Jacks Web Site
Work Logs Found: 728
Category Work Time: 2689 Hours
 Date
Hours
Work Log Summary

Details

 07-09-2012
3.00
Remounted wheel fairings
Details
       

 07-08-2012
3.00
Finished rear cowl attachment
Details
       

 07-08-2012
4.00
Finished oil fillter door
Details
       

 07-04-2012
3.00
Fitted oil filler door to the upper cowl
Details
       

 07-04-2012
1.00
Fabricated latch open limiters
Details
       

 06-30-2012
2.00
Finished rear fitment of vertical stabilizer fairi
Details
       

 06-30-2012
4.00
Attached vertical stabilizer fairing
Details
       

 06-11-2012
4.00
Fixed clearance between spinner and cowl
Details
       

 05-19-2012
3.00
Radio and electrical checkout
Details
       

 05-13-2012
6.00
Windshield fairing attached
Details
       

 05-12-2012
3.00
Added rudder and elevators
Details
       

 05-10-2012
2.00
Recieved the upholstery
Details
     

 05-07-2012
3.00
Reattached the empanage
Details
     

 05-06-2012
4.00
Attached the wings
Details
       

 05-05-2012
3.00
Moving fuselage out of the shop
Details
       

 04-19-2012
3.00
Canopy closure treatment
Details
       

 04-17-2012
6.00
Cleanup windshield fairing
Details
     

 04-15-2012
3.00
Prep fpor windshield fairing layu
Details
       

 04-15-2012
5.00
Applied glass to the windshield area
Details
       

 04-14-2012
3.00
Initial windshield fairing layup
Details
       

 04-14-2012
3.00
Final clearance check
Details
       

 04-01-2012
4.00
Lay up cowl supports
Details
       

 04-01-2012
5.00
Covers laid up
Details
       

 03-31-2012
4.00
Preparing pin cover molds
Details
       

 03-31-2012
4.00
Cut holes for hinge pin cover.
Details
       

 02-11-2012
2.00
Reattached Cowl to Finish Horizontal Seam
Details
       

 01-22-2012
2.00
Mounted canopy with windshield
Details
       

 01-21-2012
5.00
Mounted windshield
Details
       

 01-15-2012
4.00
Finished canopy details
Details
       

 01-14-2012
4.00
Mounted wing tip lens hardware
Details
       

 01-14-2012
3.00
Finished wings
Details
       

 01-08-2012
2.00
Rivetted rear wing tip ribs
Details
       

 01-07-2012
4.00
Fabricated right wing tip support baffles
Details
     

 01-07-2012
3.00
Cut and trimmed wing tip lenses
Details
       

 01-01-2012
2.00
Fabricated spacers for wing tips
Details
       

 01-01-2012
4.00
Fabricated left wing tip support baffles
Details
       

 12-31-2011
2.00
Secured wing tip hinge pins
Details
     

 12-31-2011
4.00
Rivetted left wing tip hinge to wing tip
Details
       

 12-29-2011
6.00
Rivetted right wing tip hinge to wing tip
Details
       

 12-17-2011
4.00
Mounted wing tip antenna and lights
Details
       

 12-16-2011
2.00
Mounted rear left wing tip rib
Details
     

 12-15-2011
3.00
Drilled holes to mount left wing tip
Details
       

 12-11-2011
4.00
Mounted left wing tip hinges and fitted wing tip
Details
       

 12-10-2011
4.00
Drilled holes to mount right wing tip
Details
       

 12-09-2011
3.00
Fitted right wing tip to wing
Details
       

 12-08-2011
5.00
Mounted wing tip hinges on right wing
Details
       

 12-04-2011
5.00
Rivetted left wing bottom skin
Details
       

 12-04-2011
4.00
Rivetted joint fairing nut plates on left wing
Details
       

 12-03-2011
3.00
Wired left lights, OAT, and antenna
Details
       

 12-03-2011
2.00
Coupled pitot and aoa lines to pitot tube
Details
       

 12-01-2011
3.00
Mounted pitot controller
Details
       

 11-29-2011
3.00
Installed Dynon pitot in left wing
Details
       

 11-26-2011
4.00
Wired right wing lights, antenna, fuel sensor
Details
       

 11-26-2011
5.00
Installed OAT, rivetted lower right wing skin
Details
       

 11-25-2011
4.00
Wired right wing roll servo
Details
       

 11-25-2011
3.00
Wired right wing roll servo
Details
       

 11-25-2011
3.00
Assembled fuel pump and sticks
Details
       

 11-24-2011
8.00
Assembled canopy
Details
       

 11-22-2011
2.00
Built wheel rollers
Details
     

 11-20-2011
2.00
Tested avionics
Details
       

 11-19-2011
4.00
Rivetted cabin top skin
Details
       

 11-06-2011
4.00
Painted canopy parts
Details
     

 11-05-2011
3.00
Installled handles on canopy bar
Details
       

 10-31-2011
6.00
Installed new brake lines
Details
       

 10-30-2011
3.00
Finished cable firewall feedthroughs
Details
       

 10-30-2011
2.00
Fabricated passenger side vent panel
Details
       

 10-29-2011
3.00
Wired compass and cabin lights
Details
       

 10-23-2011
3.00
Mounted compass to center strut
Details
       

 10-22-2011
4.00
Tested windshield fit
Details
       

 10-20-2011
6.00
Rivetted brackets on cabin top skin
Details
     

 10-16-2011
3.00
Secured brake lines
Details
       

 10-13-2011
4.00
Installed remaining engine control cables
Details
       

 10-11-2011
2.00
Installed throttle control
Details
       

 10-09-2011
3.00
Installed engine control cables
Details
       

 10-08-2011
3.00
Installed cooling vents
Details
       

 10-06-2011
1.00
Installed oil vent control cable
Details
     

 10-06-2011
3.00
Finished air vent control installation
Details
       

 10-02-2011
1.00
Installed forward center cover
Details
     

 10-02-2011
3.00
Installed antenna leads
Details
       

 10-02-2011
1.00
Installed air vents
Details
       

 10-02-2011
2.00
Completed ignition system wiring
Details
     

 09-29-2011
2.00
Buttoned up flap mechanism
Details
       

 09-25-2011
6.00
Wired up control sticks
Details
       

 09-24-2011
6.00
Installed GTX-327 Transponder
Details
       

 09-23-2011
1.00
First lesson for Kay
Details
     

 09-22-2011
3.00
Tested the GNS-430
Details
     

 09-21-2011
3.00
Tested SL-30
Details
     

 09-20-2011
3.00
Powered up GMA 340 Audio panel
Details

 09-19-2011
4.00
Build roller carts for wheels
Details
     

 09-17-2011
5.00
GPSMAP-696 Testing
Details

 09-15-2011
3.00
Powered up Skyview systems
Details

 09-12-2011
3.00
Wired status lights
Details
     

 09-11-2011
4.00
Wired ignition modules
Details
       

 09-10-2011
6.00
Finsih assembled intstrument panel
Details
       

 09-08-2011
3.00
Sprayed clear coad
Details
       

 09-07-2011
6.00
Decalled main panel
Details
       

 09-06-2011
3.00
Started decaling panels
Details
       

 09-05-2011
4.00
Mounted antenna diplexer
Details
       

 09-04-2011
8.00
Rewired stick controls
Details
       

 09-03-2011
6.00
Ran antennal wires
Details
       

 09-02-2011
3.00
Plumbed manifold pressure lines
Details
       

 08-28-2011
5.00
Mounted ELT antenna bracket
Details
     

 08-27-2011
5.00
Finsh mounted GPS antenna shelf
Details
       

 08-26-2011
4.00
Mounted avionics fan
Details
     

 08-25-2011
4.00
Mounted center harnes point brackets
Details
       

 08-22-2011
4.00
Wired rudder strobe
Details
       

 08-21-2011
6.00
Painted parts
Details
     

 08-20-2011
4.00
Removed front panal for finishing
Details
       

 08-19-2011
6.00
Fabricated mounting for avionics fan
Details
       

 08-18-2011
7.00
Fabricated backing plates for shelf
Details
       

 08-17-2011
4.00
Fabricated ELT antenna mount
Details
     

 08-13-2011
8.00
Added GPS Antenna shelf on the firewall
Details
       

 08-07-2011
4.00
Powered up lights and Skyview system
Details
     

 08-06-2011
6.00
Wired headsets
Details
     

 08-05-2011
7.00
Wired front panel controls
Details
       

 08-03-2011
5.00
Mounted COM antennas
Details
       

 08-02-2011
3.00
Mounted GNS 430 GPS antenna
Details
     

 07-23-2011
4.00
Finish wired GPSMAP 696
Details
       

 07-16-2011
6.00
Finished wiring Skyview 700
Details
       

 07-07-2011
4.00
Prepare for front panel wiring
Details
       

 07-02-2011
4.00
Complete fuse block wiring
Details
       

 06-18-2011
3.00
Wire Skynet bus connector
Details
       

 06-04-2011
6.00
Wire main Skyview connector
Details
       

 05-31-2011
6.00
Finish wirng fuse blocks
Details
     

 05-29-2011
0.50
My favorite birds visit me
Details
     

 05-28-2011
6.00
Laced front panel wiring
Details
       

 05-21-2011
6.00
Initial finish wiring fuse blocks
Details
     

 05-14-2011
6.00
Finish wired heat sinks
Details
       

 05-07-2011
8.00
Finish wired dimmer modules
Details
     

 04-23-2011
7.00
Finish wired EMS module
Details
       

 04-16-2011
8.00
Prepare for finish wiring
Details
       

 04-10-2011
6.00
Assembled Fuseholder shelf
Details
       

 04-09-2011
6.00
Routing wires and lacing
Details
       

 04-05-2011
4.00
Laced wiring
Details
     

 04-04-2011
4.00
Mounted heat sinks and lighting controllers
Details
     

 04-03-2011
6.00
Completed Secondary Regulator wiring
Details
       

 04-02-2011
8.00
Completed Ignition Wiring
Details
       

 03-29-2011
5.00
Completed firewall wiring
Details
       

 03-28-2011
6.00
Mounted Skyview Modules and Ignition
Details
       

 03-27-2011
6.00
Final assembly firewall penetrations
Details
       

 03-26-2011
7.00
Final assembly for mountings
Details
       

 03-25-2011
5.00
Parts final assembly
Details
       

 03-22-2011
4.00
Painted parts
Details
       

 03-06-2011
8.00
Fabricated ignition battery box
Details
       

 03-05-2011
8.00
Mounted Fuel Flow Sensor
Details
       

 02-27-2011
2.00
Secured fuel line
Details
       

 02-27-2011
6.00
Fabricated firewall penetrations
Details
       

 02-26-2011
6.00
Finished firewall wiring
Details
     

 02-12-2011
3.00
Finished up power cable runs
Details
       

 02-06-2011
6.00
Power Cable runs
Details

 02-05-2011
8.00
Terminated Power Cables
Details

 01-15-2011
8.00
Mounting Firewall Components
Details

 01-08-2011
7.00
Ran ground wires
Details
     

 01-01-2011
6.00
Wired ARINC-429 Module connector
Details
       

 12-19-2010
8.00
Wired Network to Modules
Details
     

 12-18-2010
5.00
Wire runs to the panel
Details
       

 12-11-2010
8.00
Lacing cables
Details
       

 12-04-2010
10.00
Rewiring Fuselage
Details

 11-28-2010
6.00
Reworked Autopilot Trim Servo
Details
       

 11-27-2010
8.00
Wired and Mounted ADAHRS Platform
Details
       

 11-26-2010
15.00
Reworked the fuselage wiring
Details

 11-25-2010
6.00
Fitted Main Control Cables
Details
       

 11-24-2010
2.00
Preparing Skyview Network Junctions
Details
     

 11-23-2010
2.00
Preparing Skyview Network Junctions
Details
       

 11-22-2010
6.00
Preparing Skyview Network Junctions
Details
       

 11-21-2010
8.00
Mounted auxilary control cables
Details
     

 11-14-2010
7.00
Installed Parking Brake
Details
       

 11-10-2010
0.75
Assembled Regulator Mounting Plate
Details
     

 11-09-2010
2.00
Second Bulkhead Mountings Assembly
Details
       

 11-09-2010
1.00
GPS 696 Mounting
Details
       

 11-09-2010
2.00
Front Panel Mounting Assembly
Details
       

 11-08-2010
1.00
Component Mountings Final Assembly
Details
       

 11-07-2010
8.00
Spray parts
Details
       

 11-06-2010
9.00
Parts preparation
Details
     

 10-31-2010
8.00
Front panel switch mounting
Details
       

 10-30-2010
8.00
Mounted Panel Switches
Details
       

 10-25-2010
10.00
Mounted ADAHRS Modules
Details
       

 10-23-2010
6.00
Mounted the secodary alternator regulator
Details
       

 10-09-2010
5.00
Mounted Firewall Componenets
Details
       

 10-08-2010
8.00
Completed mounting of bulkhead components
Details
       

 10-02-2010
6.00
Mounted dimmer controls and heat sink
Details
       

 09-27-2010
2.00
Cut holes for Skyview USB ports
Details
       

 09-25-2010
7.00
Refined 696 mounting.
Details
       

 09-23-2010
5.00
Mounted GPSMAP-696
Details
       

 09-19-2010
4.00
Assembled bulkhead and panel to top skin
Details
       

 09-18-2010
6.00
Mounted backup battery and relays
Details
       

 09-11-2010
8.00
Mounted Skyview Modules
Details
       

 09-05-2010
8.00
Built Fuse Panel Under Pilot Panel
Details
       

 08-29-2010
8.00
Prepared wiring harness for Garmin stack
Details
     

 08-22-2010
20.00
Created Skyview Schematic
Details
     

 08-15-2010
20.00
Prepared Avionics Schematics
Details
     

 08-07-2010
6.00
Fitted Garmin stack to second bulkhead
Details
       

 07-25-2010
10.00
Mounted SV-D700
Details
     

 07-24-2010
5.00
Cut hole for GPSMAP-696
Details
     

 07-22-2010
4.00
Prepared instrument side panels
Details
       

 07-20-2010
3.00
Measuring up Garmin components
Details
       

 07-19-2010
3.00
Cut hole for Garmin stack
Details
       

 07-18-2010
3.00
Cut hole for the SV-D1000
Details
     

 07-17-2010
3.00
Marked panel for major cuts
Details
     

 07-17-2010
5.00
Layout Instrument Panel
Details
     

 07-10-2010
20.00
Design Instrument Panel
Details
     

 06-26-2010
4.00
Routed ignition leads
Details
       

 06-26-2010
1.00
Planning fuel flow sensor installation
Details
       

 06-26-2010
3.00
Built desecant holders for exhaust systems
Details
     

 06-14-2010
3.00
Installed right EFIS backup battery
Details
       

 06-13-2010
7.00
Attached ignition system rails
Details
       

 06-12-2010
3.00
Mounted ignition systems to rails
Details
     

 06-07-2010
3.00
Sniffle valve install
Details
       

 06-06-2010
4.00
Reattached prop. Spinner cutout layup
Details
       

 06-05-2010
5.00
Finished ignition system install and test
Details
     

 06-05-2010
2.00
Final assembly of skybolt assembly
Details
     

 06-04-2010
1.00
Received Dynon gear
Details

 05-31-2010
3.00
Finished lower baffle attachment
       

 05-31-2010
6.00
Final assembly for baffles
Details
       

 05-30-2010
9.00
Finsh paint baffle parts
Details
     

 05-29-2010
9.00
Primed baffle parts
Details
     

 05-29-2010
4.00
Prepared parts for priming
Details
     

 05-28-2010
4.00
Made plug hole covers
Details
 

 05-27-2010
3.00
Fabricated fin extensions for cylinder cooling
Details
       

 05-23-2010
1.00
Removed baffles for painting
Details

 05-22-2010
6.00
Finished lower ignition system installation
Details
       

 05-21-2010
2.00
Sanded snorkel and fitted flanges
Details
       

 05-18-2010
1.00
Final layup on snorkel
Details
     

 05-16-2010
4.00
Installed alternator cooling hose
Details
       

 05-15-2010
5.00
Installed cabin heat hoses
Details
       

 05-14-2010
1.00
Ignition coil fitting
Details

 05-09-2010
7.00
Mounted 2nd set of ignition coils
Details
       

 05-09-2010
2.00
Fuel injection system hookup
Details

 05-08-2010
1.00
Drilled holes for ignition wires
Details
     

 05-02-2010
8.00
Installed 1st set of ignition coils
Details
       

 05-01-2010
2.00
Finish baffle cleanup
Details
       

 05-01-2010
2.00
Added oil cooler shutter
       

 04-25-2010
3.00
Final fitting of snorkel flange
Details

 04-25-2010
7.00
Adjusted the height of the baffles
Details

 04-23-2010
2.00
Cutting snorkel flange
Details

 04-18-2010
6.00
Fitted oil filter to baffles
Details
       

 04-03-2010
3.00
Fitted upper cowl
Details
       

 04-02-2010
2.00
Garmin equipment arrived
Details
       

 03-06-2010
2.00
Snorkel sanded
Details
       

 03-06-2010
2.00
Snorkel fitting
Details
       

 03-05-2010
2.00
Snorkel second layup.
Details
       

 02-28-2010
2.00
Preparing snorkel transition form and first layup
Details
       

 02-28-2010
3.00
Making transition form
Details
       

 02-28-2010
2.00
Further measurements for snorkel fit
Details
       

 02-28-2010
2.00
First cut not good
Details
       

 02-27-2010
2.00
Worked on left inlet baffles
Details
       

 02-27-2010
4.00
Preparing for snorkel attachment
Details
       

 02-27-2010
3.00
First cut to shrink snorkel
Details
       

 02-27-2010
2.00
Baffle mounting brackets
Details
       

 02-14-2010
3.00
Inlet snorkel attachment
Details
       

 02-13-2010
5.00
Engine baffle kit
Details
       

 02-13-2010
2.00
Attached inlet fairings
Details
     

 02-07-2010
4.00
Miscellaneous work
Details
       

 02-06-2010
4.00
Rivetting and gluing the top hinges
Details
       

 02-06-2010
2.00
Prepared top cowl for Sky Bolts
Details
       

 02-06-2010
3.00
Prepared flanges for Sky Bolts
Details
       

 02-01-2010
2.00
Upper horizontal cowl hinge views
Details
       

 02-01-2010
4.00
Spacing the cowl halves
Details
       

 02-01-2010
2.00
Drilled holes for hinge pins
Details
       

 01-31-2010
4.00
Lower hnge attachment
Details
       

 01-31-2010
3.00
Horizontal cowl hinge after drilling
Details
       

 01-31-2010
4.00
Clamping horizontal hinges to cowl
Details
       

 01-31-2010
3.00
Attaching rear edge hinges to cowl
Details
       

 01-30-2010
7.00
Adjusting lower cowl fit
Details
       

 01-25-2010
2.00
Trimming the top edges
Details
       

 01-25-2010
2.00
Drilling side hinges for the cowl
Details
       

 01-24-2010
3.00
Shimming the sides of the cowl
Details
       

 01-24-2010
3.00
Setting the side cowl hinge pins
Details
       

 01-24-2010
3.00
Installing bottom cowl hinges
Details
       

 01-23-2010
3.00
Drilling holes for Sky Bolts
Details
       

 01-23-2010
4.00
Cutting back edge of bottom cowl
Details
       

 01-18-2010
3.00
Finishing top cowl flanges
Details
       

 01-18-2010
6.00
Cutting top cowl to length
Details
       

 01-17-2010
6.00
Start Sky Bolt installation
Details
       

 01-02-2010
5.00
Adjusting cowl fit
Details
       

 01-01-2010
4.00
Initial cowl fitting
Details
       

 12-20-2009
3.00
Spinner fillin plates added
Details
       

 12-20-2009
1.00
Lower canopy fitted
Details
       

 12-19-2009
4.00
Spinner attached
Details
       

 12-19-2009
4.00
Propeller mounted to the engine
Details
       

 12-16-2009
1.00
Propeller arrives
Details
       

 11-03-2009
0.50
Fitted top cowl
Details
       

 11-03-2009
1.50
Fitted cabin heat muff to exhaust
Details
       

 11-03-2009
1.00
Attached tail pipe support
Details
       

 11-02-2009
3.00
Attached exhaust system
Details
       

 11-01-2009
2.00
Ran fuel line to injector intake
Details
       

 11-01-2009
0.50
Mounted throttle cable
Details
     

 11-01-2009
0.50
Mounted oil pressure transducer hose
Details
     

 11-01-2009
2.00
Mounted fuel pump overflow line
Details
     

 11-01-2009
1.00
Mounted alternator
Details
     

 11-01-2009
1.00
Added firewall to pump fuel line
Details
     

 10-31-2009
3.00
Mounted firewall components and engine mount
Details
       

 10-31-2009
3.00
Mounted engine
Details
       

 10-31-2009
0.50
Engine on fuselage
Details
       

 10-29-2009
3.00
Relieved main wheel clearance
Details
       

 10-27-2009
3.00
Nose fairing assembly
Details
       

 10-26-2009
2.00
Finish assembly of main gear
Details
     

 10-25-2009
5.00
Painted parts
Details
     

 10-24-2009
5.00
Mounted prop governor to engine
Details
       

 03-07-2009
3.00
Fabricated ELT antenna backing plate
Details
       

 03-05-2009
2.00
Mounted wing root connectors
Details
       

 03-01-2009
2.00
Finished wiring barriers
Details
     

 02-28-2009
5.00
Canted grips 15 degrees
Details
       

 02-14-2009
3.00
Finished wiring grips into barrier strip
Details
       

 02-13-2009
3.00
Ran grip wires to barrier strips
Details
       

 02-12-2009
3.00
Wired pilot grip
Details
       

 02-11-2009
1.00
Routed copilot grip wires to barrier strip
Details
     

 02-10-2009
3.00
Mounted base assembly
Details
       

 02-08-2009
4.00
Prepare base wiring
Details
       

 02-07-2009
3.00
Assembled base connector
Details
       

 02-06-2009
3.00
Prepared copilot stick base
Details
       

 02-05-2009
3.00
Brazed pins into copilot stick
Details
       

 02-04-2009
2.00
Prepared copilot stick mounting
Details
       

 01-31-2009
4.00
Wired and mounted copilot grip
Details
       

 01-30-2009
3.00
Laced wires for copilot grip connector
Details
       

 01-29-2009
3.00
Continued connector assembly
Details
       

 01-28-2009
2.00
Started copilot grip connector wiring
Details
       

 01-27-2009
1.00
Prepared joystick grips
Details
     

 01-26-2009
3.00
Added braces to ELT panel, ran wires
Details
       

 01-25-2009
7.00
Ran wires, mounted barrier strip panel
Details
       

 01-24-2009
5.00
Mounted ELT in fuselage
Details
       

 01-23-2009
3.00
Mounted and wired ELT.
Details
       

 01-19-2009
3.00
Laced wires running to fuselage tail
Details
       

 01-18-2009
5.00
Finished elevator autopilot servo install
Details
       

 01-17-2009
7.00
Final assembly of flap position sensor
Details
       

 01-12-2009
5.00
Primed aluminum parts
Details
     

 01-11-2009
3.00
Assembled barrier strip panel
Details
       

 01-10-2009
9.00
Wired flap controls and relays
Details
       

 01-09-2009
3.00
Wired elevator autopilot servo
Details
       

 01-08-2009
3.00
Mounted trim lockout relays
Details
       

 01-06-2009
4.00
Wired trim lockout relays
Details
       

 01-05-2009
2.00
Spliced cable to elevator trim servo
Details
     

 01-04-2009
2.00
Routed static pressure line
Details
     

 01-03-2009
3.00
Mounted barrier strip for flap control
Details
       

 12-31-2008
4.00
Installed trim servo relay decks
Details
       

 12-30-2008
3.00
Started servo relay deck wiring
Details
     

 12-27-2008
3.00
Finished installing flap position transducer
Details
       

 12-21-2008
4.00
Mounted Flap Position Transducer
Details
       

 12-20-2008
8.00
Build magnetometer mount
Details
       

 12-19-2008
2.00
Mounted Elevator Servo
Details
       

 12-18-2008
1.00
Mounted Strobe Power Supply
Details
       

 12-07-2008
7.00
Assembled canopy handle
Details
       

 12-06-2008
5.00
Drilled and tapped holes for windscreen
Details
       

 06-22-2008
5.00
Drilled and countersunk canopy holes
Details
       

 05-26-2008
8.00
Adjusted canopy fit to frame
Details
       

 05-25-2008
6.00
Fitted windscreen to frame
Details
       

 05-24-2008
8.00
Fitted windscreen to frame
Details
       

 05-17-2008
9.00
Drilled attachment holes through canopy
Details
       

 05-11-2008
5.00
Cut forward windscreen from canopy
Details
       

 02-13-2008
3.00
Fitted canopy frame to canopy
Details
       

 02-12-2008
4.00
Finished canopy stand.
Details
       

 02-10-2008
6.00
Built stand for cutting canopy
Details
       

 02-09-2008
5.00
Mount rear sliding rail
Details
       

 02-09-2008
4.00
Finished canopy frame alignment
Details
       

 02-08-2008
3.00
Started canopy frame alignment
Details
       

 01-12-2008
6.00
Mounted forward canopy frame
Details
       

 01-12-2008
5.00
Mounted forward brace. Started canopy frame
Details
       

 01-06-2008
4.00
Finished wing root fairings
Details
       

 11-22-2007
2.00
Attached left wing root fairing
Details

 11-12-2007
2.00
Attached aileron pushrods
Details

 11-11-2007
7.00
Drilled incidence holes, set tank brackets
Details
       

 11-10-2007
7.00
Mounted wings, trimmed flaps, set incidence
Details
       

 11-09-2007
1.00
Fineished wing horses
Details
     

 11-08-2007
3.00
Started wing horses
Details
       

 11-06-2007
1.00
Reattached top front cabin
Details
       

 11-05-2007
2.00
Finished brakes
Details

 11-04-2007
5.00
Assembled NACA vents, rudder fairings, brakes
Details
       

 11-03-2007
10.00
Reassembled fuel pump, flaps, empenagge
Details
     

 11-02-2007
1.00
Riveted flap hinges
Details
     

 11-01-2007
6.00
Finished riveting inside bottom wing skins
Details
       

 10-31-2007
2.00
Clean up, move fuselage to hangar.
Details
     

 10-30-2007
4.00
Spray cabin interior
Details
       

 10-29-2007
2.00
Prep cabin interior
Details

 10-25-2007
2.50
Rivet inside right lower wing skin
Details

 10-24-2007
5.00
Spray interior parts - finish kit arrives
Details
     

 10-23-2007
2.00
Prep interior parts
Details

 10-22-2007
2.50
Spray finish on interior parts
Details

 10-17-2007
4.00
Assemble pitot to wing, rivet lower interior skin
Details
       

 10-15-2007
3.00
Prime pitot parts
Details

 10-14-2007
6.00
Mounted pitot on left wing
Details
       

 10-14-2007
2.00
Cut pitot hole in skin
Details
       

 10-11-2007
1.50
Primed test sheets
Details

 10-11-2007
2.00
Masked cabin interior
Details
       

 10-10-2007
1.00
Prep test sheets
Details

 10-09-2007
2.00
Spray primer on riveted parts
Details
       

 10-07-2007
6.00
Prep parts, rivet rear skin to skin
Details
       

 10-04-2007
4.00
Final assembly, painted parts
Details
     

 10-01-2007
1.50
Small assembly, nutplates and pushrods
Details

 09-30-2007
6.00
Primed parts
Details
       

 09-29-2007
9.00
Scrubbed, etched, and alodined parts
Details

 09-28-2007
2.00
Remove empennage to prime parts
Details

 09-27-2007
2.00
Install wiring conduit in the tail
Details
       

 09-20-2007
3.00
Fitted rudder fairings
Details
       

 09-19-2007
2.00
Fiberglassed rudder fairings
Details

 09-18-2007
3.00
Made rudder fairing mold
Details
       

 09-17-2007
2.00
Fitted rudder stops
Details
       

 09-15-2007
2.00
Riveted nutplates for access hole
Details
     

 09-15-2007
5.00
Mounted vert stab tip, drilled rudder tip
Details
       

 09-14-2007
3.00
Prepared elevator tips for mounting
Details
       

 09-13-2007
2.50
Installed strobe/elt mounting brackets
Details
       

 09-11-2007
2.50
Fiberglassed horizontal stabilizer tip ends
Details
       

 09-10-2007
2.00
Installed electric elevator trim assembly
Details
       

 09-09-2007
3.00
Installed NACA ducts for ventilation
Details
       

 09-08-2007
3.00
Installed NACA ducts for ventilation
Details
       

 09-07-2007
1.00
Worked on horizontal stabilizer tips
Details
     

 09-06-2007
2.00
Worked on horizontal stabilizer tips
Details
     

 09-04-2007
2.00
Worked on horizontal stabilizer tips
Details
       

 09-03-2007
8.00
Finished rudder light install, started elevator ti
Details
       

 09-02-2007
6.00
Worked on elevator tips
Details
       

 09-01-2007
3.00
Fitted lower rudder tip
Details
       

 08-31-2007
2.00
Cut hole in rudder for tail light
Details
     

 08-28-2007
3.00
Install flap position system, static ports.
Details
       

 08-27-2007
3.00
Finished tank selector, fuel pump install
Details
       

 08-26-2007
5.00
Fuel pump, ridgid brake lines, rudder cables
Details
       

 08-25-2007
6.00
Worked on fuel pump
Details
       

 08-24-2007
3.00
Installed fuel tank vent lines
Details
       

 08-21-2007
3.00
Installed left landing gear mount, right fuel line
Details

 08-20-2007
2.00
Installed the right landing gear mount
Details

 08-16-2007
3.00
Finished aileron trim installation
Details
       

 08-14-2007
3.00
Finished elevator pushrod and aileron trim
Details
       

 08-13-2007
1.50
Built control pushrods
Details
       

 08-12-2007
7.00
Assembled front top cabin
Details
       

 08-11-2007
5.00
Assembled front top cabin
Details
       

 08-05-2007
5.00
Finished vertical stabilizer, attach rudder
Details
       

 08-03-2007
3.50
Assembled vertival stabilizer
Details
       

 07-29-2007
6.00
Built main elevator control rod
Details
       

 07-22-2007
4.00
Attached horizontal stabilizer
Details
       

 07-21-2007
5.00
Assembled elevators to horizontal stab
Details
     

 07-19-2007
3.00
Seat back final assembly
Details
       

 07-17-2007
2.50
Fuselage assembly
Details
     

 07-16-2007
1.00
Aft Seat floor assembly
Details
       

 07-15-2007
7.00
Started final assembly
Details
       

 07-14-2007
10.00
Primed fuselage parts
Details
       

 07-13-2007
4.00
Alodined parts
Details
       

 07-12-2007
2.00
Done scrubbing parts
Details
     

 07-11-2007
1.00
Finish floor box assembly
Details
       

 07-10-2007
2.00
Floor box assembly
Details

 07-08-2007
6.00
Continue floor box assembly
Details
     

 07-05-2007
2.00
Start floor box assembly
Details

 06-23-2007
7.00
Dimple, deburr, and scrub parts
Details

 06-21-2007
3.00
Deburr parts
Details

 05-13-2007
5.00
Deburr parts
Details
     

 05-12-2007
2.00
Forward covers
Details
       

 05-12-2007
6.00
Electric flaps
Details
       

 05-11-2007
3.50
Assemble seat backs
Details
       

 05-10-2007
1.50
Assemble seat backs
Details
       

 05-06-2007
4.00
Seat backs
Details

 05-05-2007
2.50
Forward set floors and control rod tunnel
Details

 05-03-2007
3.00
Attach seat adjusters to aft seat floors
Details
       

 05-02-2007
5.00
Finished baggage compartment
Details
       

 04-27-2007
3.50
Drilled top skins and riveted baggage floor
Details
       

 04-26-2007
3.00
Gussets, elevator bell crank, rear top skin
Details
       

 04-25-2007
2.00
Installed side rails and gussets
Details
       

 04-24-2007
3.00
Attach aft deck
Details
       

 04-22-2007
2.50
Finished riveting, turned canoe over
Details
       

 04-21-2007
16.00
Riveted round 4
Details

 04-20-2007
6.00
Riveted round 3
Details
     

 04-19-2007
6.00
Riveted round 2
Details
       

 04-17-2007
5.00
Riveted round 1
Details
       

 04-15-2007
5.00
Clecoed fuselage
Details
     

 04-14-2007
5.00
Started assembly
Details
       

 04-13-2007
12.00
Finished alodine, primed all parts
Details
       

 04-12-2007
4.00
Scrubbed/alodined parts
Details
     

 04-08-2007
8.00
Deburr aft fuse, longerons, ready for paint prep
Details
     

 04-07-2007
10.00
Deburr, dimple skins
Details
       

 03-31-2007
8.00
Deburr, dimple parts
Details
     

 03-29-2007
2.50
Deburr, dimple parts
Details
       

 03-27-2007
2.00
Cleanup and disassemble fuselage
Details
       

 03-26-2007
2.00
Match drill skins
Details
     

 03-25-2007
7.00
Finished up step installation
Details
       

 03-24-2007
10.00
Finished brake assembly intall
Details
       

 03-23-2007
1.50
Completed brake pedal assembly
Details
       

 03-22-2007
3.00
Started brake pedal assembly
Details

 03-21-2007
1.00
Fabricated brake pedal angles
Details

 03-20-2007
3.50
Deburred brake pedals
Details

 03-19-2007
1.50
Worked on forward fuselage
Details
     

 03-18-2007
3.00
Worked on forward bulkheads
Details
       

 03-17-2007
7.00
Fit and drilled auxiliary longerons
Details
       

 03-15-2007
3.00
Cut holes for landing gear brackets
       

 03-11-2007
7.00
Finished working side skins
Details
       

 03-08-2007
2.00
Bent side skin to fit rear section
Details
     

 03-04-2007
8.00
Riveted the bottom skin onto the center section
Details
       

 03-03-2007
8.00
Rivetted center section skeleton
Details
       

 02-14-2007
5.50
Completed aft fuselage riveting
Details

 02-13-2007
3.50
Started riveting aft fuselage
Details

 02-12-2007
2.00
Clecoed aft fuselage for final assembly
Details
     

 02-11-2007
11.00
Primed parts
Details
       

 02-10-2007
6.00
Scrubbed and alumidined parts.
     

 02-04-2007
6.00
Finished preping center section parts
Details

 02-03-2007
11.00
Deburr and dimple the center section
Details
     

 02-02-2007
2.00
Disassembled center section.
Details
     

 02-01-2007
2.00
Finished the seat and baggage compartment skins
Details
       

 01-22-2007
3.00
Started the seat and baggage skins
Details
       

 01-21-2007
7.50
Prepared and drilled center section
Details
       

 01-20-2007
6.50
Deburred and dimpled aft fuselage parts
Details
       

 01-19-2007
3.00
Finished the aft fuselage drilling
Details
       

 01-16-2007
2.00
Started drilling the aft fuselage
Details
     

 01-14-2007
7.00
Prepared the aft fuselage assembly
Details
       

 01-13-2007
10.00
Prepared longerons
Details
       

 01-12-2007
4.00
Finished assembling bulkheads
Details
       

 01-11-2007
2.00
Finish F-704 bulkhead
Details
     

 01-10-2007
1.00
Assembled F-704 bulkhead
Details
       

 01-09-2007
1.00
Finished firewall
Details
       

 01-07-2007
5.00
Assembled firewall
Details
       

 01-06-2007
10.00
Scrubbed, alumidyned, and primed parts
Details
       

 01-05-2007
4.00
Finished F-711, F-712 bulkheads
Details
     

 01-04-2007
3.00
Prepared F-710 thru F-711 bulkheads
Details

 01-03-2007
2.50
Prepare F-706, F-707, F708 bulkheads
Details
     

 01-02-2007
4.00
Started F-706 bulkhead
Details
       

 01-01-2007
3.00
Sealed tank
Details

 01-01-2007
5.00
Finished right wing
Details
       

 12-31-2006
7.00
Finished prep of F-705 bulkhead
Details
       

 12-31-2006
3.00
Cut cover plate for wing tank
Details

 12-30-2006
9.00
Prepare F-705 bulkhead
Details
       

 12-27-2006
2.50
Started F-705 bulkhead
Details
       

 12-26-2006
5.00
Assembled F-704 bulkhead
Details
       

 12-25-2006
4.00
Fabricated stiffeners and plates for F-704 bulkhea
Details
     

 12-24-2006
4.00
Finished firewall prep, started center section
Details

 12-23-2006
8.00
Flute ribs, fit & drill firewall parts
Details

 12-23-2006
2.50
Deburr and dimple firewall parts
Details

 12-21-2006
3.00
Ran plastic conduit, worked on tank
Details
       

 12-19-2006
2.00
Attach right flap
Details
       

 12-18-2006
3.00
Attach flap brace, aileron right wing
Details
       

 12-17-2006
5.00
Inventory main boxes
Details
     

 12-16-2006
11.00
Inventory small parts
Details
       

 12-15-2006
4.00
Inventory small parts
Details

 12-14-2006
2.00
Attach aileron brackets and gap fairing
Details
       

 12-13-2006
4.00
Fuselage arrived
Details
       

 12-11-2006
1.00
Leak tested right wing
Details

 12-10-2006
9.00
Riveted right wing
Details
     

 12-07-2006
3.00
Prepared wing for flap attachment
Details
       

 12-06-2006
1.50
Attached aileron to left wing
Details
     

 12-04-2006
2.00
Installed bellcrank
Details

 12-03-2006
5.00
Completed left flap assembly
Details
     

 12-02-2006
4.00
Completed right flap assembly
Details

 12-01-2006
2.00
Began right flap assembly
Details
     

 11-30-2006
5.00
Assembled ailerons to completion
Details
       

 11-29-2006
2.50
Riveted aileron stiffeners and frame
Details
       

 11-28-2006
3.00
Assembled aileron hinge brackets, etc
Details
       

 11-22-2006
7.00
Sprayed remaining parts
Details
       

 11-21-2006
3.50
Setup spray booth for painting
Details

 11-19-2006
6.50
Riveted leading edge to right wing
Details
     

 11-19-2006
5.00
Prepared paint booth and parts
Details
       

 11-18-2006
7.00
Alumidined all aileron and flap parts - ready to p
Details
     

 11-12-2006
2.00
Set right wing skeleton on frame
Details

 11-12-2006
11.00
Riveted top skin to left wing
Details
       

 11-11-2006
4.00
Scrubbed aileron and flap parts
Details

 11-11-2006
4.50
Riveted leading edge, mounted tank, clecoed top sk
Details
       

 11-11-2006
1.50
Prepared wing access panels
Details

 11-10-2006
2.00
Scrubbed aileron and flap parts
Details
     

 11-09-2006
2.00
Scrubbed aileron and flap parts
Details
     

 11-07-2006
1.50
Scrubbed aileron and flap parts
Details
     

 11-02-2006
2.50
Prepared pushroads - ready for paint prep
Details
     

 11-01-2006
2.50
Prepared pushrods
Details
     

 10-31-2006
3.50
Prepared flaps - ready for paint prep
Details
       

 10-30-2006
3.00
Prepared flaps
Details
       

 10-29-2006
6.00
Prepared flaps
Details
       

 10-29-2006
5.00
Prepared ailerons - ready for paint prep
Details
       

 10-28-2006
8.00
Prepared ailerons
Details
     

 10-27-2006
4.00
Riveted left leading edge to spar
Details
     

 10-26-2006
7.00
Riveted leading edges
Details
       

 10-24-2006
2.50
Deburred and clecoed stiffeners to skins
Details
       

 10-20-2006
2.00
Cut aileron skin stiffeners
Details
     

 10-17-2006
2.50
Match drilled aileron brackets
Details
     

 10-16-2006
2.50
Finished landing light assemblies
Details
       

 10-15-2006
5.00
Riveted right wing baffle
Details
       

 10-15-2006
1.50
Finished riveting left tank
Details

 10-14-2006
4.00
Riveted baffle to left tank
Details
       

 10-14-2006
2.00
Installed fuel pickups and plates
Details
       

 10-14-2006
2.00
Finished installing sensor plates
Details
     

 10-14-2006
2.50
Cleaned up clecos and tools
Details

 10-13-2006
6.00
Riveted T-410's and T-405's to leading edges
Details
     

 10-12-2006
3.50
Riveted outside ribs to left tank
Details
       

 10-10-2006
3.50
Riveted outside ribs to right tank
Details
       

 10-09-2006
7.00
Riveted 4 ribs to tanks
Details
       

 10-08-2006
13.00
Riveted 6 internal tank ribs
Details
       

 10-08-2006
2.50
Finished fuel pickups and vent tubes
Details
       

 10-06-2006
5.00
Riveted ribs to main spars
Details

 10-05-2006
2.00
Masked tanks for rib assembly
Details
     

 10-03-2006
3.00
Fabricated fuel vent lines.
Details
     

 10-01-2006
10.00
Assemble stiffeners to right tank
Details
       

 09-30-2006
2.00
Clean parts for tank assembly
Details
     

 09-30-2006
2.00
Attached ribs to right rear spar
Details
       

 09-30-2006
6.00
Assembled stiffeners to left tank
Details
     

 09-29-2006
2.00
Final assembly of rear spars
Details
       

 09-29-2006
1.50
Attached ribs to left rear spar
Details
     

 09-28-2006
3.00
Attacked nutplates to main spars
Details
       

 09-25-2006
3.00
Prime front spars and nutplates
Details
     

 09-24-2006
9.00
Scrub and prime leading edge skins and ribs
Details

 09-23-2006
14.00
Preped and primed small parts and ribs
Details
     

 09-17-2006
8.00
Primed right wing ribs and skins
Details
       

 09-16-2006
14.50
Preped right wing ribs and skins for priming
Details
     

 09-03-2006
0.00
Built filter unit and mounts for spray equipment
Details
       

 08-19-2006
0.00
Put up plastic curtains for spray booth
Details
       

 08-08-2006
2.50
Trim lenses, countersink holes
Details
       

 08-08-2006
1.00
Drill lens holes
Details
       

 08-07-2006
1.50
Install lights in brackets
Details
     

 08-06-2006
3.00
Start landing light installation
Details
       

 08-06-2006
6.00
Deburr and dimple skins - right wing ready for pri
Details

 08-05-2006
7.00
Dimple ribs, spars, and prepare parts
Details
     

 08-04-2006
2.00
Prepare skins for dimpling
Details

 08-03-2006
1.00
Dissasemble right wing
Details

 08-02-2006
0.50
Drill holes for filler flange and drain
Details

 08-01-2006
1.50
Prepare capacitive fuel sensor plates
Details

 07-31-2006
1.75
Final prep on inboard tank rib
Details

 07-31-2006
0.25
Drill T405 tank attach angle
Details

 07-30-2006
0.50
Match drill leading edge
Details

 07-30-2006
1.00
Machine countersink tank skin
Details
     

 07-30-2006
1.50
Install fuel tank baffle
Details
     

 07-30-2006
0.50
Disassemble tank
Details

 07-30-2006
1.00
Attach tank skin to baffle and adjust
Details
     

 07-30-2006
2.50
Attach ribs and tank skin and match drill
Details

 07-29-2006
1.00
Started right wing - cleco and match drill ribs to
Details

 07-29-2006
0.25
Redrilled holes for electrical conduit to 3/4"
     

 07-29-2006
0.50
Prepare scarf joint on skins
     

 07-29-2006
0.50
Mount wing skeleton to framd
     

 07-29-2006
1.00
Mount and match drill top skins
       

 07-29-2006
0.75
Mount and match drill bottom skins
     

 07-29-2006
0.50
Make root doubler plate
     

 07-29-2006
1.50
Dimpled top skins
Details

 07-29-2006
0.50
Dimpled tank ribs and skin
Details

 07-29-2006
2.00
Dimpled bottom skins - left wing ready to prime
Details
       

 07-29-2006
0.50
Cleco leading edge to spar, drill joint plate
       

 07-29-2006
0.50
Cleco leading edge in cradle
     

 07-28-2006
1.00
Dimpled skins
Details
     

 07-28-2006
1.00
Dimpled ribs
Details
       

 07-28-2006
0.50
Deburr skins
Details

 07-27-2006
2.50
Deburr skins
Details

 07-25-2006
1.25
Deburr skins
Details
     

 07-25-2006
0.75
Deburr joint plate for nutplates
Details
     

 07-25-2006
0.75
Deburr and countersink rear spar
Details
       

 07-25-2006
0.75
Countersink main spar for skin
Details
     

 07-24-2006
1.50
Deburr rib holes
Details
     

 07-24-2006
1.00
Countersink main spar for skin
Details
     

 07-23-2006
2.50
Rivet stiffener ring to rib
Details
       

 07-23-2006
2.00
Drill tank plate holes & make anti-rotation bracke
Details
     

 07-23-2006
0.75
Drill holes in filler flange
Details
       

 07-23-2006
0.25
Drill holes for tank drain fitting
Details
     

 07-23-2006
1.50
Disassemble left wing and start to deburr parts
Details

 07-23-2006
2.00
Deburr tank parts
Details
       

 07-23-2006
0.50
Cut hole in inboard tank rib
Details
     

 07-22-2006
0.50
Solder wire to BNC connector
Details

 07-22-2006
0.25
Modified snap bushings
Details

 07-22-2006
1.00
Match drill tank holes
       

 07-22-2006
0.20
Match drill joint plate
Details
     

 07-22-2006
0.25
Install plate 2
Details

 07-22-2006
3.00
Fabricate tank brackets
Details
       

 07-22-2006
0.50
Fabricate & drill nose reinforcement plate
Details
     

 07-22-2006
0.25
Drill out screw holes

 07-22-2006
0.40
Disassemble tank
     

 07-22-2006
1.40
Countersink baffle holes
Details
       

 07-22-2006
1.20
Capacitive sensors - install plate 1
Details
     

 07-22-2006
0.50
Attach wire to outboard plate
Details

 07-22-2006
0.25
Attach nutplates to sensor plates
Details
     

 07-10-2006
0.50
Mount ribs to baffle
Details
       

 07-10-2006
0.50
Fit tank skin to baffle
Details
       

 07-10-2006
0.50
Cleco skins to ribs
Details
       

 07-09-2006
0.50
Match drill leading edge
Details
       

 07-09-2006
0.50
Match drill holes in T-712's to main spar
Details
     

 07-09-2006
1.50
Make tank stiffeners and cleco
Details
       

 07-09-2006
0.20
Drill holddown hole in bottom of leading edge
Details
     

 07-09-2006
1.00
Drill for nutplates
Details
     

 07-09-2006
0.50
Drill center holes in T-712's
Details
     

 07-09-2006
0.10
Draw center lines on T-712's
Details
       

 07-09-2006
0.20
Cleco baffel to main spar
Details
     

 07-09-2006
0.30
Back drill T-712 number 1
Details

 07-08-2006
0.50
Remove bottom skins
Details

 07-08-2006
1.00
Match drill top skins
Details
     

 07-08-2006
1.00
Match drill bottom skins
Details

 07-08-2006
0.50
Insert joint plate into leading edge
Details
       

 07-08-2006
0.50
Cleco outboard leading edge to spar
Details
       

 07-08-2006
0.50
Cleco outboard leading edge
Details
       

 07-08-2006
0.50
Cleco bottom skins
Details
     

 07-07-2006
1.00
Mount wing to frame (left wing)
Details
     

 07-07-2006
0.50
Match Drill main rib holes
Details
     

 07-07-2006
1.00
Drill wing doubler plate
Details
       

 07-07-2006
0.75
Cleco top skins
Details
       

 07-06-2006
1.00
Straighten Main Ribs
       

 07-06-2006
1.50
Drill holes for wiring conduit
Details
       

 07-06-2006
0.50
Cleco main ribs to spars (left wing)
Details
     

 07-05-2006
1.00
Straighten main ribs
Details
     

 07-04-2006
3.50
Straightend leading edge ribs
Details
       

 07-04-2006
2.75
Straighten main ribs
Details
       

 07-04-2006
2.00
Deburred main ribs
Details
       

 07-03-2006
3.50
Deburr leading edge ribs
Details
     

 07-02-2006
1.20
Trimmed ends of rear spar inside doubler plates
Details
     

 07-02-2006
1.70
Prepared doubler plates.
Details
       

 07-02-2006
1.20
Prepared doubler plates for spars
Details

 07-02-2006
0.30
Drilled out holds for inside doubler plates
Details
     

 07-02-2006
0.20
Clamped doubler plates to rear spar
Details
       

 07-01-2006
0.50
Spot primed the spar
Details

 07-01-2006
1.25
Fabricate the tie-down assembly
Details
     

 07-01-2006
0.60
Drilled holes and countersunk for tie-down rivets
Details

 07-01-2006
2.00
Deburred edges of rear spars
Details
       

 07-01-2006
0.30
Countersunk center spar for nutplates
Details
       

 07-01-2006
1.50
Countersinked main spar for access plate platenuts
Details
       

 07-01-2006
2.00
Completed platenut countersinking
Details
     

 06-29-2006
3.00
Continued platenut countersinking
Details
     

 06-28-2006
1.00
Made countersink template
Details

 06-27-2006
0.50
Started drilling main spars for plate nuts
Details
     

 06-25-2006
0.00
Wing Holder
Details
       

 06-24-2006
0.00
Built the leading edge jig
Details
       

 06-24-2006
0.00
Build Leading Edge Jig
Details
       

 06-17-2006
0.00
Shop preparation - bench top
Details
       

 05-27-2006
0.00
Shop preparation - table drawers
Details
       

 05-06-2006
0.00
Shop preparation - Dry erase board
Details
       

 04-29-2006
0.00
Shop Preparation - drawing boards
Details
       

 03-18-2006
0.00
Shop preparation - hand tool panel
Details
       

 02-04-2006
0.00
Shop preparation - power tool panel
Details
       

 01-21-2006
0.00
Shop preparation - clamp panel
Details
       

 01-07-2006
0.00
Shop preparation
Details
       

 12-16-2005
0.00
Built empenagge holder
Details
       

 12-02-2005
4.00
Skin vertical stab, roll and rivet leading edge
       

 12-02-2005
0.00
Build crate to bring empennage home
Details
       

 12-02-2005
2.00
Assemble trim tab to elevator
       

 12-02-2005
1.00
Assemble trim tab
       

 12-02-2005
3.00
Assemble elevator frames and skin them
     

 12-01-2005
2.00
Rivet vert stab frame and skin stabilizers
       

 12-01-2005
2.00
Rivet skins to vertical stabilizer
       

 12-01-2005
6.00
Rivet skins to horizontal stabilizer
       

 12-01-2005
2.00
Rivet horizontal stabilzer ribs to front spar
     

 11-30-2005
6.00
Prepare elevator components for priming
Details
       

 11-30-2005
3.00
Assemble rear spar
Details
       

 11-30-2005
3.00
Assemble rear spar
Details
       

 11-29-2005
6.00
Prepare rudder for priming
Details
     

 11-29-2005
6.00
Prep Vertical Stabilizer components
Details
     

 11-28-2005
12.00
Prepare horizontal stabilizer components
Details
       

 11-27-2005
2.00
Inventory Kit
Details
       