Date
|
Hours
|
Work Log Summary
|
Details
|
09-29-2013
|
4.00
|
Install ADSB, fix PTT switch,EGT moniter issue
|
|
|
|
05-18-2013
|
1.00
|
Its done! Fly's like an RV should!
|
Details
|
|
|
03-13-2013
|
1.00
|
Final inspection by Jon Blosser DAR
|
Details
|
|
|
03-12-2013
|
1.50
|
Install data plate, balance carbs, finish punchlis
|
Details
|
|
|
03-11-2013
|
3.00
|
Pitot static system test, find and fix static leak
|
Details
|
|
|
03-09-2013
|
8.00
|
Fix trim, Weight and Balance, Punchlist
|
Details
|
|
|
03-07-2013
|
3.50
|
emptyl tank, enter HEX, towbar,start punchlist
|
Details
|
|
|
03-03-2013
|
4.00
|
Calibrate fuel tank, install interior light, inter
|
|
|
|
03-02-2013
|
3.00
|
Fuel in, First Start, Trim indicator issues...
|
|
|
|
02-28-2013
|
3.00
|
Bleed brakes, set up Dynon, air in tires, canopy o
|
|
|
|
02-12-2013
|
4.00
|
Install roll and pitch servo
|
|
|
|
02-10-2013
|
2.00
|
ELT bracket, Pitch servo pushrods
|
|
|
|
02-06-2013
|
2.00
|
Install ELT antenna, bracket, fill out registratio
|
Details
|
|
|
02-03-2013
|
6.50
|
Com Antenna, intercom,transponder, autopilot harne
|
Details
|
|
|
01-30-2013
|
3.50
|
Install control module, engine monitor battery, pl
|
|
|
|
01-23-2013
|
1.00
|
Inventory Avionics Kit
|
|
|
|
01-06-2013
|
1.00
|
Trial fit wings post gear fix, pic paint schemes,
|
Details
|
|
|
01-05-2013
|
4.50
|
Install Gas tank, check flapperon brackets, reins
|
|
|
|
01-03-2013
|
4.50
|
Finish Gear AD
|
Details
|
|
|
01-01-2013
|
4.50
|
Finish skin doublers, work on gear leg brackets
|
|
|
|
12-30-2012
|
3.50
|
Start service bulletin 12-11-09
|
Details
|
|
|
12-22-2012
|
2.00
|
disassembly for AD gear fix, Tweak baggage wall
|
|
|
|
12-20-2012
|
1.00
|
Attach canopy fairing
|
|
|
|
12-15-2012
|
4.00
|
Spinner install,reinstall prop, cowling heat shiel
|
Details
|
|
|
12-12-2012
|
3.00
|
Spinner attach points, and prop cutouts
|
Details
|
|
|
12-09-2012
|
1.50
|
Finish fiberglass airduct, attach oil cooler, plac
|
|
|
|
12-08-2012
|
2.50
|
Blast tube regulator, fiberglass airduct, cowling
|
|
|
|
12-03-2012
|
2.00
|
Prepare air duct for fibeglass, oil hoses, panel w
|
|
|
|
11-29-2012
|
3.00
|
Oil cooler assembly, start air duct installation
|
|
|
|
11-28-2012
|
2.50
|
Oil cooler box,
|
|
|
|
11-25-2012
|
4.00
|
Overflow hose, heater cable install
|
Details
|
|
|
11-24-2012
|
1.00
|
Stage inspection,by DAR Jonathan Blosser
|
Details
|
|
|
11-20-2012
|
3.00
|
Install box cooler, radiator, clean up wiring
|
|
|
|
11-18-2012
|
1.50
|
EGT probes, wrap exhausts, start cooler box
|
|
|
|
11-17-2012
|
3.00
|
Prop on, muffler on, trim tail pipe, cowling
|
|
|
|
11-14-2012
|
4.00
|
fuel lines,fuel return line, MAP hose, pitot tube,
|
|
|
|
11-10-2012
|
7.00
|
Install engine mount,cooling shield, mate engine t
|
|
|
|
11-08-2012
|
3.00
|
install battery, wiring harnesses, fuel pressure s
|
|
|
|
11-04-2012
|
1.50
|
Open and inventory engine kit-finally
|
Details
|
|
|
10-17-2012
|
1.50
|
Sand and prep canopy fairing
|
|
|
|
10-13-2012
|
3.00
|
Nose leg fairing, sand canopy fairing
|
|
|
|
10-09-2012
|
2.50
|
Trim and fill canopy fairing
|
|
|
|
10-06-2012
|
2.00
|
Fiberglass canopy shield-initial layup
|
|
|
|
10-03-2012
|
2.00
|
Nose leg Fairing
|
|
|
|
09-25-2012
|
2.50
|
Nose leg fairing
|
|
|
|
09-22-2012
|
4.00
|
Finish Wheel Fairings! finally...
|
|
|
|
09-18-2012
|
3.00
|
Wheel fairings, epoxy, nutplates, etc.
|
|
|
|
09-09-2012
|
3.00
|
EAA visit, epoxy wheel pant brackets, nutplates
|
Details
|
|
|
09-05-2012
|
2.50
|
Front Wheel Fairing
|
|
|
|
09-01-2012
|
3.00
|
Wheel fairings
|
|
|
|
08-28-2012
|
2.50
|
Wheel fairing brackets, nutplates on fairings
|
|
|
|
08-25-2012
|
3.00
|
Wheel fairings trim and fit
|
|
|
|
08-19-2012
|
4.00
|
Tailcone finish, fit and attach
|
|
|
|
08-16-2012
|
3.50
|
Tail cone
|
Details
|
|
|
08-14-2012
|
3.00
|
Dash panels glove box- Dan does while I vacation!
|
|
|
|
08-12-2012
|
2.00
|
Glove box- Dan finishes in my absence
|
|
|
|
07-31-2012
|
3.50
|
Final attach canopy to painted frame
|
|
|
|
07-25-2012
|
3.50
|
Oil Door on cowling,install and fit
|
|
|
|
07-22-2012
|
4.00
|
Rivet cowl hinges, nut plates, final fit
|
|
|
|
07-18-2012
|
3.50
|
Cowel attachment and fitting
|
Details
|
|
|
07-14-2012
|
4.00
|
Trim cowling,hinges and pins for cowling, trial fi
|
|
|
|
07-11-2012
|
3.50
|
Canopy frame paint, trim cowling
|
|
|
|
07-03-2012
|
3.50
|
Canopy latch, guide blocks, adjust fit
|
|
|
|
06-30-2012
|
3.50
|
Canopy trimming,fitting
|
|
|
|
06-26-2012
|
2.00
|
Canopy trimming,drilling attach points
|
|
|
|
06-18-2012
|
3.50
|
Attach canopy frame, struts,
|
|
|
|
06-16-2012
|
3.00
|
Seatbelts, baggage panel, floor panels
|
Details
|
|
|
06-12-2012
|
3.50
|
Cable tension set, fuel tank in, rear window
|
|
|
|
06-07-2012
|
3.50
|
Stabilator, Rudder Cables,lap belts
|
|
|
|
06-06-2012
|
2.00
|
Wing Electrical Interconnector Update
|
|
|
|
05-30-2012
|
3.50
|
Left wing connector plug,flaperon torque tubes
|
|
|
|
05-26-2012
|
3.50
|
Pushrods, fork, detent bracket,bellcrank
|
Details
|
|
|
05-24-2012
|
3.50
|
Control sticks, flaperon pushrods,fork assembly
|
|
|
|
05-22-2012
|
3.00
|
Flange bearings, flapperon handle, push rods
|
|
|
|
05-16-2012
|
3.00
|
Wiring routing, tunnel cover,
|
Details
|
|
|
05-12-2012
|
3.00
|
Headset plugs, servo wires,plugs,
|
|
|
|
05-09-2012
|
3.50
|
Skyview updates, install options wire harness, pow
|
|
|
|
05-06-2012
|
4.00
|
New skyview upgrades,
|
Details
|
|
|
05-02-2012
|
4.00
|
OAT probe, wire harness, final tasks, try seats!
|
|
|
|
04-28-2012
|
5.00
|
Wire harness, hinge pin sensors,
|
|
|
|
04-28-2012
|
4.00
|
Control sticks,ELT bracket, wiring ELT,fuel pump
|
Details
|
|
|
04-23-2012
|
3.50
|
Flaperon hinges, Transponder,Com cables, wire harn
|
Details
|
|
|
04-19-2012
|
2.50
|
Motor mount, hinge pins, install wings
|
|
|
|
04-15-2012
|
3.00
|
Install landing gear and wheels
|
|
|
|
04-14-2012
|
3.00
|
Wheels and Tire assembly, start main gear assembly
|
|
|
|
04-10-2012
|
1.50
|
Inventory Finish Kit
|
Details
|
|
|
02-15-2012
|
2.00
|
Aft window install, wings trial fit
|
Details
|
|
|
02-11-2012
|
5.00
|
Mate tail to fuselage,
|
Details
|
|
|
02-08-2012
|
3.50
|
Oil tank bracket, battery box, upper dash cowling
|
|
|
|
02-04-2012
|
5.00
|
Lower dash panel
|
|
|
|
02-01-2012
|
3.00
|
Strut attach angle, panel attach strap, prep work
|
|
|
|
01-29-2012
|
2.00
|
Upper firewall
|
Details
|
|
|
01-26-2012
|
3.00
|
Upper Firewall
|
|
|
|
01-23-2012
|
5.00
|
Fuel System installation
|
|
|
|
01-21-2012
|
5.50
|
Rudder Pedal Assembly, brake lines
|
|
|
|
01-17-2012
|
3.00
|
Seat Backs
|
|
|
|
01-14-2012
|
5.00
|
Bulkhead Assembly
|
|
|
|
01-11-2012
|
3.50
|
Roll Bar Assembly
|
|
|
|
01-09-2012
|
3.00
|
Install vents, lower cowl hinges
|
|
|
|
01-07-2012
|
5.00
|
Finish and rivet sideskins
|
|
|
|
01-04-2012
|
3.50
|
Side skins match drill longerons,spar cutouts
|
|
|
|
01-01-2012
|
6.00
|
Longerons, Roll bar attach plate, start side skins
|
|
|
|
12-24-2011
|
2.50
|
Tunnel assembly, engine mounts, more nut plates...
|
|
|
|
12-23-2011
|
3.50
|
Attach bulkhead,step floors,nutplates, prep tunnel
|
|
|
|
12-15-2011
|
3.00
|
Rivet bottom skin, install steps
|
|
|
|
12-14-2011
|
3.50
|
Rivet step ribs, corner skins, start on floor skin
|
|
|
|
12-11-2011
|
3.00
|
insert control column,rivet bulkhead
|
Details
|
|
|
12-10-2011
|
4.00
|
Bulkhead assembly
|
Details
|
|
|
12-07-2011
|
3.50
|
Floor assembly, bulkhead caps rollers,control moun
|
|
|
|
12-06-2011
|
3.00
|
seat ribs,seat floor assembly,trial fit
|
|
|
|
12-03-2011
|
4.00
|
Flaperon mixer arm,bracket, seat ribs assembly
|
|
|
|
11-30-2011
|
3.00
|
Baggage ribs, pulley brackets
|
|
|
|
11-27-2011
|
4.00
|
Center bulkhead, baggage floor and ribs
|
|
|
|
11-25-2011
|
3.00
|
Start Fuuselage Kit
|
|
|
|
11-22-2011
|
1.50
|
Open and inventory Fuselage Kit
|
Details
|
|
|
11-20-2011
|
3.50
|
Finish Flaperon
|
|
|
|
11-16-2011
|
3.50
|
Finish Flaperon Skin
|
|
|
|
11-03-2011
|
2.50
|
Finish flaperon skeleton, fuselage kit arrives!
|
|
|
|
11-01-2011
|
2.50
|
Flaperons skeleton
|
|
|
|
10-30-2011
|
2.00
|
Build Brackets for Flaperons
|
|
|
|
10-26-2011
|
2.50
|
Flaperon brackets
|
|
|
|
10-22-2011
|
4.00
|
Finish rivet top skins, end skins, start on light
|
|
|
|
10-20-2011
|
3.00
|
Rivet Wing Skins
|
|
|
|
10-18-2011
|
3.00
|
Work on wing light kit
|
|
|
|
10-12-2011
|
2.50
|
Rivet Right Wing bottom skin
|
|
|
|
10-05-2011
|
2.50
|
Landing light hole, support brackets
|
|
|
|
09-28-2011
|
2.50
|
Start Right Wing, bottom skins
|
|
|
|
09-24-2011
|
6.00
|
install strobe kit, finish end skins
|
|
|
|
09-23-2011
|
2.00
|
Work on end skin
|
|
|
|
09-18-2011
|
2.50
|
Finish step, wing tip skins
|
|
|
|
09-14-2011
|
4.50
|
Finish top skins left wing
|
Details
|
|
|
09-07-2011
|
2.00
|
Finish Leading Edge, Hinge Brackets
|
|
|
|
09-05-2011
|
6.00
|
Finish Bottom Skin left wing, inspection plate
|
|
|
|
09-02-2011
|
2.00
|
Wing Skins
|
|
|
|
08-27-2011
|
4.50
|
Finish ribs, stall warning device,
|
|
|
|
08-24-2011
|
2.50
|
Attach ribs to main spar
|
|
|
|
08-20-2011
|
3.00
|
Install main ribs, nut plates, rivet
|
|
|
|
07-31-2011
|
1.50
|
Main Ribs prep, install new compressor
|
|
|
|
07-27-2011
|
2.50
|
Rivet Rear Spar Assembly, Debur, Flute Ribs
|
|
|
|
07-23-2011
|
2.50
|
Front spar assembly- countersink, rivet
|
|
|
|
07-14-2011
|
2.50
|
Prep work on ribs, Amanda painting!
|
|
|
|
07-09-2011
|
4.00
|
Flaperon hinge brackets, and hinges, rear spar
|
|
|
|
07-06-2011
|
2.50
|
Sub spar riveting, Rear sub spar prep work
|
|
|
|
07-04-2011
|
2.50
|
Start Wing Spar prep work, tie downs
|
Details
|
|
|
07-04-2011
|
2.50
|
Start Wing Spar prep work, tie downs
|
Details
|
|
|
04-13-2011
|
1.50
|
Open Wing Kit, Inventory, Hang Tail Kit
|
Details
|
|
|
03-09-2011
|
2.00
|
Wire servo, V-stab Tip Fairing, Rudder Tip Fairing
|
|
|
|
03-05-2011
|
6.00
|
Rivet top skin, attach vertical stabilizer,rudder,
|
Details
|
|
|
03-02-2011
|
4.50
|
Rivet Side Skins, tailcone, prepare top skin, and
|
|
|
|
02-26-2011
|
7.00
|
Attach skins tailcone, install static ports and tu
|
|
|
|
02-16-2011
|
3.00
|
Finish Bulkhead Assembly, redo tailskid bracket
|
|
|
|
02-12-2011
|
6.00
|
Prepare tailcone skins,rivet fuselage frames, skid
|
|
|
|
02-09-2011
|
3.00
|
Counterbalance Weights, Start Skins Prep work
|
|
|
|
02-06-2011
|
3.00
|
Finish riveting stabilator and anti-servo tab
|
|
|
|
02-05-2011
|
3.00
|
Amanda and Dan finish Stabilator and Rivet
|
|
|
|
01-30-2011
|
5.00
|
Finish Stabilator Box Skeleton, start skins
|
|
|
|
01-29-2011
|
8.00
|
Build Spar Box, Prep work
|
Details
|
|
|
01-27-2011
|
3.00
|
Forward and Rear Spars-prep work
|
|
|
|
01-22-2011
|
7.00
|
Finish Rudder, Anti-Servo Tabs, Rivet
|
|
|
|
01-19-2011
|
4.00
|
Adjust hinge, start rudder
|
Details
|
|
|
01-15-2011
|
6.00
|
Finish skeleton, Riviting, start skins
|
Details
|
|
|
01-12-2011
|
2.00
|
Prepare for riviting skeleton
|
|
|
|
01-08-2011
|
5.00
|
Building Rear Spar & Hinges
|
Details
|
|
|
01-04-2011
|
2.00
|
Inventory Kit
|
|
|
|
01-02-2011
|
4.00
|
Build Table, Open Kit
|
|
|
|
12-30-2010
|
0.80
|
Vans Kit Arrives
|
|
|