Date
|
Hours
|
Work Log Summary
|
Details
|
09-08-2018
|
3.00
|
CAN bus repair
|
Details
|
|
|
09-07-2018
|
1.00
|
Update
|
Details
|
|
|
02-24-2018
|
6.00
|
Fairings & seat heat installation
|
Details
|
|
|
02-18-2018
|
6.00
|
Crotch strap installation
|
Details
|
|
|
02-17-2018
|
6.00
|
Fairings & aileron trim
|
Details
|
|
|
02-11-2018
|
6.00
|
Aileron trim & misc fiberglass work
|
Details
|
|
|
02-03-2018
|
6.00
|
Gear fairings
|
Details
|
|
|
01-21-2018
|
6.00
|
Wheel pants
|
Details
|
|
|
12-31-2017
|
2.00
|
Cowl work
|
Details
|
|
|
12-29-2017
|
4.00
|
Cowl & baffles
|
Details
|
|
|
12-24-2017
|
4.00
|
Inlet ramp modifications
|
Details
|
|
|
12-17-2017
|
6.00
|
|
Details
|
|
|
12-16-2017
|
3.00
|
First oil change
|
Details
|
|
|
12-10-2017
|
1.00
|
Jack pad fabrication
|
Details
|
|
|
12-03-2017
|
1.50
|
Max gross weight testing
|
Details
|
|
|
11-12-2017
|
4.00
|
Interior and cowling
|
Details
|
|
|
11-05-2017
|
3.00
|
ELT testing, interior installation
|
Details
|
|
|
10-29-2017
|
1.00
|
Changed some avionics settings
|
Details
|
|
|
10-29-2017
|
1.00
|
Adjusted right rear latching block
|
Details
|
|
|
10-28-2017
|
3.00
|
|
Details
|
|
|
10-13-2017
|
4.00
|
First Flight!
|
Details
|
|
|
10-12-2017
|
3.00
|
N413DJ is officially an airplane!
|
Details
|
|
|
10-11-2017
|
8.00
|
Final airworthiness inspection preparation
|
Details
|
|
|
10-09-2017
|
2.00
|
Primed windshield fairing
|
Details
|
|
|
10-08-2017
|
9.00
|
Fuel system calibration & misc finish work
|
Details
|
|
|
10-07-2017
|
8.00
|
Misc finish work
|
Details
|
|
|
10-02-2017
|
1.50
|
Weight & Balance
|
Details
|
|
|
10-01-2017
|
5.00
|
Misc finish work
|
Details
|
|
|
09-30-2017
|
9.00
|
Spinner, aft canopy skirt and latch
|
Details
|
|
|
09-28-2017
|
1.00
|
First engine start
|
Details
|
|
|
09-25-2017
|
6.00
|
First start attempt
|
Details
|
|
|
09-24-2017
|
8.00
|
More misc finish work
|
Details
|
|
|
09-23-2017
|
8.50
|
Misc finish work
|
Details
|
|
|
09-17-2017
|
2.50
|
Misc finish work
|
Details
|
|
|
09-16-2017
|
7.00
|
Misc finish work
|
Details
|
|
|
09-10-2017
|
5.00
|
Empennage fairing
|
Details
|
|
|
09-09-2017
|
5.00
|
Misc finishing tasks
|
Details
|
|
|
08-28-2017
|
1.00
|
Pulled magnetos for SB1-15 repair
|
Details
|
|
|
08-27-2017
|
8.50
|
Misc odds and ends
|
Details
|
|
|
08-26-2017
|
7.00
|
Interior installation
|
Details
|
|
|
08-20-2017
|
6.50
|
Control system, flaps & cabin covers
|
Details
|
|
|
08-19-2017
|
7.00
|
Flight controls & control stick wiring
|
Details
|
|
|
08-13-2017
|
7.00
|
Wired control stick & checked magneto timing
|
Details
|
|
|
08-12-2017
|
5.00
|
Bled brakes, attached rudder pedal & rudder cables
|
Details
|
|
|
08-06-2017
|
6.00
|
Flight control rigging
|
Details
|
|
|
08-05-2017
|
4.50
|
Fuel system testing and misc finish work
|
Details
|
|
|
07-30-2017
|
7.00
|
Installed pitot tube, secured wing wiring, added
|
Details
|
|
|
07-29-2017
|
6.00
|
Fuel quantity wiring, brake line installation, etc
|
Details
|
|
|
07-23-2017
|
10.00
|
Finishing rudder, elevators & other misc fuselage
|
Details
|
|
|
07-21-2017
|
4.00
|
Oil filler door & control surface tips
|
Details
|
|
|
07-16-2017
|
7.00
|
Cowl & flap installation
|
Details
|
|
|
07-15-2017
|
8.00
|
Cowl camlock installation
|
Details
|
|
|
07-09-2017
|
8.00
|
Wingtips & cowling
|
Details
|
|
|
07-08-2017
|
6.00
|
Misc finishing work
|
Details
|
|
|
07-04-2017
|
3.00
|
Cowl work
|
Details
|
|
|
06-25-2017
|
6.00
|
Misc fiberglass work
|
Details
|
|
|
06-24-2017
|
6.00
|
Cowl & right wingtip
|
Details
|
|
|
06-21-2017
|
9.00
|
Wingtip installation & cowl work
|
Details
|
|
|
06-20-2017
|
7.00
|
Windshield fairing & wingtip work
|
Details
|
|
|
06-11-2017
|
3.00
|
Windshield & canopy fairing work
|
Details
|
|
|
06-10-2017
|
5.00
|
Windshield & canopy fairing work
|
Details
|
|
|
06-05-2017
|
2.50
|
Windscreen & canopy fairing work
|
Details
|
|
|
06-04-2017
|
5.00
|
Windscreen & canopy fairing work
|
Details
|
|
|
05-26-2017
|
7.50
|
Windscreen fairing fabrication
|
Details
|
|
|
05-23-2017
|
3.50
|
Initial windscreen fairing work
|
Details
|
|
|
05-21-2017
|
5.00
|
Final fitting and windscreen fairing prep
|
Details
|
|
|
05-20-2017
|
4.00
|
Attached aft and side skirts
|
Details
|
|
|
05-15-2017
|
3.50
|
More aft skirt work
|
Details
|
|
|
05-08-2017
|
1.50
|
More aft skirts
|
Details
|
|
|
05-07-2017
|
5.00
|
Aft skirts...again
|
Details
|
|
|
05-06-2017
|
4.00
|
Canopy frame final adjustments
|
Details
|
|
|
04-30-2017
|
6.00
|
Fuel pump installation and other finishing tasks
|
Details
|
|
|
04-29-2017
|
6.00
|
Alternate air cable and other finishing tasks
|
Details
|
|
|
04-23-2017
|
1.00
|
Radio troubleshooting
|
Details
|
|
|
04-15-2017
|
3.50
|
Interior inventory
|
Details
|
|
|
04-09-2017
|
3.50
|
Spray booth construction
|
Details
|
|
|
04-08-2017
|
3.50
|
Cowl fitting
|
Details
|
|
|
04-02-2017
|
6.00
|
Cable rigging and cowling fitting
|
Details
|
|
|
04-01-2017
|
3.00
|
Tail light wiring and system check
|
Details
|
|
|
04-01-2017
|
3.50
|
Panel installation, wiring & testing
|
Details
|
|
|
03-26-2017
|
5.00
|
Prop bolts & misc finish work
|
Details
|
|
|
03-25-2017
|
4.00
|
Tail light installation
|
Details
|
|
|
03-25-2017
|
3.50
|
Prop safety wire & tail light installation
|
Details
|
|
|
03-16-2017
|
3.00
|
Tail light bracket & flight control installation
|
Details
|
|
|
03-12-2017
|
4.50
|
Rudder fairing & tail strobe
|
Details
|
|
|
03-11-2017
|
3.00
|
Misc finishing work
|
Details
|
|
|
02-26-2017
|
2.50
|
Misc firewall forward work
|
Details
|
|
|
02-26-2017
|
2.50
|
Brake lines
|
Details
|
|
|
02-25-2017
|
3.00
|
Panel labeling attempt #1
|
Details
|
|
|
02-19-2017
|
6.00
|
Misc firewall forward work
|
Details
|
|
|
02-18-2017
|
3.50
|
Misc firewall forward work
|
Details
|
|
|
02-12-2017
|
6.00
|
Alternator, spinner hub and prop installation
|
Details
|
|
|
02-11-2017
|
4.00
|
Standby alternator installation
|
Details
|
|
|
02-05-2017
|
5.00
|
Propeller governor cable, exhaust hangers & panel
|
Details
|
|
|
02-04-2017
|
2.00
|
Finishing throttle quadrant sub panel
|
Details
|
|
|
02-04-2017
|
2.00
|
Adjusted throttle cable bracket
|
Details
|
|
|
01-28-2017
|
5.00
|
Instrument panel prep
|
Details
|
|
|
01-22-2017
|
6.00
|
Exhaust hangers and throttle sub panel
|
Details
|
|
|
01-21-2017
|
3.00
|
Exhaust hanger installation
|
Details
|
|
|
01-16-2017
|
7.50
|
Sensor wiring and wire bundle organization
|
Details
|
|
|
01-15-2017
|
4.00
|
CHT, EGT & manifold pressure wiring
|
Details
|
|
|
01-14-2017
|
4.00
|
Oil fittings & sensor wiring
|
Details
|
|
|
01-08-2017
|
8.00
|
Misc firewall forward installation
|
Details
|
|
|
01-07-2017
|
4.00
|
Misc firewall forward work
|
Details
|
|
|
01-07-2017
|
2.00
|
Audio panel troubleshooting
|
Details
|
|
|
01-02-2017
|
5.50
|
GPS antenna and misc wiring
|
Details
|
|
|
01-01-2017
|
3.00
|
Radio harness modification
|
Details
|
|
|
12-31-2016
|
6.00
|
Audio panel & antenna installation
|
Details
|
|
|
12-30-2016
|
1.50
|
Circuit testing and planning
|
Details
|
|
|
12-30-2016
|
3.50
|
Avionics power up and initial programming
|
Details
|
|
|
12-29-2016
|
4.00
|
Left side wire bundle organization
|
Details
|
|
|
12-29-2016
|
1.00
|
Fuel vent line final installation
|
Details
|
|
|
12-28-2016
|
4.00
|
Wire bundle organization
|
Details
|
|
|
12-27-2016
|
5.00
|
GDL 39 power & wire bundle organization
|
Details
|
|
|
12-18-2016
|
6.00
|
Standby alternator wiring
|
Details
|
|
|
12-17-2016
|
4.00
|
Autopilot wiring & wire bundle organization
|
Details
|
|
|
12-04-2016
|
4.50
|
Autopilot wiring
|
Details
|
|
|
12-03-2016
|
3.50
|
Autopilot wiring
|
Details
|
|
|
11-27-2016
|
3.50
|
Autopilot wiring and throttle, prop & mixture cabl
|
Details
|
|
|
11-23-2016
|
3.50
|
Pitot/Static and electrical
|
Details
|
|
|
11-20-2016
|
6.50
|
Wiring, pitot & AOA installation
|
Details
|
|
|
11-19-2016
|
3.50
|
Mid-cabin wiring
|
Details
|
|
|
11-11-2016
|
3.50
|
Elevator control rigging
|
Details
|
|
|
11-06-2016
|
5.00
|
Flight controls & electrical
|
Details
|
|
|
10-29-2016
|
3.50
|
Elevator push rod
|
Details
|
|
|
10-23-2016
|
5.00
|
Power on!
|
Details
|
|
|
10-22-2016
|
5.00
|
Pitot & AOA lines
|
Details
|
|
|
10-16-2016
|
3.00
|
Nav & strobe light wiring
|
Details
|
|
|
10-15-2016
|
2.00
|
Nav & strobe light wiring
|
Details
|
|
|
10-15-2016
|
2.00
|
Cabin heat cable installation
|
Details
|
|
|
10-09-2016
|
5.00
|
Firewall sealing, fuel lines & electrical
|
Details
|
|
|
10-08-2016
|
3.00
|
Final riveting & fuselage covers
|
Details
|
|
|
10-02-2016
|
5.00
|
Covers & misc
|
Details
|
|
|
10-01-2016
|
4.00
|
Fuel & electrical
|
Details
|
|
|
09-22-2016
|
3.00
|
Brake lines and covers
|
Details
|
|
|
09-18-2016
|
3.50
|
Fuel system and brake line plumbing
|
Details
|
|
|
09-17-2016
|
6.50
|
Aft fuselage riveting & fuel system
|
Details
|
|
|
09-13-2016
|
3.50
|
Riveting & fuel system
|
Details
|
|
|
09-11-2016
|
7.00
|
ELT antenna and aft fuselage riveting
|
Details
|
|
|
09-10-2016
|
4.00
|
Aft fuselage wire runs
|
Details
|
|
|
08-28-2016
|
3.50
|
Aft fuselage wiring
|
Details
|
|
|
08-27-2016
|
3.00
|
Aft fuselage wiring
|
Details
|
|
|
08-22-2016
|
7.50
|
Canopy adjustment and fitting skirts
|
Details
|
|
|
08-21-2016
|
4.50
|
Canopy fitting and attachment
|
Details
|
|
|
08-20-2016
|
1.00
|
Canopy fitting
|
Details
|
|
|
08-14-2016
|
6.00
|
Glareshield painting and windscreen attachment
|
Details
|
|
|
08-13-2016
|
2.00
|
Side skirt fabrication
|
Details
|
|
|
08-13-2016
|
2.00
|
Glareshield prep and painting
|
Details
|
|
|
08-07-2016
|
4.50
|
Windscreen attachment
|
Details
|
|
|
08-06-2016
|
2.00
|
Windscreen fitting
|
Details
|
|
|
07-31-2016
|
4.50
|
Avionics ventilation
|
Details
|
|
|
07-23-2016
|
6.00
|
Riveted forward fuselage
|
Details
|
|
|
07-17-2016
|
1.50
|
Riveted panel brackets to top skin
|
Details
|
|
|
07-17-2016
|
4.00
|
Final preparations for riveting
|
Details
|
|
|
07-16-2016
|
1.00
|
Forward fuselage closeout planning
|
Details
|
|
|
07-10-2016
|
4.00
|
Wire bundle organization
|
Details
|
|
|
07-09-2016
|
3.00
|
Final forward wiring organization
|
Details
|
|
|
06-26-2016
|
4.00
|
Wire bundle organization
|
Details
|
|
|
06-25-2016
|
3.50
|
Main wire bundles
|
Details
|
|
|
06-16-2016
|
3.00
|
Wire bundle organization
|
Details
|
|
|
06-12-2016
|
4.50
|
Main wire bundle organization
|
Details
|
|
|
06-05-2016
|
5.00
|
Wire bundle organization and installation
|
Details
|
|
|
06-04-2016
|
3.00
|
More wiring
|
Details
|
|
|
05-20-2016
|
3.00
|
Misc wiring
|
Details
|
|
|
05-19-2016
|
7.00
|
Misc wiring
|
Details
|
|
|
05-15-2016
|
6.00
|
Misc wiring
|
Details
|
|
|
05-14-2016
|
3.00
|
Standby alternator wiring
|
Details
|
|
|
05-08-2016
|
4.00
|
More odds & ends
|
Details
|
|
|
05-07-2016
|
1.50
|
Electrical odds & ends
|
Details
|
|
|
04-24-2016
|
4.00
|
Autopilot servo wiring
|
Details
|
|
|
04-23-2016
|
5.50
|
Misc wiring
|
Details
|
|
|
04-17-2016
|
4.50
|
Servo wiring and bundle organization
|
Details
|
|
|
04-16-2016
|
3.00
|
Hot battery bus wiring
|
Details
|
|
|
04-10-2016
|
3.50
|
Aux battery installation
|
Details
|
|
|
04-09-2016
|
5.50
|
Aux battery installation
|
Details
|
|
|
04-03-2016
|
5.00
|
Panel wiring
|
Details
|
|
|
04-02-2016
|
5.00
|
Panel wiring
|
Details
|
|
|
03-31-2016
|
2.50
|
Main power relay
|
Details
|
|
|
03-27-2016
|
3.00
|
Switch and circuit breaker installation
|
Details
|
|
|
03-26-2016
|
4.00
|
Main power & panel wiring
|
Details
|
|
|
03-19-2016
|
3.00
|
Main power wiring
|
Details
|
|
|
03-19-2016
|
3.00
|
Fuel system plumbing
|
Details
|
|
|
03-13-2016
|
3.50
|
Wire bundle organization
|
Details
|
|
|
03-12-2016
|
2.50
|
Main power supply
|
Details
|
|
|
03-12-2016
|
1.50
|
Fuel supply lines
|
Details
|
|
|
03-03-2016
|
3.75
|
Ammeter shunt and current limiter installation
|
Details
|
|
|
02-28-2016
|
8.00
|
Aft fuselage wiring
|
Details
|
|
|
02-27-2016
|
4.00
|
Planning and organization
|
Details
|
|
|
02-21-2016
|
4.50
|
Antenna installation
|
Details
|
|
|
02-20-2016
|
7.50
|
ADS-B & transponder antennas
|
Details
|
|
|
02-14-2016
|
3.50
|
VHF comm antenna installation
|
Details
|
|
|
02-14-2016
|
3.00
|
VHF antenna installation
|
Details
|
|
|
02-13-2016
|
2.00
|
VHF antenna installation
|
Details
|
|
|
02-07-2016
|
3.50
|
Left GPS antenna tray
|
Details
|
|
|
02-06-2016
|
4.50
|
Garmin GPS antenna mounting
|
Details
|
|
|
01-31-2016
|
2.00
|
Oil breather tube installation
|
Details
|
|
|
12-20-2015
|
3.50
|
Rerouted magneto harness
|
Details
|
|
|
11-29-2015
|
1.00
|
Exhaust heat shield
|
Details
|
|
|
09-20-2015
|
2.00
|
More odds and ends
|
Details
|
|
|
09-13-2015
|
1.50
|
Baffle tension rods
|
Details
|
|
|
08-29-2015
|
5.00
|
Magneto harnesses & sensor wiring
|
Details
|
|
|
08-23-2015
|
5.00
|
Magneto harness
|
Details
|
|
|
08-22-2015
|
3.00
|
Spark plug wires
|
Details
|
|
|
08-16-2015
|
5.75
|
Odds & Ends
|
Details
|
|
|
08-15-2015
|
4.00
|
Avionics rack & grounding block
|
Details
|
|
|
08-09-2015
|
4.00
|
Cabin heat
|
Details
|
|
|
08-08-2015
|
2.50
|
ELT installation
|
Details
|
|
|
08-08-2015
|
1.50
|
Cabin heat
|
Details
|
|
|
08-02-2015
|
5.00
|
Exhaust and cabin heat
|
Details
|
|
|
07-25-2015
|
4.00
|
Exhaust system installation
|
Details
|
|
|
07-18-2015
|
4.00
|
Probes and exhaust installation
|
Details
|
|
|
06-28-2015
|
4.50
|
Odds & Ends
|
Details
|
|
|
06-27-2015
|
1.50
|
Wire run planning
|
Details
|
|
|
06-23-2015
|
4.00
|
Avionics rack and component installation
|
Details
|
|
|
06-19-2015
|
3.00
|
Power distribution planning
|
Details
|
|
|
06-14-2015
|
6.00
|
Wire harness and avionics rack
|
Details
|
|
|
06-13-2015
|
6.00
|
Wire harness splicing
|
Details
|
|
|
06-07-2015
|
6.00
|
Wire harness splicing
|
Details
|
|
|
06-06-2015
|
1.00
|
GMU 22 attach plate
|
Details
|
|
|
05-31-2015
|
6.00
|
Avionics installation
|
Details
|
|
|
05-30-2015
|
2.00
|
Wire harnesses
|
Details
|
|
|
05-30-2015
|
3.00
|
Subpanel riveting
|
Details
|
|
|
05-25-2015
|
4.00
|
Forward center section assembly
|
Details
|
|
|
05-24-2015
|
4.00
|
Forward fuselage
|
Details
|
|
|
05-24-2015
|
2.00
|
Avionics tray swap and plans study
|
Details
|
|
|
05-23-2015
|
5.00
|
Cabin tunnel covers
|
Details
|
|
|
05-10-2015
|
5.25
|
Brake lines and covers
|
Details
|
|
|
05-09-2015
|
5.00
|
Covers and brake lines
|
Details
|
|
|
05-03-2015
|
5.00
|
Fuel system plumbing
|
Details
|
|
|
05-02-2015
|
6.00
|
Electric boost pump installation
|
Details
|
|
|
04-27-2015
|
2.00
|
Fuel pump installation
|
Details
|
|
|
04-26-2015
|
3.00
|
Boost pump brackets
|
Details
|
|
|
04-25-2015
|
4.00
|
Prop governor and bypass air
|
Details
|
|
|
04-25-2015
|
2.00
|
Bypass air
|
Details
|
|
|
04-20-2015
|
2.50
|
Prop governor installation
|
Details
|
|
|
04-19-2015
|
2.50
|
Prop governor installation
|
Details
|
|
|
04-18-2015
|
2.50
|
Prop and mixture cable installation
|
Details
|
|
|
04-09-2015
|
4.00
|
Baffle tension rods
|
Details
|
|
|
04-06-2015
|
1.50
|
Fuel flow sensor installation
|
Details
|
|
|
04-04-2015
|
4.50
|
Fuel flow sensor installation
|
Details
|
|
|
03-29-2015
|
6.00
|
Baffle fabric and tension rods
|
Details
|
|
|
03-28-2015
|
5.50
|
Baffles
|
Details
|
|
|
03-22-2015
|
3.00
|
Baffles and cowl fitting
|
Details
|
|
|
03-21-2015
|
6.00
|
Engine Baffles
|
Details
|
|
|
03-15-2015
|
4.00
|
Engine baffles and oil cooler
|
Details
|
|
|
03-14-2015
|
4.00
|
Engine Baffles
|
Details
|
|
|
03-01-2015
|
4.00
|
Baffles
|
Details
|
|
|
02-22-2015
|
3.50
|
Baffles and air box, what else?
|
Details
|
|
|
02-21-2015
|
5.50
|
Air induction system
|
Details
|
|
|
02-15-2015
|
6.25
|
Baffle and inlet ramp
|
Details
|
|
|
02-08-2015
|
2.00
|
Firewall forward odds & ends
|
Details
|
|
|
01-31-2015
|
4.50
|
Engine baffles and odds & ends
|
Details
|
|
|
01-26-2015
|
2.00
|
Air induction
|
Details
|
|
|
01-25-2015
|
4.50
|
Engine baffles
|
Details
|
|
|
01-24-2015
|
3.50
|
Engine baffles
|
Details
|
|
|
01-19-2015
|
5.00
|
Engine baffles
|
Details
|
|
|
01-17-2015
|
4.00
|
Engine baffles
|
Details
|
|
|
01-01-2015
|
2.50
|
Oil cooler installation
|
Details
|
|
|
01-01-2015
|
2.50
|
Fuel lines & prop governor
|
Details
|
|
|
12-31-2014
|
3.50
|
Fuel line
|
Details
|
|
|
12-30-2014
|
3.50
|
Throttle, prop & mixture brackets
|
Details
|
|
|
12-29-2014
|
3.50
|
Throttle cable
|
Details
|
|
|
12-21-2014
|
1.50
|
Starter power cable
|
Details
|
|
|
12-21-2014
|
1.50
|
Starter power cable
|
Details
|
|
|
12-21-2014
|
2.00
|
Power and ground cables cont.
|
Details
|
|
|
12-19-2014
|
3.00
|
Hoses and clamps
|
Details
|
|
|
12-06-2014
|
4.00
|
Misc engine work, Part 2
|
Details
|
|
|
12-06-2014
|
4.00
|
Misc engine work
|
Details
|
|
|
12-05-2014
|
3.00
|
Misc engine work
|
Details
|
|
|
11-30-2014
|
2.50
|
Engine mount and engine bolts
|
Details
|
|
|
11-29-2014
|
4.00
|
Engine oil fittings
|
Details
|
|
|
11-28-2014
|
3.00
|
Wire routing and alternator installation
|
Details
|
|
|
11-23-2014
|
2.50
|
Cowl fitting and SafeAir bracket installation
|
Details
|
|
|
11-22-2014
|
3.50
|
Cowl fitting
|
Details
|
|
|
11-22-2014
|
2.00
|
Cowl fitting
|
Details
|
|
|
11-16-2014
|
3.00
|
Electrical system planning
|
Details
|
|
|
11-15-2014
|
2.50
|
Cowl fitting
|
Details
|
|
|
11-10-2014
|
3.00
|
Cowl attach brackets
|
Details
|
|
|
11-09-2014
|
3.50
|
More organizing
|
Details
|
|
|
11-09-2014
|
1.50
|
Fuel line grommets
|
Details
|
|
|
11-09-2014
|
2.00
|
Cowl fitting
|
Details
|
|
|
11-08-2014
|
4.00
|
Organized & inventoried
|
Details
|
|
|
11-05-2014
|
4.00
|
Forward rib modification & wiring
|
Details
|
|
|
11-03-2014
|
1.50
|
Forward rib reinforcement
|
Details
|
|
|
11-02-2014
|
1.00
|
Removed insulating foam
|
Details
|
|
|
11-02-2014
|
3.00
|
Cabin heat diverter box
|
Details
|
|
|
10-27-2014
|
3.50
|
Fuel supply lines
|
Details
|
|
|
10-26-2014
|
4.00
|
Fuel valve
|
Details
|
|
|
10-20-2014
|
3.00
|
Forward rib modification
|
Details
|
|
|
10-19-2014
|
5.00
|
Modifications for GPS and audio panel
|
Details
|
|
|
10-18-2014
|
2.00
|
Initial panel fitting
|
Details
|
|
|
10-02-2014
|
1.00
|
Avionics inventory
|
Details
|
|
|
09-28-2014
|
3.00
|
Cowl fitting
|
Details
|
|
|
09-20-2014
|
4.00
|
Battery box and cowl fitting
|
Details
|
|
|
09-15-2014
|
3.50
|
Cowl fitting and battery box
|
Details
|
|
|
09-14-2014
|
6.00
|
Cowling
|
Details
|
|
|
09-13-2014
|
2.50
|
Initial prop fitting
|
Details
|
|
|
09-13-2014
|
5.00
|
Cowling fitting and attachment
|
Details
|
|
|
09-07-2014
|
4.00
|
Relay installation and misc work
|
Details
|
|
|
09-06-2014
|
5.00
|
Misc firewall forward work
|
Details
|
|
|
09-06-2014
|
3.00
|
Misc firewall forward work
|
Details
|
|
|
08-24-2014
|
3.50
|
Battery tray construction and installation
|
Details
|
|
|
08-23-2014
|
1.50
|
Static line and fuel supply line
|
Details
|
|
|
08-23-2014
|
5.00
|
Fuel vent and supply lines
|
Details
|
|
|
08-17-2014
|
6.00
|
Bolts...and more bolts
|
Details
|
|
|
08-16-2014
|
3.50
|
Wing installation
|
Details
|
|
|
08-16-2014
|
3.00
|
Engine installation
|
Details
|
|
|
08-10-2014
|
2.50
|
Odds and ends--3 small tasks that I've neglected
|
Details
|
|
|
08-10-2014
|
3.00
|
AD-06-02-23 compliance
|
Details
|
|
|
08-09-2014
|
3.00
|
Aft skirts
|
Details
|
|
|
07-29-2014
|
1.00
|
It's here...
|
Details
|
|
|
07-27-2014
|
4.50
|
Aft skirts
|
Details
|
|
|
07-26-2014
|
2.50
|
Canopy finish work
|
Details
|
|
|
07-26-2014
|
3.50
|
Canopy finish work
|
Details
|
|
|
07-20-2014
|
4.50
|
Canopy finish work
|
Details
|
|
|
07-19-2014
|
3.00
|
Nose gear installation
|
Details
|
|
|
07-19-2014
|
2.50
|
Engine mount installation
|
Details
|
|
|
07-06-2014
|
1.00
|
Engine mount
|
Details
|
|
|
06-24-2014
|
3.00
|
Nutplate installation and initial engine mount fit
|
Details
|
|
|
06-24-2014
|
1.50
|
Dimpled forward skin
|
Details
|
|
|
06-23-2014
|
1.50
|
Right wheel nut adjustment
|
Details
|
|
|
06-23-2014
|
1.50
|
Breather tube attachment
|
Details
|
|
|
06-15-2014
|
2.50
|
Drilled axles
|
Details
|
|
|
06-10-2014
|
2.50
|
Up on the main gear!
|
Details
|
|
|
06-08-2014
|
5.00
|
Brake installation
|
Details
|
|
|
06-01-2014
|
3.45
|
Anchor blocks and windshield work
|
Details
|
|
|
05-31-2014
|
5.25
|
Canopy latch and other misc work
|
Details
|
|
|
05-24-2014
|
0.50
|
Inventory
|
Details
|
|
|
05-13-2014
|
3.00
|
Inventory and organization
|
Details
|
|
|
05-11-2014
|
3.00
|
Getting organized
|
Details
|
|
|
05-10-2014
|
2.00
|
Misc canopy work
|
Details
|
|
|
05-09-2014
|
2.50
|
Misc canopy work
|
Details
|
|
|
05-05-2014
|
2.50
|
Canopy fitting
|
Details
|
|
|
01-01-2014
|
1.00
|
Fiberglass work
|
Details
|
|
|
12-31-2013
|
1.50
|
Fiberglass work
|
Details
|
|
|
12-28-2013
|
2.00
|
Fiberglass work
|
Details
|
|
|
11-17-2013
|
1.00
|
Misc canopy work
|
Details
|
|
|
11-17-2013
|
2.00
|
Fiberglass work
|
Details
|
|
|
11-10-2013
|
3.00
|
Nut plates and canopy rail work
|
Details
|
|
|
11-08-2013
|
5.00
|
Nut Plates--The Final Showdown
|
Details
|
|
|
11-03-2013
|
7.00
|
Nut plates...
|
Details
|
|
|
10-29-2013
|
1.50
|
Nut plate installation
|
Details
|
|
|
10-27-2013
|
2.25
|
More nut plates
|
Details
|
|
|
10-26-2013
|
5.00
|
Side skirt fabrication
|
Details
|
|
|
10-26-2013
|
3.00
|
Installing nut plates for cabin and baggage floors
|
Details
|
|
|
10-20-2013
|
4.00
|
Fitting side skirts
|
Details
|
|
|
10-13-2013
|
3.00
|
More canopy trimming
|
Details
|
|
|
10-12-2013
|
2.50
|
Canopy trimming
|
Details
|
|
|
10-11-2013
|
2.50
|
Drilled canopy to frame
|
Details
|
|
|
10-11-2013
|
2.50
|
Attached canopy tracks
|
Details
|
|
|
10-03-2013
|
2.50
|
El Grande Recorte
|
Details
|
|
|
10-02-2013
|
2.00
|
Initial fitting and trimming
|
Details
|
|
|
09-30-2013
|
1.50
|
Canopy frame fitting
|
Details
|
|
|
09-29-2013
|
3.50
|
Canopy frame fitting
|
Details
|
|
|
09-28-2013
|
4.00
|
Canopy slide rail fabrication
|
Details
|
|
|
09-28-2013
|
2.00
|
Canopy fitting
|
Details
|
|
|
09-21-2013
|
4.00
|
Misc fuselage construction
|
Details
|
|
|
09-16-2013
|
1.00
|
Aft fuselage construction
|
Details
|
|
|
09-15-2013
|
6.00
|
Canopy
|
Details
|
|
|
09-14-2013
|
4.50
|
Canopy
|
Details
|
|
|
09-08-2013
|
4.00
|
Misc fuselage work
|
Details
|
|
|
09-02-2013
|
4.00
|
Firewall and misc fuselage
|
Details
|
|
|
08-24-2013
|
3.00
|
More nut plates
|
Details
|
|
|
08-17-2013
|
2.00
|
Misc fuselage work
|
Details
|
|
|
08-17-2013
|
3.00
|
Installed nut plates on top of wing
|
Details
|
|
|
08-10-2013
|
1.00
|
Primed misc parts
|
Details
|
|
|
01-27-2013
|
1.25
|
Main gear leg installation
|
Details
|
|
|
01-27-2013
|
2.50
|
Brake line installation
|
Details
|
|
|
12-22-2012
|
4.00
|
Parts prep and misc fuselage work
|
Details
|
|
|
12-16-2012
|
3.50
|
More fuel line work and rudder pedal installation
|
Details
|
|
|
12-15-2012
|
3.00
|
Brake lines and forward tunnel
|
Details
|
|
|
12-08-2012
|
3.00
|
Brake line installation
|
Details
|
|
|
12-02-2012
|
2.50
|
More fuel lines...
|
Details
|
|
|
11-18-2012
|
0.00
|
Random thoughts
|
Details
|
|
|
11-18-2012
|
4.50
|
Fuel vent lines
|
Details
|
|
|
11-17-2012
|
3.50
|
Fuel line & brake line installation
|
Details
|
|
|
11-11-2012
|
1.50
|
Fuel & brake line brackets
|
Details
|
|
|
11-06-2012
|
1.75
|
Forward fuel tank mounts
|
Details
|
|
|
11-04-2012
|
2.50
|
Fuel tank attach brackets and misc fuselage work
|
Details
|
|
|
11-04-2012
|
2.50
|
Fuel line installation
|
Details
|
|
|
10-21-2012
|
2.00
|
Fuel lines
|
Details
|
|
|
10-20-2012
|
3.50
|
Gear mount and fuel vent line installation
|
Details
|
|
|
10-14-2012
|
2.00
|
Cabin vent installation
|
Details
|
|
|
10-07-2012
|
2.00
|
Wing removal
|
Details
|
|
|
10-06-2012
|
2.50
|
First attempt at wing removal
|
Details
|
|
|
09-30-2012
|
1.00
|
Forward fuselage
|
Details
|
|
|
09-29-2012
|
1.00
|
Foreward fuselage
|
Details
|
|
|
09-16-2012
|
1.00
|
Forward fuselage construction
|
Details
|
|
|
09-16-2012
|
3.00
|
Attached empennage
|
Details
|
|
|
09-15-2012
|
2.50
|
Forward fuselage and cabin
|
Details
|
|
|
09-09-2012
|
1.00
|
Forward fuselage
|
Details
|
|
|
09-08-2012
|
3.00
|
Forward fuselage
|
Details
|
|
|
08-18-2012
|
2.75
|
Forward fuselage
|
Details
|
|
|
07-28-2012
|
4.50
|
Forward structure and skin prep
|
Details
|
|
|
07-22-2012
|
4.00
|
Forward cabin covers & side rails
|
Details
|
|
|
07-21-2012
|
4.50
|
Forward cover fabrication
|
Details
|
|
|
07-14-2012
|
1.50
|
Inventory
|
Details
|
|
|
05-21-2011
|
4.00
|
Attached vertical stabilizer
|
Details
|
|
|
05-08-2011
|
4.00
|
Vertical stab fitting
|
Details
|
|
|
05-07-2011
|
1.00
|
Vertical stabilizer prep
|
Details
|
|
|
05-07-2011
|
1.00
|
Autopilot servo attachment
|
Details
|
|
|
05-01-2011
|
4.50
|
Misc elevator construction
|
Details
|
|
|
04-23-2011
|
1.00
|
Elevator work
|
Details
|
|
|
04-16-2011
|
2.50
|
Drilled elevator horns
|
Details
|
|
|
04-16-2011
|
2.50
|
Attached horizontal stabilizer
|
Details
|
|
|
04-03-2011
|
3.50
|
Horizontal stab and elevator fitting
|
Details
|
|
|
01-17-2011
|
3.00
|
Misc fuselage construction
|
Details
|
|
|
01-17-2011
|
0.50
|
Initial fit of horizontal stabilator
|
Details
|
|
|
01-15-2011
|
2.50
|
Misc fuselage construction
|
Details
|
|
|
01-13-2011
|
2.50
|
Misc fuselage construction
|
Details
|
|
|
01-09-2011
|
3.00
|
Misc fuselage construction
|
Details
|
|
|
01-08-2011
|
3.00
|
Misc fuselage work
|
Details
|
|
|
11-21-2010
|
3.00
|
Rudder pedal assembly
|
Details
|
|
|
11-20-2010
|
1.50
|
Rudder pedals and brakes
|
Details
|
|
|
11-07-2010
|
1.00
|
Rudder pedals
|
Details
|
|
|
11-06-2010
|
4.00
|
Flap installation and misc fuselage work
|
Details
|
|
|
10-31-2010
|
2.50
|
Flap installation
|
Details
|
|
|
10-30-2010
|
5.00
|
Flap construction
|
Details
|
|
|
10-24-2010
|
1.00
|
Flap installation
|
Details
|
|
|
10-23-2010
|
2.50
|
Flap installation
|
Details
|
|
|
10-22-2010
|
3.00
|
Flap installation
|
Details
|
|
|
10-16-2010
|
3.00
|
Aft spar drilling
|
Details
|
|
|
10-12-2010
|
3.00
|
Fitting wings
|
Details
|
|
|
10-10-2010
|
3.00
|
Wing mate
|
Details
|
|
|
10-09-2010
|
3.50
|
Landing gear mount installation
|
Details
|
|
|
10-09-2010
|
3.00
|
Flap hinge replacement
|
Details
|
|
|
09-29-2010
|
1.50
|
Replacement part practice session
|
Details
|
|
|
09-28-2010
|
3.00
|
Misc wing prep work
|
Details
|
|
|
09-26-2010
|
3.00
|
Wing skin riveting
|
Details
|
|
|
09-25-2010
|
2.50
|
Lower wing skin riveting
|
Details
|
|
|
09-23-2010
|
1.00
|
Getting organized
|
Details
|
|
|
09-12-2010
|
4.00
|
Landing gear mounts and rudder pedals
|
Details
|
|
|
09-11-2010
|
4.50
|
Lower wing skin riveting
|
Details
|
|
|
09-11-2010
|
2.50
|
Gear mounts and rudder pedals
|
Details
|
|
|
09-09-2010
|
4.00
|
Seat and center cabin construction
|
Details
|
|
|
09-06-2010
|
1.50
|
Priming parts
|
Details
|
|
|
09-06-2010
|
1.00
|
Lower wing skin riveting
|
Details
|
|
|
09-06-2010
|
1.00
|
Forward control tunnel cover
|
Details
|
|
|
09-05-2010
|
3.00
|
Seat backs and brackets
|
Details
|
|
|
09-04-2010
|
3.00
|
Lower wing skins
|
Details
|
|
|
08-28-2010
|
5.00
|
Seat construction
|
Details
|
|
|
08-26-2010
|
2.00
|
Seat construction
|
Details
|
|
|
08-21-2010
|
4.00
|
Baggage compartment construction
|
Details
|
|
|
08-17-2010
|
2.00
|
More nuplates...
|
Details
|
|
|
08-16-2010
|
2.00
|
Baggage compartment construction
|
Details
|
|
|
08-15-2010
|
4.00
|
Baggage compartment construction
|
Details
|
|
|
08-14-2010
|
2.00
|
Replaced nutplate on right fuel tank
|
Details
|
|
|
07-30-2010
|
2.50
|
Riveting steps
|
Details
|
|
|
07-30-2010
|
1.50
|
Lower wing skins
|
Details
|
|
|
07-18-2010
|
6.00
|
Forward fuselage
|
Details
|
|
|
07-13-2010
|
2.00
|
Fitting steps
|
Details
|
|
|
07-10-2010
|
4.00
|
Upper skins and misc shop prep
|
Details
|
|
|
07-08-2010
|
2.50
|
Upper skins
|
Details
|
|
|
07-06-2010
|
2.00
|
Aft fuselage construction
|
Details
|
|
|
07-02-2010
|
4.00
|
Aft deck and side rails
|
Details
|
|
|
06-29-2010
|
2.00
|
Finished organizing hangar
|
Details
|
|
|
06-27-2010
|
2.50
|
Organizing hangar
|
Details
|
|
|
06-26-2010
|
10.00
|
Wing & Fuselage Move
|
Details
|
|
|
06-21-2010
|
2.00
|
Prep for move to hangar
|
Details
|
|
|
03-08-2009
|
1.50
|
Aft deck riveting
|
Details
|
|
|
03-04-2009
|
1.00
|
Parts preparation
|
Details
|
|
|
02-28-2009
|
2.00
|
Fuselage construction
|
Details
|
|
|
02-21-2009
|
2.00
|
Aft fuselage construction
|
Details
|
|
|
02-16-2009
|
2.50
|
More riveting and aft deck fitting
|
Details
|
|
|
02-15-2009
|
4.50
|
Finished the lower fuselage riveting!
|
Details
|
|
|
02-14-2009
|
1.50
|
Forward fuselage riveting
|
Details
|
|
|
02-13-2009
|
1.00
|
Forward fuselage riveting
|
Details
|
|
|
02-11-2009
|
2.00
|
Center fuselage riveting
|
Details
|
|
|
02-08-2009
|
3.50
|
Forward fuselage riveting
|
Details
|
|
|
02-07-2009
|
8.50
|
Forward fuselage construction
|
Details
|
|
|
02-05-2009
|
2.00
|
Forward fuselage construction
|
Details
|
|
|
02-03-2009
|
1.00
|
Forward fuselage prep
|
Details
|
|
|
02-01-2009
|
5.00
|
Forward fuselage assembly
|
Details
|
|
|
01-31-2009
|
7.50
|
Prepped and primed forward fuselage parts
|
Details
|
|
|
01-25-2009
|
2.50
|
Deburring and dimpling
|
Details
|
|
|
01-24-2009
|
3.50
|
Deburring and dimpling
|
Details
|
|
|
01-22-2009
|
2.50
|
Forward fuselage prep
|
Details
|
|
|
01-20-2009
|
1.50
|
Forward fuselage prep
|
Details
|
|
|
01-19-2009
|
5.50
|
Forward fuselage prep
|
Details
|
|
|
01-18-2009
|
2.50
|
Fuselage preparation
|
Details
|
|
|
01-17-2009
|
9.50
|
Forward fuselage preparation
|
Details
|
|
|
01-11-2009
|
2.00
|
Forward fuselage preparation
|
Details
|
|
|
01-10-2009
|
2.00
|
Forward fuselage preparation
|
Details
|
|
|
01-04-2009
|
2.50
|
Forward fuselage prep
|
Details
|
|
|
01-03-2009
|
2.50
|
Forward fuselage preparation
|
Details
|
|
|
01-02-2009
|
3.50
|
Firewall fitting and drilling
|
Details
|
|
|
01-01-2009
|
4.50
|
Drilling longerons and fitting firewall
|
Details
|
|
|
12-31-2008
|
2.00
|
Drilling Longerons
|
Details
|
|
|
06-29-2008
|
4.00
|
Fuselage construction
|
Details
|
|
|
06-28-2008
|
2.50
|
Fuselage construction
|
Details
|
|
|
06-21-2008
|
3.50
|
Center to aft fuselage mating
|
Details
|
|
|
06-20-2008
|
2.50
|
Center to aft fuselage attach prep
|
Details
|
|
|
06-18-2008
|
3.00
|
Center fuselage construction
|
Details
|
|
|
06-17-2008
|
3.50
|
Center fuselage construction
|
Details
|
|
|
06-16-2008
|
1.00
|
Center fuselage construction
|
Details
|
|
|
06-15-2008
|
4.00
|
Center fuselage prep
|
Details
|
|
|
06-14-2008
|
6.00
|
Center fuselage prep
|
Details
|
|
|
06-01-2008
|
3.50
|
Center fuselage prep
|
Details
|
|
|
05-31-2008
|
4.50
|
Center section preparation
|
Details
|
|
|
02-23-2008
|
4.50
|
Center fuselage construction
|
Details
|
|
|
02-16-2008
|
1.50
|
Center fuselage prep
|
Details
|
|
|
02-10-2008
|
2.00
|
Riveted aft fuselage bottom skin
|
Details
|
|
|
02-09-2008
|
6.50
|
Aft fuselage riveting
|
Details
|
|
|
02-06-2008
|
1.00
|
Aft fuselage prep
|
Details
|
|
|
02-03-2008
|
2.00
|
Aft fuselage prep
|
Details
|
|
|
02-02-2008
|
9.50
|
Aft fuselage preparation
|
Details
|
|
|
02-01-2008
|
6.00
|
Aft fuselage preparation
|
Details
|
|
|
01-30-2008
|
3.00
|
Fuselage stiffener prep
|
Details
|
|
|
01-27-2008
|
3.50
|
Shop prep and aft fuselage assembly
|
Details
|
|
|
01-26-2008
|
3.50
|
Longeron preparation
|
Details
|
|
|
01-21-2008
|
4.50
|
Fuselage bulkhead preparation
|
Details
|
|
|
01-20-2008
|
1.00
|
Fuselage prep
|
Details
|
|
|
01-07-2008
|
4.00
|
Fuselage bulkhead prep
|
Details
|
|
|
01-06-2008
|
3.50
|
Fuselage bulhead prep
|
Details
|
|
|
01-05-2008
|
1.00
|
Fuselage bulkhead prep
|
Details
|
|
|
12-08-2007
|
6.00
|
Bulkhead construction
|
Details
|
|
|
11-24-2007
|
3.00
|
Worked F-706, F-707, F-708, F-710 bulkhead pieces
|
Details
|
|
|
11-23-2007
|
8.00
|
Completed F-705 bulkhead
|
Details
|
|
|
11-20-2007
|
2.00
|
F-705 construction
|
Details
|
|
|
11-18-2007
|
2.50
|
F-705 construction
|
Details
|
|
|
11-15-2007
|
2.50
|
Began F-705 construction
|
Details
|
|
|
11-14-2007
|
6.00
|
Completed F-704 Center Section
|
Details
|
|
|
11-13-2007
|
3.50
|
Center section construction
|
Details
|
|
|
10-16-2007
|
4.50
|
Fuselage center section
|
Details
|
|
|
09-30-2007
|
3.50
|
Fuselage center section prep
|
Details
|
|
|
09-19-2007
|
9.00
|
Firewall and fuselage center section
|
Details
|
|
|
09-18-2007
|
3.00
|
Firewall prep
|
Details
|
|
|
09-17-2007
|
5.50
|
Firewall prep
|
Details
|
|
|
09-17-2007
|
3.00
|
Autopilot servo install and aileron attachment
|
Details
|
|
|
09-15-2007
|
1.50
|
Fabricated F-601 brackets
|
Details
|
|
|
09-08-2007
|
1.50
|
Began fuselage
|
Details
|
|
|
08-25-2007
|
5.00
|
Wing finishing work
|
Details
|
|
|
08-19-2007
|
1.00
|
Right lower wing skin
|
Details
|
|
|
08-18-2007
|
5.00
|
Aileron/flap rigging and lower skin prep
|
Details
|
|
|
08-11-2007
|
4.00
|
Aileron attachment
|
Details
|
|
|
08-04-2007
|
1.50
|
Aileron control fittings
|
Details
|
|
|
07-29-2007
|
1.50
|
Aileron fittings
|
Details
|
|
|
07-28-2007
|
1.50
|
Aileron fittings
|
Details
|
|
|
07-22-2007
|
4.00
|
Finished flaps
|
Details
|
|
|
07-15-2007
|
6.50
|
Flap construction
|
Details
|
|
|
07-14-2007
|
4.00
|
Flap construction
|
Details
|
|
|
07-04-2007
|
6.00
|
Flap construction
|
Details
|
|
|
04-22-2007
|
4.00
|
Finished ailerons
|
Details
|
|
|
04-19-2007
|
8.00
|
Aileron construction
|
Details
|
|
|
04-18-2007
|
5.00
|
Aileron construction
|
Details
|
|
|
04-17-2007
|
4.00
|
Aileron construction
|
Details
|
|
|
04-16-2007
|
6.50
|
Aileron construction
|
Details
|
|
|
04-11-2007
|
4.00
|
Aileron attach brackets, flap braces, and gap seal
|
Details
|
|
|
04-10-2007
|
1.00
|
Aileron attach brackets
|
Details
|
|
|
04-08-2007
|
5.50
|
Aileron and flap prep
|
Details
|
|
|
04-07-2007
|
1.50
|
Aileron prep
|
Details
|
|
|
04-04-2007
|
1.00
|
Right aileron prep
|
Details
|
|
|
04-01-2007
|
3.50
|
Aileron and flap prep
|
Details
|
|
|
03-31-2007
|
4.00
|
Aileron & flap prep
|
Details
|
|
|
03-29-2007
|
1.00
|
Aileron & Flap prep
|
Details
|
|
|
03-27-2007
|
5.00
|
Inventoried and stored fuselage kit
|
Details
|
|
|
03-25-2007
|
3.50
|
Finished right wing top skins
|
Details
|
|
|
03-24-2007
|
4.50
|
Riveted top wing skins
|
Details
|
|
|
03-21-2007
|
2.50
|
Riveted leading edge in place
|
Details
|
|
|
03-18-2007
|
3.00
|
Wing skin deburring and dimpling
|
Details
|
|
|
03-07-2007
|
1.50
|
Wing skin deburring
|
Details
|
|
|
03-04-2007
|
3.00
|
Wing ribs and spar prep
|
Details
|
|
|
03-03-2007
|
3.00
|
Finished landing light
|
Details
|
|
|
03-01-2007
|
1.50
|
Landing light construction
|
Details
|
|
|
02-28-2007
|
2.00
|
Landing light installation
|
Details
|
|
|
02-24-2007
|
4.00
|
Leading edge construction
|
Details
|
|
|
02-21-2007
|
5.00
|
Shop prep and leading edge work
|
Details
|
|
|
01-09-2007
|
1.00
|
Fuel tank leak check
|
Details
|
|
|
01-06-2007
|
5.00
|
Fuel tank sealing
|
Details
|
|
|
12-17-2006
|
3.00
|
Fuel tank construction
|
Details
|
|
|
12-16-2006
|
4.00
|
Fuel tank sealing
|
Details
|
|
|
12-15-2006
|
2.50
|
Fuel tank construction
|
Details
|
|
|
12-13-2006
|
2.00
|
Fuel tank sealing
|
Details
|
|
|
12-09-2006
|
4.00
|
Fuel tank construction
|
Details
|
|
|
12-03-2006
|
2.00
|
Fuel tank construction
|
Details
|
|
|
12-02-2006
|
3.00
|
Fuel tank construction
|
Details
|
|
|
11-18-2006
|
2.00
|
Fuel tank prep
|
Details
|
|
|
11-12-2006
|
2.50
|
Fuel tank prep
|
Details
|
|
|
11-08-2006
|
1.50
|
Fuel tank prep
|
Details
|
|
|
11-04-2006
|
5.00
|
Right fuel tank preparation
|
Details
|
|
|
10-25-2006
|
1.50
|
Fuel tank prep
|
Details
|
|
|
09-24-2006
|
2.00
|
Fuel tank prep
|
Details
|
|
|
09-20-2006
|
2.00
|
Right tank prep
|
Details
|
|
|
09-16-2006
|
3.00
|
Right fuel tank prep
|
Details
|
|
|
09-02-2006
|
3.50
|
Right fuel tank construction
|
Details
|
|
|
08-27-2006
|
6.50
|
Right wing assembly
|
Details
|
|
|
08-26-2006
|
5.00
|
Right wing construction
|
Details
|
|
|
08-23-2006
|
3.00
|
Right wing substructure
|
Details
|
|
|
08-20-2006
|
4.00
|
Right wing prep work
|
Details
|
|
|
07-23-2006
|
4.00
|
Removed wing from stand
|
Details
|
|
|
07-12-2006
|
4.00
|
Finished riveting upper wing skins
|
Details
|
|
|
07-04-2006
|
2.00
|
Upper wing skin riveting
|
Details
|
|
|
06-17-2006
|
4.00
|
Finished leading edge
|
Details
|
|
|
06-16-2006
|
1.50
|
Finished landing light installation
|
Details
|
|
|
06-15-2006
|
1.50
|
Landing light installation
|
Details
|
|
|
06-11-2006
|
3.00
|
Landing light installation
|
Details
|
|
|
06-03-2006
|
3.00
|
Wing skin work
|
Details
|
|
|
05-29-2006
|
2.00
|
Wing skins
|
Details
|
|
|
05-20-2006
|
6.00
|
Spar and skin prep for riveting
|
Details
|
|
|
05-14-2006
|
5.00
|
Finished wing leading edge
|
Details
|
|
|
05-13-2006
|
6.00
|
Wing leading edge
|
Details
|
|
|
05-10-2006
|
1.00
|
Fuel tank pressure check
|
Details
|
|
|
05-09-2006
|
1.00
|
Installed fuel tank access plate
|
Details
|
|
|
05-06-2006
|
10.00
|
Finished sealing left tank
|
Details
|
|
|
04-30-2006
|
6.00
|
Fuel tank sealing
|
Details
|
|
|
04-19-2006
|
2.00
|
Fuel tank prep
|
Details
|
|
|
04-15-2006
|
5.00
|
Fuel tank construction
|
Details
|
|
|
04-08-2006
|
2.00
|
Fuel tank preparation
|
Details
|
|
|
04-02-2006
|
5.00
|
Fuel tank construction
|
Details
|
|
|
03-26-2006
|
3.50
|
Fuel tank prep
|
Details
|
|
|
03-25-2006
|
2.00
|
Fuel tank prep
|
Details
|
|
|
03-21-2006
|
1.50
|
Fabricated forward tank attach bracket
|
Details
|
|
|
03-08-2006
|
2.75
|
Fuel tank preparation
|
Details
|
|
|
03-05-2006
|
1.50
|
Fuel tank preparation
|
Details
|
|
|
03-04-2006
|
4.50
|
Wing tank construction
|
Details
|
|
|
03-02-2006
|
1.50
|
Fuel tank construction
|
Details
|
|
|
02-26-2006
|
3.50
|
Drilled leading edge, began tank construction
|
Details
|
|
|
02-25-2006
|
4.00
|
Left wing leading edge
|
Details
|
|
|
02-22-2006
|
3.50
|
Lower wing skin & outboard leading edge
|
Details
|
|
|
02-15-2006
|
1.50
|
Drilled upper wing skins
|
Details
|
|
|
02-12-2006
|
1.00
|
Attached lower wing skins
|
Details
|
|
|
02-11-2006
|
9.50
|
Wing construction
|
Details
|
|
|
02-08-2006
|
1.50
|
Wing structure prep
|
Details
|
|
|
02-05-2006
|
2.50
|
Wing rib prep
|
Details
|
|
|
02-04-2006
|
2.00
|
Built wing stand
|
Details
|
|
|
01-31-2006
|
1.50
|
Wing rib prep
|
Details
|
|
|
01-29-2006
|
3.00
|
Wing rib prep
|
Details
|
|
|
01-26-2006
|
1.50
|
Wing rib prep
|
Details
|
|
|
01-24-2006
|
2.00
|
Right wing rib prep
|
Details
|
|
|
01-22-2006
|
5.00
|
Wing assembly
|
Details
|
|
|
01-18-2006
|
1.75
|
Wing rib deburring
|
Details
|
|
|
01-02-2006
|
0.50
|
Moving Files
|
|
|
|
12-07-2005
|
1.50
|
Fluted ribs
|
Details
|
|
|
11-16-2005
|
1.50
|
Wing rib prep
|
Details
|
|
|
11-13-2005
|
1.00
|
Wing rib prep
|
Details
|
|
|
11-02-2005
|
1.00
|
Wing rib prep
|
Details
|
|
|
10-30-2005
|
3.00
|
Wing rib prep
|
Details
|
|
|
10-22-2005
|
5.00
|
Aft spar prep
|
Details
|
|
|
10-20-2005
|
2.00
|
Aft spar prep
|
Details
|
|
|
10-16-2005
|
4.50
|
Aft wing spar prep
|
Details
|
|
|
10-15-2005
|
3.00
|
Finished wing tie down brackets
|
Details
|
|
|
10-12-2005
|
4.00
|
Wing tie down brackets
|
Details
|
|
|
10-02-2005
|
1.50
|
Wing spar prep
|
Details
|
|
|
10-01-2005
|
3.00
|
Wing spar prep
|
Details
|
|
|
09-28-2005
|
3.00
|
Wing spar prep
|
Details
|
|
|
09-24-2005
|
2.50
|
Wing spar prep
|
Details
|
|
|
09-21-2005
|
1.50
|
Wing spar prep
|
Details
|
|
|
09-18-2005
|
3.00
|
Wing spar prep
|
Details
|
|
|
09-17-2005
|
2.50
|
Wing spar prep
|
Details
|
|
|
09-14-2005
|
1.00
|
Wing spar prep
|
Details
|
|
|
09-07-2005
|
1.50
|
Finished elevator trim
|
Details
|
|
|
08-31-2005
|
2.00
|
Finished elevators
|
Details
|
|
|
08-28-2005
|
3.00
|
Rolled elevator leading edges
|
Details
|
|
|
08-24-2005
|
2.00
|
Finished trim tab
|
Details
|
|
|
08-20-2005
|
6.50
|
Riveted left elevator
|
Details
|
|
|
08-20-2005
|
1.50
|
Finished inventory, arranged parts
|
Details
|
|
|
08-19-2005
|
2.00
|
Inventoried wing shipment
|
|
|
|
08-17-2005
|
10.00
|
Prep work, riveted right elevator
|
Details
|
|
|
08-17-2005
|
0.50
|
Opened crates, checked parts
|
Details
|
|
|
08-14-2005
|
5.00
|
Left elevator and trim tab
|
Details
|
|
|
08-06-2005
|
6.00
|
Left elevator prep
|
Details
|
|
|
08-03-2005
|
2.00
|
Right elevator prep
|
Details
|
|
|
07-31-2005
|
4.00
|
Elevator construction
|
Details
|
|
|
07-30-2005
|
5.50
|
Elevator prep
|
Details
|
|
|
07-17-2005
|
3.50
|
Elevator prep
|
Details
|
|
|
07-16-2005
|
3.00
|
Fabricated elevator stiffeners
|
Details
|
|
|
07-15-2005
|
1.50
|
Rudder finishing
|
Details
|
|
|
07-13-2005
|
2.50
|
Rudder trailing edge
|
Details
|
|
|
07-12-2005
|
1.50
|
Rudder assembly
|
Details
|
|
|
07-10-2005
|
6.50
|
Rudder assembly
|
Details
|
|
|
06-29-2005
|
3.00
|
Primed rudder, began riveting
|
Details
|
|
|
06-28-2005
|
1.00
|
Finished rudder prep work
|
Details
|
|
|
06-26-2005
|
0.50
|
Dimpled rudder rib holes
|
Details
|
|
|
06-25-2005
|
5.50
|
Rudder preparation
|
Details
|
|
|
06-22-2005
|
2.50
|
Rudder substructure
|
Details
|
|
|
06-19-2005
|
2.00
|
Back riveted rudder skins
|
Details
|
|
|
06-18-2005
|
8.00
|
Rudder components
|
Details
|
|
|
06-16-2005
|
1.00
|
Finished vertical stabilizer
|
Details
|
|
|
06-15-2005
|
2.00
|
Riveted skin on VS
|
Details
|
|
|
06-12-2005
|
7.00
|
Vertical spar assembly
|
Details
|
|
|
06-11-2005
|
3.50
|
Vertical stab prep work
|
Details
|
|
|
06-08-2005
|
3.00
|
Vertical spar prep work
|
Details
|
|
|
06-07-2005
|
1.00
|
HS finish work, VS plans study
|
Details
|
|
|
06-05-2005
|
7.00
|
Finished horizontal stab
|
Details
|
|
|
06-04-2005
|
7.00
|
Riveted front spar, left HS skin
|
Details
|
|
|
06-02-2005
|
1.00
|
Riveted hinge brackets to rear spar
|
Details
|
|
|
06-02-2005
|
1.00
|
Remove and replace rivets
|
Details
|
|
|
06-01-2005
|
3.50
|
Empennage priming, riveted rear spar
|
Details
|
|
|
05-14-2005
|
3.00
|
Finished fabricating right HS
|
Details
|
|
|
05-07-2005
|
6.00
|
Finished HS prep work
|
Details
|
|
|
05-05-2005
|
0.50
|
Dimpled substructure
|
|
|
|
05-04-2005
|
2.50
|
Horizontal stab prep work
|
Details
|
|
|
05-02-2005
|
0.50
|
Right horizontal stab preparation
|
Details
|
|
|
05-01-2005
|
3.50
|
Right horizontal stab assembly
|
Details
|
|
|
04-30-2005
|
7.00
|
Forward spar and eft HS assembly
|
Details
|
|
|
04-27-2005
|
3.50
|
Rear spar assembly
|
Details
|
|
|
04-23-2005
|
0.50
|
Finished workspace preparation
|
Details
|
|