Curran RV-9A

Builder:
Steve Curran
Location:
Woodland, CA - Yolo
Aircraft:
Vans Aircraft - RV-9A
Manufacturer:   
http://www.vansaircraft.com/
Engine:
-
Prop:
-
Total Build Time:
140 Hours

Welcome,

The empennage will be complete sometime in March of 2011. The wing kit is un-packed and ready to be built next. Our goal is to have the wings complete by the end of 2011 and plan on ordering the fuselage kit late this summer or early fall. We have found that working on the project more frequently keeps your skill level where it needs to be for faster and better quality building. Also, thank you to all the other builders before us for all of the useful information available on the internet. You will notice that we have elected not to primer. When the airplane is finished we will have the inside weather sealed.

Regards,
Steve Curran

Recent Activity
 Date Hours Work Log Summary Details
 02-20-2011
2.5
Right Elevator Riveting And Fitting.
Details
       

 02-19-2011
3.0
More Right Elevator Riveting.
Details
       

 02-18-2011
3.5
Rivet Right Elevator Skeleton.
Details
       

 02-18-2011
0.5
Rivet Leading Edge Of Rudder.
Details
       

 02-16-2011
1.0
Rolled Rudder Leading Edge.
Details
     

 02-11-2011
8.0
Rivet The Rudder Together.
Details
       

 02-10-2011
1.0
Right Elevator Counter Balance.
Details
     

 01-30-2011
1.0
Started Riveting Rudder.
Details
       

 01-28-2011
7.0
Rudder Work.
Details
       

 01-26-2011
1.0
Back Riveted Stiffeners To Left Rudder Skin.
Details
     