00
Assembled Baggage Door Frame
Details

 12-27-2010
8.00
Installed Insulation and ran conduit
Details
       

 12-27-2010
4.00
Assembled Baggage Door
Details
       

 12-23-2010
14.00
Prepared Baggage Floor Panels for Installation
Details
       

 12-21-2010
15.00
Continued riveting the fuse to the tailcone
       

 12-20-2010
12.00
Began Riveting of Fuse to Tailcone
Details
       

 12-19-2010
17.00
Re-Attached Fuse
Details
     

 12-18-2010
14.00
Finished Prime of Fuse and Floor Panels
Details
       

 12-17-2010
19.00
Built Paint Booth and Primed Fuse
Details
       

 12-16-2010
15.00
Removed Tailcone and prepared for re-attachment
Details

 12-14-2010
12.00
Continued with Tailcon and Fuse Attachment
Details
       

 12-13-2010
10.00
Began attachment of Tailcone to fuse
Details
       

 12-10-2010
18.00
Dis-asembled Fuse QB
Details
       

 12-08-2010
18.00
QB Fuse and Wing Kit Arrived
Details
       

 12-01-2010
30.00
Added an equipment shelf in tail cone
Details
       

 11-30-2010
40.00
Completed Vertical and Elevator Fairing glass work
Details
       

 11-26-2010
12.00
Glassed in upper rudder fairing
Details
       

 11-11-2010
5.00
Installed Nut Plates on lower Rudder Fairing
Details
       

 11-05-2010
3.00
Closed Horizontal Stab tip fairing left side
Details

 11-03-2010
4.00
Continued Glassing the Horiz. tip fairings
Details
       

 10-29-2010
2.00
Closed the Hor. Stab Fairing
Details
     

 10-28-2010
5.00
Fiberglass fairings
Details
       

 10-25-2010
4.00
Inspection
Details

 10-25-2010
14.00
Attached Rudder
       

 10-25-2010
16.00
Attached Elevator and Rudder tip Fairings
Details
       

 10-23-2010
4.00
Attached Vert. Stab to Tail Cone
Details
       

 10-22-2010
10.00
Fabricated four shims, attached and aligned elevat
Details
       

 10-21-2010
6.50
Match Drill Elevator Horns
Details
       

 10-20-2010
20.00
Installed Elevator on Horizontal Stab
Details
       

 10-19-2010
17.00
Installed both Left and Right Elevators
Details
       